Plate VI. is a view of an entrance ventilator; this stands on one side

of the Aqueduct, where the masonry of the side wall is enlarged for

its base; we can descend from the door and gain an entrance to the

channel-way by an opening in the side of the roofing arch. The sill of

the door is about 12 feet above the bottom of the channel-way.

[Illustration: VI

_F. B. Tower._ _Gimber._

ENTRANCE VENTILATOR]

Those not intended for an entrance stand directly over the top of the

Aqueduct and are groined into the roofing arch.

Besides these Ventilators, there are openings 2 feet square in the top

of the roofing arch, every quarter of a mile: they are covered with a

flag stone and the place is marked by a small stone monument projecting

above the surface of the ground. These may be useful to obtain entrance

to the Aqueduct, or to afford increased ventilation should it ever

become necessary.

CULVERTS.

Where streams intersect the line of Aqueduct, culverts are built to

allow them to pass under it. They are simply a stone channel-way built

under the Aqueduct of such form and dimensions as will allow the stream

to pursue its natural direction without causing injury to the work. The

foundation of these culverts is formed by laying down concrete, upon

which an inverted arch of cut stone is laid forming the bottom of the

water-way: side walls of stone are built and surmounted by an arch of

stone. The span, or width of water way, of the culverts built, varies

from 1½ foot to 25 feet. Those of 1½ foot span have a square form for

the water-way, and are constructed by making a foundation of concrete,

upon which a flooring of well dressed stone is laid forming the bottom

of the water-way, and from this, side walls are built and covered by a

course of thick stone flagging well dressed and closely fitted. At each

end of the culvert a deep wall is built underneath so as to prevent

the water from doing injury by undermining it. Buttresses and wing

walls are built at each end of the culvert to guide the water to and

from the channel-way, and a parapet wall is built over the top of the

channel-way at each end to sustain the embankment of earth over the

culvert. These wing walls and parapets have various forms; sometimes

the parapet is built across the top of the culvert, and the wing walls

built at right angles to it, and sloping down to the buttresses, and

sometimes the wing walls and parapet form one continuous wall of a

semi-circular form, the top sloping up from the buttresses in a plane

parallel with the slope of the embankment covering the Aqueduct above.

These culverts are permanently constructed, and in preparing the plans

for them much skill has been displayed in adapting the form and size

which the circumstances required, and much taste displayed in the

design for their construction.

Plate VII. is an isometrical drawing of one of the culverts with

rectangular wings and parapets; the body of the culvert is cut in two

in the drawing, showing that it may be of any length, according to the

width of the embankment through which it is constructed. The length is

generally arranged so that the slope of the embankment may intersect

the rear of the top of the parapet and pursue a direction down,

parallel with the slope of the top of the wing walls.

[Illustration: VII

Scale of 4 feet to one inch

_F. B. Tower._ _Gimber._

]

_Gate Chamber at the Head of the Aqueduct and Grade of the Water-way of

the Aqueduct._

Plate VIII. is a longitudinal section through the _tunnel_ and _gate

chamber_ at the head of the Aqueduct showing its connection with the

_Fountain Reservoir_. This gate chamber is not in any way connected

with the dam itself, but stands some distance from it, and the water

reaches it by means of the tunnel which leaves the Reservoir above the

dam and passes through the solid rock of the hill against which the

masonry of the dam is built, a distance of over 200 feet. This tunnel

descends into the Reservoir, so that the centre of it at the mouth is

about 12 feet below the surface of the water; any floating substance

cannot enter it, and during the winter season when the water is frozen

over no obstruction can take place to the flow into the Aqueduct, and

during the summer season the water will be drawn from a level where it

is cooler than at the surface.

The gate chamber has two ranges, or sets of gates; one called

_regulating gates_, and the other _guard gates_: the regulating gates

are made of gun metal, and work in frames of the same material which

are fitted to stone jambs and lintels: the guard gates are made of

cast iron, and work in cast iron frames also attached to stone jambs

and lintels. The gates are all managed by means of wrought iron rods

attached to them, having a screw formed on the upper part on which a

brass nut works, being set in a cast iron socket-cap.

