CHAPTER IX

STORM AND SANITARY DRAINAGE WITH SEWAGE DISPOSAL IN VIEW

The accompanying drawing of storm and sanitary drains should be

studied in detail by the reader. The location of each trap and

fitting should be studied carefully and the reason that it is put

in that particular place should be thoroughly understood. Below,

each plan has been taken and gone over in detail, bringing out the

reasons for fittings and traps, also the arrangement of the piping.

[Illustration: FIG. 46.]

The first thing to note in Fig. 46 is the number and kinds of

fixtures to be drained. There is in the basement a set of

three-part wash trays. This will require a 2-inch waste and a

1-1/2-inch vent. There is in the drawing a 2-inch waste extending

to the fixtures above. On the same line is a rain leader with a

trap showing also a 4-inch floor drain. There are two 4-inch rain

leaders on the opposite corners of the plan, in the rear of the

building. There is a 4-inch soil stack for fixtures above and a

4-inch soil stack in the basement on the same line for a basement

toilet. On the front there are rain leaders in each corner. These

will be connected outside of the house trap (this feature should be

noted). The outlets that are to discharge into the house drain are

as follows:

Two 4-inch rain leaders.

One 2-inch sink waste.

One 2-inch wash tray waste.

One 4-inch floor drain.

One 4-inch soil pipe.

One 4-inch closet connection.

Two 4-inch front rain leaders to discharge into house

sewer.

If we were to install this job, we would first locate each pipe

that enters the house drain. The lowest outlet would be

particularly noted, in this case the 4-inch floor drain. From this

drain we must make sure that at least 1/4 inch to the foot fall is

secured. We must then locate the house sewer where it enters the

foundation wall, then the work can be started. I will not attempt

to list the material that is necessary for this work, at this time.

With all the material at hand the house drain is started. All of

this work is installed under the ground, therefore trenches must be

dug for all the piping. The plumber must lay these trenches out and

in doing so he must have in mind all connections and the fittings

he can use so that the trenches can be dug at the right angle. The

trenches must be dug allowing a pitch for the pipe. The height of

the cellar is 8 feet below the joists. A stick is cut 8 feet long

which can be used to get the trenches below the cement floor at the

right depth. After the digging is completed, the house trap, which

is a 6-inch running trap, is caulked into a length of 6-inch

cast-iron pipe. This piece of pipe is pushed out toward the sewer

bringing the trap near the foundation wall, on the inside. The

fittings and traps and pipe are caulked in place as fast as

possible. When possible, the joints are caulked outside of the

trench in an upright position. There are a number of different ways

to caulk this pipe together, and to make it clear to the beginner

just how it is done the following exercise is suggested. This job

brings in the caulking of pipes, traps, and fittings in various

positions. Two or three can work on this job together. Fig. 47

shows how the pipe and fittings are put together, which needs no

further explanation. Therefore, we will go over in detail only the

caulking of the joints in the various positions.

[Illustration: FIG. 47.]

MATERIAL NEEDED.--One length of 4-inch extra heavy cast-iron pipe,

single hub; two lengths of 4-inch extra heavy cast-iron pipe,

double hub; one running trap, one full Y, one 4-inch 1/4 bend; two

4-inch clean-out screws with iron body; one 4-inch vent cap; one

4-inch 1/8 bend; 30 pounds of block lead; 2 pounds of oakum.

TOOLS REQUIRED.--Ladle, asbestos pourer, hammer, cold chisel,

yarning iron, two caulking irons, furnace and pot.

The beginner should start at the trap and caulk the joints with the

trap held in place. The cold chisel should be sharp as it is used

to cut the cast-iron pipe.

To caulk the straight end of cast-iron pipe into the hub end and

make a water-tight joint when the pipe is in a vertical position,

the spigot end of the pipe is entered into the hub end of another

piece. A wad of oakum is taken and forced into the hub with the

yarning iron. This piece of oakum is forced to the bottom of the

hub, then another piece is put in. The oakum is set and packed by

using the yarning iron and hammer. The hub is half filled with

oakum. The oakum is forced tight enough to make a water-tight

joint. If the oakum used comes in a bale, pieces of it will have to

be taken and rolled into long ropes about 18 inches long, the

thickness of the rope corresponding with the space between the hub

and the pipe. If rope oakum is used, the strands of the rope can be

used. After the oakum is well packed into place and the pipe is

lined up and made straight, molten lead is poured in and the hub

filled. When the lead has cooled, set the lead with the caulking

tool and hammer, making one blow on each side of the joint. This

sets the lead evenly on every side. If there is any surplus lead,

it can now be cut off, using the hammer and cold chisel. The

caulking iron is again taken and the lead next to the pipe is

tamped, striking the iron with the hammer at an angle to drive the

lead against the pipe. After this has been done all around, the

caulking iron is held in such a position that the lead around the

hub will receive the force of the blow. After this has been done,

the center of the lead is caulked and the joint should be tight.

