LAND TUNNELS.

General.

The following is a brief account of the main features of the "Land

Tunnel" work, by which is meant all the part of the structure built

without using tunneling shields.

The Land Tunnels consist of about 977 ft. of double tunnel on the New

York side and 230 ft. on the New Jersey side, or a total of 1,207 lin.

ft. of double tunnel.

The general design of the cross-section consists of a semi-circular

arch, vertical side-walls and a flat invert. The tunnel is adapted for

two lines of track, each being contained in its compartment or tunnel.

The span of the arch is wider than is absolutely necessary to take the

rolling stock, and the extra space is utilized by the provision of a

sidewalk or "bench" forming by its upper surface a gangway, out of the

way of traffic, for persons walking in the tunnels, and embedded in its

mass are a number of vitrified earthenware ducts, for high-and

low-tension electric cables. The provision of this bench enables its

vertical wall to be brought much nearer to the side of the rolling stock

than is usually possible, thus minimizing the effects of a derailment or

other accident. Refuge niches for trackmen, and ladders to the top of

the bench are provided at frequent intervals. In cases where a narrow

street limits the width of the structure, as on the New York side, the

two tunnels are separated by a medial wall of masonry, thus involving

excavation over the entire width of both tunnels, and in such case the

tunnels are spoken of as "Twin Tunnels"; where the exigencies of width

are not so severe, the two tunnels are entirely distinct, and are

separated by a wall of rock. This type is found on the Weehawken side.

The arches are of brick, the remainder of the tunnel lining being of

concrete.

New York Land Tunnels.

The work on the Land Tunnels on the Manhattan side was carried on from

the shaft at 11th Avenue and 32d Street.

The plans and designs for these tunnels are shown on Plate XXXII. In

this short length of about 977 ft. there are no less than nine different

kinds of cross-section. The reason for these changes is the fact that

the two lines of track are here not straight and parallel to the center

line between the tunnels, but are curved, although symmetrical about

this center line. The various changes of section are to enable the

tunnels to be built in straight lengths, thus avoiding the disadvantages

attending the use of curved forms, and at the same time minimizing the

quantity of excavation, an item which accounts for from 60 to 70% of the

total cost of tunnels of this type. Of course, there are corresponding

and obvious disadvantages in the adoption of many short lengths of

different cross-sections, and these disadvantages were well brought out

in the course of the work; on the whole, however, they may be said to

have justified their adoption. These New York Land Tunnels were divided

into three contracts, viz.: From Station 190 + 15 (the Portal to the

open work of the Terminal Station at the east side of Tenth Avenue, New

York City) to Station 197 + 60, called "Section Gy-East." The next

contract, called "Section Gy-West Supplementary," extended from Station

197 + 60 to Station 199 + 20, which is the east side of Eleventh Avenue.

The third contract was called "Section Gy-West," and extended from

Station 199 + 20 to Station 231 + 78 (the dividing line between the

States of New York and New Jersey). Thus, for nearly all its length,

this contract consists of shield-driven tunnel. The portion between

Stations 199 + 20 and 199 + 91.5, however, was of the Land Tunnel type,

and therefore will be included here. A fourth contract extended from

Station 231 + 78 to the Weehawken Shaft at Station 263 + 50, and of this

all but 230 ft. was of the shield-driven type, only the portion next to

the Weehawken Shaft being of the Land Tunnel type.

The four contracts were let to one contractor (The O'Rourke Engineering

Construction Company), and the work was carried on simultaneously in all

four, so that the division into contracts had no bearing on the methods

of work adopted, and these will now be described as a whole and with no

further reference to the different sections.

Excavation.

Work was started on the New York side on April 18th, 1904, the Weehawken

shaft being at that date still under construction. As will have been

noted in the description of the shafts, the contractor found a shaft

already prepared for his use, and cross-drifts at grade and at right

angles to the future tunnels, and extending across their entire width.

The first essential was to get access to the shield chambers, which were

to lie about 330 ft. to the west of the shaft, so that the construction

of these enlargements in which the shields for the subaqueous tunnels

were to be built might be finished as soon as possible and thus allow

the earliest possible start to be made with the shield-driven tunnels.