The bottom of the water way, of the Aqueduct, where it leaves the gate

chamber is 11.40 feet below the surface of the Fountain Reservoir, and

154.77 feet above the level of mean tide at the city of New-York. The

following table shows the length of the Aqueduct as it is divided into

different planes of descent, from the gate chamber at the Croton dam to

the gate chamber at the Receiving Reservoir on the Island of New-York.

Commencing at the south side of the gate chamber at the Croton dam,

and the

ft. miles, descent

The 1st plane of Aqueduct extends 26099.72 = 4.943, 2.94 ft.

The 2d plane of  Aqueduct extends 148121.25 = 28.053, 30.69 ft.

Length of pipes across Har. River, 1377.33 = 0.261.

Diff. of level betw’n extremes of pipes 2.29 ft.

The 3d plane of Aqueduct extends 10733.14 = 2.033, 2.25 ft.

Length of pipes across Manhat. valley, 4105.09 = 0.777.

Diff. of level betw’n extremes of pipes 3.86 ft.

The 4th plane of Aqueduct extends 10680.89 = 2.023 1.60 ft.

--------- ------ ---------

201117.42 = 38.090 43.63 ft.

Making the whole distance from the gate chamber at the Croton dam to

the gate chamber at the Receiving Reservoir 201117.42 feet, or 38.09

miles, and the whole descent 43.63 feet.

The descent on the first plane is about 7⅛ inches per mile.

The descent on the second and third plane is about 13¼ inches per mile.

The descent on the fourth plane is about 9½ inches per mile.

In crossing Harlem River there is a fall of 2 feet more than there

would have been had the Aqueduct continued across with its regular

inclination: this _extra_ fall will afford an opportunity to adjust the

number and capacity of the pipes (which descend below the level of the

Aqueduct and rise again) to discharge the full quantity of water as

freely as the Aqueduct, or channel-way of masonry, would have done had

it continued its regular inclination across the valley.

In crossing Manhattan Valley there is an _extra_ fall of 3 feet for the

same reasons as before stated for that at Harlem River. In both cases,

by using the pipes, there is a loss of the head of water for the City

Reservoirs, equal to the amount of this _extra_ fall; but this small

loss of head was not considered of such importance as to induce the

building of structures across these valleys up to the plane of Aqueduct

grade.

[Illustration: VIII

_F. B. Tower._ _Gimber._

]

The bottom of the water-way of the Aqueduct at the gate chamber where

it enters the Receiving Reservoir, is 7.86 feet below the level of

top water line in the Reservoir, thus when the Reservoir is full the

water will rise to within 7¼ inches of the top of the interior of

the Aqueduct at that place, and the height from top water to the

top of the interior will increase, going northward according to the

inclination of the plane of Aqueduct grade, until it reach the surface

level of the flow of water in the Aqueduct.

The height of the interior of the Aqueduct is 8 feet 5½ inches, and the

greatest width is 7 feet 5 inches. The sectional area of the interior

is 53.34 square feet. On the _first plane_, the Aqueduct is larger;

being 2.05 feet higher at the gate chamber, 2.31 feet higher at 2244.

feet from the chamber, and then diminishing, to the head of the second

plane, where it assumes the size above mentioned and continues of that

size throughout the remainder except in tunnels, where it assumes the

forms before described. Where the Aqueduct on the _first plane_ is

larger, the width across the interior at the spring line of the roofing

arch is the same as the general width, but the increase takes place

only in the height of the side walls, and the slope of the inner face

of the walls being the same, the width across at the spring line of the

inverted arch will be less according to the increased height of walls.

The original design was to continue the inclination which the _second

plane_ has, up to the _Fountain Reservoir_; but it was considered

desirable to draw from this Reservoir at a lower level, and the head

of the Aqueduct was depressed for that purpose, and a less inclination

adopted for the length of the _first plane_. The roofing arch was left

on the same inclination as was originally designed, except for the

distance of 2244. feet from the gate chamber, where it was built on a

level.

The curves which are used to change the direction of the line of the

Aqueduct are generally formed with a radius of 500 feet; some have a

radius of 1000 feet, and in a few instances larger ones are adopted,

but the majority of them are of 500 feet radius.

