TABLE 14.--COST OF WATER-PROOFING, IN DOLLARS PER SQUARE FOOT.

=======================================+==========+===========+========

|Manhattan.| Weehawken.| Total.

---------------------------------------+----------+-----------+--------

Square feet covered | 47,042 | 13,964 | 60,736

---------------------------------------+----------+-----------+--------

Average cost per square foot.

---------------------------------------+----------+-----------+--------

Labor | $0.07 | $0.07 | $0.07

Material | 0.12 | 0.09 | 0.11

---------------------------------------+----------+-----------+--------

Total field charges | $0.19 | $0.16 | $0.18

Chief office and plant depreciation | 0.01 | 0.03 | 0.02

---------------------------------------+----------+-----------+--------

Total average cost | $0.20 | $0.19 | $0.20

=======================================+==========+===========+========

_Brickwork in Arches._--Owing to the heavy timbering, the brickwork at

Manhattan was interfered with to a considerable extent, and the gang was

always kept at work at two or more places. The work was carried up to a

point where it was necessary to back-fill, or prop or cut away

encroaching timbers, and then the men were moved to another place while

this was being done.

The centers were set up in sets of seven, spaced 4 ft. apart. Two

14-ft. lengths of 3 by 4-in. yellow pine lagging were used with each set

of ribs, with 24 by 8-in. block lagging in the crown.

All centers were set ¼ in. high, to allow for settlement, except in

the 24-ft. 6-in. span, in which they were set ½ in. high. This proved

ample, the average settlement of the ribs being 0.01 ft. and of the

masonry, 0.003 ft. In the 24-ft. 6-in. span the ribs were strengthened

with 6 by 6-in. blocking and 12 by 12-in. posts to subgrade. Great

trouble was here encountered with encroaching timbering, due to the

settlement of the wide flat span. Grout pipes were built in, as

previously mentioned.

Each mason laid an average of 0.535 cu. yd. of brickwork per hour, or

4.28 cu. yd. per day. The number of bricks laid per mason per hour was

218, or 1,744 per day.

The bricks were of the best quality of vitrified paving brick, and were

obtained from the Jamestown Brick Company, of Jamestown, N. Y. The

average size was 8¾ by 3-15/16 by 2-7/16 in.; the average number per

cubic yard of masonry was 408, the arches being from 19 ft. to 24 ft. 6

in. in span and from 22 to 27 in. thick. The joints were 3/16 in. at the

face and averaged 9/16 in. through the arch.

The proportions for mortar were 1 of cement and 2½ of sand. One cubic

yard of masonry was composed of 73.5% brick and 26.5% mortar. The volume

of the ingredients in a four-bag batch was 12.12 cu. ft., and the

resulting mixture was 9.54 cu. ft. The number of barrels of cement was

0.915 per cu. yd. of masonry, and about 17.7% of the mortar made was

wasted. The average force employed was:

_Laying._

1 Foreman @ $8.00 per day

4 Layers " 6.00 " "

8 Tenders " 2.00 " "

2 Mixers " 2.00 " "

_Forms._

1 Foreman @ $4.50 per day

4 Carpenters " 3.50 " "

5 Helpers " 2.25 " "

_Transport._

¼ Hoist engineer @ $3.00 per day

¼ Signalman " 2.00 " "

4 Laborers " 2.00 " "

For materials, the following prices prevailed:

Cement, $2.00 per bbl.,

Sand, $0.90 to $1.00 per cu. yd.,

Brick, $16.00 per thousand, delivered at yard,

Centers, $26.00 each,

Lagging, $45.00 per 1,000 ft. B. M.

The cost of the brickwork is given in Table 15.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 17 / 55 题