With this in view, two bottom headings, on the center line of each of

the two tracks, were driven westward from the western cross-heading at

the foot of the shaft. When about 138 ft. had been made in this way,

the two headings were brought together and a break-up was made to the

crown level of the tunnel, as the depth of rock cover was doubtful. From

this break-up a top heading was driven westward to Station 200 + 30.

While widening the heading out at Station 200 + 20 the rock was

penetrated on the south side. The exposed wet sand and gravel started to

run, and, as a consequence, a change in design was made, the shield

chambers (and consequently the start of the shield-driven tunnels) being

moved eastward from their original location 133 ft. to their present

location. A certain amount of time was necessarily spent in making these

changes of design, which involved a rearrangement of the whole layout

from the Terminal Station to the start of the River Tunnels. On July

5th, 1904, however, the new design was formally approved. No sooner had

this been decided than a strike arose on the work, and this was not

settled until August 1st, 1904, but from that time the work progressed

without delay. No further reference will be made to the work in the

shield chambers, as that will come under the heading of "River Tunnels,"

being of the segmental, cast-iron lined type.

A top heading was now driven over the original bottom heading west of

the shaft, and at the same time the original cross-drifts from the shaft

were amalgamated with and broken down by a heading driven at the crown

level of the "Intercepting Arch" which here cuts across the ordinary run

of tunnel at right angles and affords access to the tunnels from the

shafts.

The excavation of the upper portion of the intercepting arch at its

southern end gave some trouble, and caused some anxiety, as the rock

cover was penetrated and the wet sand and gravel were exposed. This made

it necessary to timber all this section heavily, and the tracks of the

New York Central Railroad directly above were successfully supported.

The general way in which this timbering was carried out will be

described under the head of "Timbering."

Meanwhile, the excavation of the tunnels west of the intercepting arch

was continued until the North and South Tunnels were taken out to their

full outlines, leaving a core of rock between them. This core was

gradually removed, and timbering supporting the rock above the middle

wall was put in as excavation went on. The ground, which was entirely of

micaceous schist, typical of this part of Manhattan, seamed with veins

of granite, was rather heavy at the west end, or adjacent to the shield

chambers, and required complete segmental timbering across the whole

span. One heavy fall of rock in the corewall between the North and South

Tunnels took place on November 2d, but fortunately did not extend beyond

the limits of the permanent work. On November 7th, 1904, the excavation

east of the intercepting arch was begun by driving a bottom heading in

the South Tunnel. This was continued to Station 197 + 14 and then was

taken up to the crown level and worked as a top heading with the view of

keeping track, by making exploratory borings upward from the roof at

frequent intervals, of the rock surface, which was here irregular and

not known with any degree of certainty. The work was not pressed with

any vigor, because all efforts were then being bent toward excavating

from the River Tunnels as much rock as possible. In Section Gy-East the

conditions were exceptionally variable, as the rock was subject to

sudden changes from a soft crumbling mica schist to broad bands of hard

granite, and, in addition, the rock surface was very irregular, and, for

a good length of this section, was below the crown of the tunnel, a

condition which led to the adoption of the cut-and-cover method for part

of the work.

The irregularity in conditions called for varying methods of procedure,

but in general the methods were as shown on Plate XXXIII, and described

as follows:

_In Solid Rock._--Where there was plenty of good rock cover, a top

middle heading was driven, which was afterward widened out to the full

cross-section of the twin tunnel arches. If necessary, a few lengths of

segmental timbering were put in before taking down the bench, which was

generally kept some 40 or 50 ft. behind the breast of the heading. After

the bench was down, the middle conduit trench was excavated and the

trimming done.

_In Soft Rock._--Where there was not enough rock cover, or where there

was actual soft ground in the roof, wall-plate headings at the springing

line level were driven ahead of the remainder of the work. The

wall-plates were laid in these, the roof was taken out in short lengths,

and segmental timbering spanning from wall-plate to wall-plate was put

in. The roof being thus held, the bench excavation proceeded without

trouble. Where the rock was penetrated and soft ground showed in the

roof, poling boards were driven ahead over the crown-bars, as shown in

Fig. 4.

_Cut-and-Cover Work._--After some 225 ft. had been driven from the

intercepting arch, it was found that the crown of the tunnel was

continually in soft ground. To ascertain the extent of this condition

the contractor decided to make soundings as far as Tenth Avenue, which

was done by sinking trial pits and making wash-borings in the street.