The velocity of the water in the Aqueduct has been ascertained to be

about one mile and a half an hour when it is 2 feet deep; this was

determined by floating _billets_ of wood from the Croton Dam to Harlem

River and noting the time of their passage. Such an experiment would

express the surface velocity and would give a greater velocity than

it would be proper to attribute to the _whole body_ of water in the

Aqueduct; but the depth of water in the Aqueduct will be probably 4

feet as soon as it is brought into general use, and then there will be

a corresponding increase in the velocity of the _body_ of water. This

velocity of a _mile and a half an hour_ may be taken in general terms

as the _velocity of the water in the Aqueduct_.

[Illustration: IX

_F. B. Tower._ _W. Bennett._

VIEW ABOVE THE CROTON DAM.]

DESCRIPTION OF THE LINE OF AQUEDUCT.

The dam, built to form the Fountain Reservoir, is about six miles above

the mouth of the Croton River. The reservoir forms a beautiful sheet of

water in the lap of the hills in the wild region of the Croton, and has

received the name of the “Croton Lake.”

Pine’s Bridge over the Croton River, which is mentioned in the early

history of the country, occupied a position which is now about the

middle of this Reservoir, and there is at that place a bridge over the

Reservoir resting upon piers and abutments.

The hills which bound the Croton Valley where the Reservoir is formed

are so bold as to confine it within narrow limits: for about two miles

above the dam the average width is about one eighth of a mile; at this

distance from the dam the valley opens so that for the length of two

miles more the width is about a quarter of a mile; here the valley

contracts again and diminishes the width until the flow line reaches

the natural width of the River at the head of the lake. The country

immediately contiguous to the shore has been cleared up, and all that

would be liable to impart any impurity to the water has been removed.

This gives a pleasing aspect to the lake, showing where the hand of

art has swept along the shores leaving a clean margin. Retiring from

the water are the richly cultivated slopes with the neat farm houses

overlooking the lake, or the hills crowned with forest trees, while at

intervals a valley or ravine opens and empties in its tributary stream.

Plate IX. is a view taken above the dam showing the position of the

entrance to the tunnel which leads from the Reservoir to the gate

chamber at the head of the Aqueduct. The entablature which is seen on

the left against the rock, is built directly over the mouth of the

tunnel, and from this the tunnel extends through the rock to the gate

house, which is seen on the right of the picture and some distance from

the dam. The structure which is seen in the centre of the picture and

on the ridge of the dam is a gate house over a culvert which extends

through the body of the dam; this culvert is 30 feet below the surface

of water when the Reservoir is full, and has gates which are operated

by means of rods which rise to the interior of the house. During low

stages of the River the water which is not drawn off by the Aqueduct

may pass through this culvert and allow none to pass over the dam.

The entrance to the tunnel is protected by a screen of timber work.

Plate X. is a representation of the entablature over the mouth of the

tunnel, showing the inscriptions upon it, relating to the date of

the commencement of the dam and its completion, the persons who had

contracts for building it, and those having charge of the work during

the time.

[Illustration: X

ENTRANCE TO THE CROTON AQUEDUCT

COMMENCED 1837

COMPLETED 1842

]

Plate XI. is a view taken from a point below the dam and shows the

relative positions of the dam and the gate chamber at the head of the

Aqueduct.

The original channel of the River where the dam is built, was about

120 feet wide; the average depth of water at this place was about 4

feet; and the greatest depth 10 feet.

The left bank of the river arose abruptly with rock, the channel was

gravelly, and on the right bank a sandy table land about 3 feet above

the ordinary surface of water extended about 80 feet; then a sandy hill

arose on a slope of about forty-five degrees.

In making the plan for a dam at this place it was determined to

fill the main channel and the table land on the right bank with an

embankment of earth; and on the left bank where rock was found, to

build a body of masonry against the slope to the requisite height for

the surface of the Reservoir and connect it with the embankment in

the channel; this masonry formed the overfall for the water, and the

rock in the side of the hill adjacent to it was excavated down to the

level of the overfall, thereby extending it into the hill, making the

space for the water to pass over partly of masonry and partly of rock.

