CHAPTER 5.

Map Sketching.

Map sketching is an important factor in trench warfare to-day as it is

in a war of movement. A fairly accurate map will indicate more than

many words and in much less time. Time is the great factor in war.

Instruction must also be rapid. Here are ten lessons which would

occupy a week if taken morning and afternoon. The aim of the

instruction as in company rifle shooting is to train many men to do a

satisfactory job, not to make a few finished topographers. Neatness,

accuracy and initiative are cardinal points.

For the instructor, reference should be made to _Grieves'_ "_Military

Sketching and Map Reading_", 2nd edition, if he desires to supplement

any points given here.

LESSON 1. (CLASS ROOM--FOUR HOURS.)

_Problem--Map Reading._

Study the conventional signs found in the "Manual for Non-commissioned

Officers and Privates of Infantry of the Army of the U.S.," 1917, page

273, or in Grieves, pages 28-35. These conventional signs are not

universal and must be used only as indications of the general

practice.

In map sketching in the field few conventional signs are used, and the

items of importance are written on the map, such as WOODS, CULTIVATED,

HEDGE, SWAMP, etc.

TAKING UP MAP SCALES.--There are three ways of indicating the relation

between the actual distance on the ground and the space the same

distance occupies on the map:

1. The graphic scale is a straight line divided into units, as miles,

yards, feet or meters, which represents the actual ground distance.

Thus if 6" = 1 mile the line would be six inches long and marked at

one end and 1 mile at the other, three inches being marked 1/2 mile,

etc. It is important to always have this graphic scale on a map so

that if the paper gets wet or is stretched from its original size the

scale will change in the same proportion.

2. A Statement in words or figures, e.g., 3 inches equal one mile,

meaning that 3 inches measured anywhere on the map represent 1 mile on

the actual ground.

3. The Representative Fraction (generally known abbreviated as R.F.)

having a number above the line that shows the unit length on the map

and below the line the number of units which are in the corresponding

actual ground distance. For example, if 1" = 1 mile, then the R.F. is:

1" (map distance)

-----------------------------------

63,360" (1 mile--ground distance)

if 3" = 1 mile the R.F. is:

3" (map distance) 1

----------------------------------- or -------

63,360" (1 mile--ground distance) 21120

if 6" = 1 mile:

6" 1

-------- or -------

63360" 10560

if 12" = 1 mile:

12" 1

--------- or ------

63360" 5280

In reading a map one must know the scale and also where the North is.

This is always indicated by an arrow pointing either to the magnetic

North or the true North. If to the magnetic North the needle will have

but one barb away from the true North. The angle between the magnetic

and the true North is the declination.

Placing the map in proper relation to the ground so that points of the

compass coincide on map and ground is called _orienting the map_.

In map work there is one vital point to remember; practically all the

ground surface is in its present form as a result of water action

1. Look for the water courses, that is the drainage system. It will

give the general slope of the land.

2. Look for the high points between the water courses, remembering

that there is always a valley then a hill then a valley again

continued in succession.

3. Finally locate towns, railroads, main highways and work down to the

minor details.

In measuring a map to get the actual distances on the ground, copy the

graphic scale on any piece of paper and apply this directly or if your

distances exceed your scale use the edge of a piece of paper and then

apply it to the graphical scale on the map.

LESSON 2. (FIELD WORK--FIVE HOURS.)

_Problem--Stride Scale Map Making_.

Producing a map from the actual ground requires certain instruments.

The second lesson takes up the preparation of the stride scale on the

alidade and the different kinds of maps, made in military sketching.

The alidade is a triangular ruler with one or more working scales on

it beside other measurements. The _working scale_ is, for infantry,

the stride or the space of ground covered from left foot to left foot

again in walking, reduced to the proper map distance. This varies with

individuals of course. Any scale of units, however, can be used as,

horse trot, telegraph poles, etc.

The working scale for each man is made by having him step off a

measured course, say 440 yards. The ground should not be too even as a

general average is needed, moreover the pace must be the natural gait

of the individual under ordinary circumstances. Let him count the

course three times then average the three results for the final

estimate.

Now to convert this into a working scale for the alidade made on a

scale of six inches to the mile; take the case of a man who takes 220

strides in 440 yards:

440 yards = 15,840 inches

15,840 ÷ 220 = 72, or his stride in inches

then 880 strides = 1 mile or 6" on the scale.

It is better to have a scale of 1,000 strides which is easily done by

the proportion:

1,000 sts. : 880 sts. : : x : 6

x = 6.8

now draw a line 6.8 inches long and a diagonal line from it; divide

this diagonal line into 10 equal parts for each 100 paces at any

convenient scale and draw a line from the end of the tenth part to the

end of the 6.8 inches line; draw lines parallel to this line from each

of the divisions. The 6.8" line is then divided into 10 equal parts;

each of these parts may be divided in the same manner into tenths.