These soundings showed that there would be soft ground in the crown from

Station 194 + 75 to Station 194 + 25 (at one point to a depth of 12 ft.

below the crown), and on each side of this section the cover was

insufficient from Station 193 + 58 to Station 195 + 30. This condition

being known, it was decided to adopt cut-and-cover work for this length,

the principal reasons being that repairs to sewers, streets, and drains

would be no more, and probably less, expensive than with the tunnel

method; the underpinning of a heavy brick brewery building adjoining the

works on the north side would be facilitated, and the opening in the

street, through which muck and materials could be handled, would relieve

the congested shaft, through which the large volume of muck from the

River Tunnels was then being conveyed. On the other hand, the

cut-and-cover method was adversely affected by the presence of a heavy

timber trestle built down the south side of the street and over which

passed all the excavation from the Terminal Station, amounting to a very

heavy traffic. As this trestle had to be supported, it complicated the

situation considerably. Very little active progress was made between

June, 1905, and April, 1906, as the contractor's energies during that

time were much taken up with the progress of the shield-driven tunnels.

In April, 1906, preparations were made to start a 50-ft. length of open

cut, rangers being fixed and sheathing driven; and the sewer which ran

down the middle of this street was diverted to the outside of the

open-cut length.

April and May were occupied in driving the sheathing down to rock,

supporting the trestle, underpinning the adjoining brewery, and

excavating the soft material above the rock. On June 2d, 1906, rock was

reached, and, by July 31st, the excavation was down to subgrade over

nearly the whole 50 ft. in the first length. In the meantime another

length was opened up, and eventually a third.

The surface of the rock now seemed to be rising, and the heavy buildings

had been passed, so that tunneling was reverted to for the rest of the

work, though many difficulties were caused by soft rock in the roof from

time to time.

[Illustration: METHOD OF DRIVING ROOF LAGGING IN SOFT GROUND. FIG. 4.]

When the excavation for the open-cut work of the Terminal Station had

advanced to the line of Tenth Avenue, the contractor started a heading

from this point and drove westward under Tenth Avenue until the headings

driven eastward from the cut-and-cover portion, were met.

This was done to expedite the work under Tenth Avenue, where the ground

was not very good, where there were several important gas and water

mains in the street, and where, moreover, the tunnels were of

exceptionally large span (24 ft. 6 in.), making a total width of some 60

ft. for the excavation. The excavation for the New York Tunnels was

practically finished in January, 1908.

_Drilling and Blasting._--The foregoing short description will serve to

show in a general way the scheme adopted in making the excavation. A few

details on drilling and blasting methods may not be out of place.

Percussive drills run by air pressure were used. They were

Ingersoll-Sergeant, Nos. 3½, A-86, C-24, and F-24. The air came from

the high-pressure compressor previously described. This compressor,

without assistance, could supply air for nine drills, but, when fed by

compressed air from the lower pressure, its capacity was increased three

or four times.

The air was compressed to 100 lb. per sq. in. in the power-house, and

was delivered at about 80 lb. per sq. in. at the drills. A 3-in. air

line was used. The drill steel was 1-1/8-to 1-3/8-in. octagonal. The

holes were about 3¼ in. in diameter at starting and 2-5/8 in. at the

full depth of 10 ft. The powder used on the New York side was 40%

Forcite, the near presence of heavy buildings and lack of much rock

cover necessitating light charges and many holes spaced close together.

To compensate the contractor for the inevitable excavation done outside

the neat lines of the masonry lining, the excavation was paid for to the

"Standard Section Line" which was 12 in. outside the neat lines on top

and sides and 6 in. outside at the bottom of the cross-section. The

actual amount of excavation done was about 11% greater than that paid

for. The distance excavated beyond the neat line, because of the very

heavy timbering necessary, was about 2.1 ft. instead of the 1 ft.

allowed, and at the bottom about 0.85 ft. instead of the 0.50 ft. paid

for.

For a period of 5 months detailed records were kept of the drilling and

blasting. About 12,900 cu. yd. of excavation are included. A sketch and

table showing the method of driving the heading, the number and location

of the holes drilled, and the amount of powder used, is given in Fig. 5.

From this and similar figures the information in Table 5 is derived.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 12 / 55 题