The embankment extended with a slope on the upstream side giving it a

broad base, and the lower or downstream side was faced with a heavy

wall of stone. There was a timber pier constructed in the embankment

extending across the channel and faced with plank on the upstream side.

The overfall was made of such length as was thought sufficient to pass

all the water of the river during its highest stages, and with the view

of adapting it to such purpose, examinations were made to find the

highest marks of floods on the banks of the river; and those who were

engaged in determining these marks were guided also by the observations

of the inhabitants of the vicinity who had long known the river in its

various stages. High freshets were witnessed during the construction

of the work, for in the course of two years that the work was going up,

all the various changes and freshets of rainy seasons were experienced,

and those in charge of it did not neglect to note the quantity of water

flowing on such occasions.

[Illustration: XI

_F. B. Tower._ _Gimbrede. sc._

VIEW BELOW THE CROTON DAM.]

With such opportunities to become acquainted with the changes of the

stream they could not fail to know the quantity of water flowing at

periods of the highest freshets, and knowing it, to adapt an overfall

of sufficient capacity for its discharge. For this purpose it was

thought ample provision was made; yet at the time when the work

was nearly completed such a flood occurred as could not have been

anticipated from previous knowledge of the River; the water filling the

entire passage at the overfall, flowed over the top of the embankment

where it was not supposed it could ever reach. The lower slope of this

embankment was covered with a wall not calculated to resist the action

of the water and it gave way; the water broke through the embankment

and rushed along the valley with most disastrous consequences. The

breach occurred at an early hour in the morning; and many persons were

suddenly aroused from their sleep to escape before the approaching

waters. Dwelling-houses and mills were carried away and three lives

were lost. Two of those who were drowned had taken refuge in the tops

of trees, but these being swept away they were drowned; while others

who were not able to reach the main land, but had also taken refuge in

trees, were saved. The change wrought by the flood, in the appearance

of the country, was truly wonderful and the destruction was complete.

Night had closed over that valley where all was happiness and quiet,

but day opened upon a scene of desolation. The fertile fields were torn

up and covered with masses of stone and gravel, and the flood left

marks of its fury far up on the hill sides.

At the commencement of the rain which caused this flood, the ground was

covered with snow to the depth of eighteen inches: the weather became

warm and the powerful rain storm continued incessantly for forty-eight

hours. Notwithstanding the immense volume discharged at the overfall

of the dam, the water was rising, during the night previous to this

disaster, at the rate of fourteen inches per hour over the Reservoir,

covering an area of four hundred acres.

It occurred on the 8th of January, 1841.

In repairing the breach it was decided to build an extension of solid

hydraulic masonry in the place of the portion of embankment which was

carried away.

The gate house and wing wall, which is seen on the ridge of the dam,

shows where the masonry of the original structure connected with the

embankment which extended across the river. The whole length of the

overfall is 251 feet. Access to the house over the culvert, is gained

by a foot bridge which is seen in the picture. The masonry of the

original structure has a rock foundation, and the extension of the

overfall which is seen on the left of the house extending across to the

embankment has an artificial foundation of concrete.

The masonry of the dam is about 8 feet thick at the top and 65 feet at

the base; it is built in a vertical form on the upstream side, with

occasional offsets, and the lower face has a curved form such as to

pass the water over without giving it a direct fall upon the apron at

the foot; this apron is formed of timber, stone, and concrete; and

extends some distance from the toe of the masonry, giving security at

the point where the water has the greatest action. A secondary dam has

been built at a distance of 300 feet from the masonry in order to form

a basin of water setting back over the apron at the toe of the main dam

so as to break the force of the water falling upon it. This secondary

dam is formed of round timber, brush wood, and gravel; it may be seen

in the picture directly under the bridge which extends across below the

main structure.

On the upstream side of the masonry of the dam, an embankment of earth

is filled in, extending 275 feet from the masonry at the base, and

extending from the masonry with a slope of 1 foot in 5 on the top.

[Illustration: XII

_F. B. Tower._ _W. Bennett._

CROTON AQUEDUCT AT SING SING.]