With a little practice, this can be done very rapidly. The lead

should be poured in while it is very hot. The caulking must not be

done by hitting heavy blows as there is a possibility of splitting

the hub and thereby rendering the joint unfit for use.

CAULKING JOINT IN HORIZONTAL POSITION.--It is necessary in a great

many cases to caulk a joint in a position where the lead would run

out of the joint unless provision were made to hold it in. To

caulk a joint in a position of this kind, the pipe is lined up and

secured, then the oakum is put in and forced to the bottom of the

hub. Then a joint runner, which is an asbestos rope about 2 feet

long and about 1 inch in diameter, is fitted around the pipe and

forced against the hub where it is clamped by means of an attached

clamp. The clamp is put on the top of the pipe and so arranged that

a channel will be left in a V shape. This channel allows the hot

lead to run between the asbestos runner and the hub. When the lead

has had a chance to cool, the asbestos runner is taken off. Where

the clamp was, there will be a triangular piece of lead sticking

out beyond the face of the hub. This piece has to be cut off, but

no attempt should be made to do so until it has been caulked in

place and well set; also the rest of the lead should be set. Then

the cold chisel can be used and this extra piece of lead taken off.

The caulking of the lead in this position is the same as in the

previous position and should be carried out closely. The beginner

should understand that it is necessary to have not only the joints

tight so that running water will not leak out of them, but that the

joints must stand a water test. The testing of soil stacks is

explained under another heading. The lines of cast-iron pipe depend

to a considerable extent upon these joints to make the whole line

rigid.

CAULKING OF FITTINGS.--The caulking of fittings, while done the

same as a straight pipe, is far more difficult. The improper making

of these joints is the cause of many leaks. A long sweep fitting is

caulked without a great deal of difficulty. If a short bend fitting

is used, the matter of caulking is difficult. The fitting is so

short that it is almost impossible to get a caulking iron into the

throat. The mechanics will have to work at the throat from each

side until this part has been sufficiently caulked. I call

attention to this point, for I know it to be a failure in a large

number of jobs when it comes to put the test on. In order to caulk

the fittings, they must be put in their exact location and

positions before the lead is poured in, for after the lead is once

in the fitting cannot be moved. When there is a series of fittings

on a line, their positions in relation to each other must be

considered before the lead is poured.

[Illustration: FIG. 48.]

[Illustration: FIG. 49.]

[Illustration: FIG. 50.]

[Illustration: FIG. 51.]

Fig. 48 shows the same fixture and stack connections as Fig. 46.

Two 4-inch lines run through the cellar, one a sanitary drain, the

other a storm drain. Each 4-inch line has an intercepting trap. On

the sewer side of these traps the two lines are brought together,

beyond which point the two front rain leaders connect; each of the

two front leaders is trapped separately.

[Illustration: FIG. 52.]

Fig. 49 differs from the preceding one in only two points. First,

the two front leaders are brought into the cellar and connected

into the storm drain on the house side of the intercepting trap.

Second, the storm and sanitary drains are connected on the outside

of the building.

Fig. 50 shows the same fixtures collected into a 4-inch house

drain, and the rain leaders run entirely on the outside of the

building. This plan is a good one as all the storm water is kept

entirely outside the building. If the storm drains are kept 5 feet

away from the cellar walls (see Plumbing Code) the pipes can be of

tile. Another good feature of this plan is that all the pipes under

the cellar are 4-inch.

Fig. 51 is similar to Fig. 46, the difference being in the location

of the floor drain and the connection of the two rear rain leaders,

into the house drain.

In Fig. 52 the drains shown take the waste and storm water from the

apartment building, also a building set in the rear. The leader

pipes in this case are trapped on the outside of the wall. The

building in the rear you will note has a separate fresh air inlet

and house trap, and the house sewer is continued through the front

house and connected into the house drain of the front building, on

the sewer side of the intercepting trap.

These drawings should be studied carefully and the student should

in each case list correctly all of the material required for the

installation of these jobs.

[Illustration: FIG. 53.--Cutting cast-iron pipe.]

CUTTING CAST-IRON PIPE.--To cut cast-iron pipe, a sharp cold chisel

and hammer are needed. The pipe is marked all around, just where it

is to be cut. Then it is laid with the part of the pipe that is to

be cut resting on a block of wood. A groove is cut with the hammer

and chisel around the pipe. One person can turn the pipe while the

other does the cutting. After a little experience one man can cut

and roll the pipe alone. This groove is cut deeper and deeper until

the pipe breaks apart. If standard pipe is being cut, a file is

generally resorted to for cutting the groove. On account of the

lightness of the pipe, a hammer and chisel will crack the pipe

lengthwise. When cutting extra heavy cast-iron pipe, a good heavy

blow must be struck to cause the chisel to cut into the iron. After

a few cuts, the beginner will understand the weight of blow that

must be struck to cut the pipe quickly.

Elements of Plumbing · 第 9 / 18 章