The whole work about the dam possesses great interest, and though it

be distant from the city and somewhat difficult of access, will not

fail to please those who may take time to visit it. Just above the

place where the dam is constructed the River had a bold turn and flowed

along at the foot of a steep and rugged bank. A road passed along at

the base of this hill leading to a mill which was situated at the turn

of the River, before mentioned; a substitute for this road, which was

submerged, has been made along the hill side passing on the right of

the gate house. Enough of the forest has been cleared away to admit of

the construction of the work, but the place still possesses much of its

original wildness, and to see such beautiful mechanical work standing

against the rude rocks,--to observe what changes have been wrought

in the form of this rock to render it subservient to the purposes of

the work, makes us feel that there has been a strife there; but it all

shows that _art_ has gained the ascendency.

The form which has been adopted for the face of the extension of the

overfall is a reversed or double curve which would be easily recognized

as _Hogarth’s line of beauty_: the overfall for the original dam has a

plane face with a curve at the base.

Walks are formed about the work bordered with grass, giving a neatness

and finished appearance to the whole; and every thing in connection

seems to indicate that the vicinity of the _Croton Dam_ will be one of

the resorts in summer seasons for the citizens of New-York. From the

Croton Dam the Aqueduct passes along the left side of the valley of the

Croton River until at the mouth of this river it reaches the left bank

of the Hudson, which it pursues, keeping at a distance of nearly half

a mile from the River, until it arrives at the village of Sing-Sing,

which is eight miles from the dam. In the course of this distance the

Aqueduct passes through four tunnels and encounters many valleys and

ravines where high foundation walls were required, and culverts for the

passage of the streams.

At the village of Sing-Sing there are two Aqueduct bridges; one over a

public road-way, and the other over the Sing-Sing Kill. These bridges

and the adjacent work form a very interesting point on the line of

Aqueduct.

Plate XII. is a view of the Aqueduct at this place: at the left of the

picture may be seen the bridge over the road, and on the right that

over the Kill. The bridge over the road has a span of 20 feet, and the

direction of the road-way being not at right angles with the line of

Aqueduct required the arch to be built askew; the arch lies in the

direction of the road-way, having the ends in planes parallel with the

direction of the Aqueduct. This bridge is worthy of notice, but public

attention is more generally directed to the larger one: _that_ has an

arch of 88 feet span and a rise of 33 feet; the form of the arch is

elliptical, being a compound curve drawn from five different centres,

or radius points. The Kill, or valley over which this arch stands, is a

deep narrow gorge worn by a small stream which empties into the Hudson

River.

The bottom of the ravine is about 70 feet below the soffit or under

side of the arch. Plate XIII. is another view of the large arch taken

from the bottom of the valley near it, and shows the bridge which has

been constructed for a public road passing under it, and the mill near

by.

[Illustration: XIII

F. B. Tower. Napoleon Gimbrede. sc.

AQUEDUCT BRIDGE AT SING SING.]

This arch presents a singularly bold appearance, vaulting over the

roadway and rising high up above the old mill, and what adds much to

this boldness, is the narrowness of the arch, or small distance from

one end of it to the other; being only 23⅓ feet long at the springing

line while the span is nearly four times this length. The length of

the arch diminishes towards the crown, the ends being in planes not

vertical, but inclining towards each other at the top. Each end has

a batter or inclination of one twenty fourth of its height, or half

an inch to the foot. The arch is built of granite, is 3 feet thick

at the crown and 4 feet at the spring or base. The abutments have a

foundation of solid rock which was excavated in proper form to give

them firm footing. The whole structure presents a degree of stability

which seems to defy the effects of time. The Aqueduct has a cast

iron lining over this bridge (as it has over all of this character): it

is formed of plates five eighths of an inch thick, put together with

screw-bolts and nuts and the joints closely filled with iron cement.

This lining is within the brick work of the bottom and sides of the

channel-way, having four inches of brick outside of it and four inside.

The object of it is to prevent any water dripping through the work,

lest by any means it should fill the exterior masonry of the bridge

with moisture and thus render it liable to injury from frost. Other

precautions are taken in forming the masonry about the channel-way, to

prevent this exuding, and the whole plan of the work shows foresight

and precaution worthy of the highest praise.