Your scale is ready to be pasted or transferred to the alidade and

each 6.8. inches on the map will equal 1,000 of your strides on the

ground, or about 1-1/12 miles (2,000 yards).

There are two general classes of sketches:

1. ROAD SKETCH.--A traverse (passing over) made along a definite rout

showing all features of military importance for a distance of 200 or

300 yards on each side of the road. A road sketch is always made on a

scale of 3 inches to 1 mile.

2. AREA SKETCH.--A map of a definite locality. There are 3 kinds of

area sketches according to opportunity for observation:

(a) Position Sketch--when access may be had to the whole area.

(b) Outpost Sketch--where part of the ground must be mapped without

passing over it. This form is applicable particularly to trench

warfare. Intersection and resection are used to locate points

within the enemy's lines.

(c) Place Sketch--when sketch must be made from one point, as when

the proximity of the enemy would prevent any movement; as from

trench observation stations, etc.; also an elaboration of the

_landscape_ or _horizon_ sketch which is used everywhere in the

trenches today. From one point an actual outline of the

opposite trench and background is made in perspective,

reference points on the horizon being marked on the edge of a

pad at arm's length. These marks are then prolonged on the

paper and the horizon is sketched. In like manner the middle

distance and the foreground come under observation and are put

on in one below the other.

Time must be allowed the men to make their stride scales and to paste

or transfer them to their alidades.

[Illustration: Plate #9]

LESSON 3. (FIELD WORK--FIVE HOURS.)

The problem is to make a Position Sketch about one mile square closing

the traverse. First considering the sketch board, compass, pencils,

etc.; next the orienting, sighting and pacing; finally the uses of

intersection and resection and in making allowance for error.

The sketch board should be about 12 to 18 inches square, being used

with or without a tripod. A cheap camera tripod is excellent. The

board should have a compass attached so that it will remain in the

same relative position on the board. If iron thumb tacks are used

avoid getting them too near the compass. A hard pencil must be used to

obtain good results. The paper must be smooth and where possible

covered with another sheet fastened on but one side which will

readily fold back when one desires to work on the sketch.

By always placing the board so that the compass reads North it will be

oriented correctly. Care must be used when near electric wires or

masses of metal as automobiles, railroad tracks, etc., which will

attract the needle from its true azimuth (N. and S. direction) and

thus throw off the whole map. In such cases it is far better to back

sight and use the compass only at intervals to verify the sights.

This brings up the matter of sighting. It is important to make long

shots thus reducing the amount of individual error. In taking a

sighting point make sure it can be recognized when reached and make

sure to look at the reverse side in order to recognize it in case of

back sighting if necessary. Always carry several large-headed pins

using one at your present station and resting the side of the alidade

against it, swinging the other end for sighting.

After sighting and lining the sight on your sketch, step off evenly to

pace the distance. Time is always a factor in military mapping and

where possible make mental notes as you go along as to where roads or

other important features are located, so that you can place them in

their proper place on the map when you have reached the next station.

It is well always to set a good pace for here time can be readily

saved.

Making an _intersection_ is very simple. For as the sketcher moves

along he ties his map together by sighting at any prominent object

near his area, running these lines very lightly and only where he

assumes the points to lie on his map. An abbreviation on the line or a

number referring to a list off to one side will answer to recall the

object. At any other station where the same point can be seen a

similar line is drawn and where the two lines cross will be the

location of the object. In the case of three lines not crossing at the

same point take the middle of the triangle so formed.

_Resection_ is just the reverse of this process. The mapper wants to

know where he is located on the map. If he is properly oriented and

can aim at two points on the ground which he has located on the map,

he places a pin at one of these locations on the map and aims with the

alidade at the object on the ground drawing a line towards himself;

this is repeated with the other known point and where the two lines

cross on the map will be the point he is standing at.

In intersection the greatest accuracy is obtained by running the rays

so as to meet as nearly as possible at right angles.

In running a traverse the sketcher must expect to find some error at

his closing point. This error must be distributed over the whole

traverse so as not to have all the error concentrated at one point.

LESSON 4. (FIELD WORK--FOUR HOURS.)

PROBLEM.--Make a simple sketch, containing topographical details using

the traverse made during the preceding lesson. Use of conventional

signs should be emphasized and the appreciation of features of

military importance impressed. A tendency is to put in details to a

point of confusion. Judgment must be developed to choose telling

points.

A sharp pencil is always needed in sketching; in putting in the

topographical details special attention must be given to the pencil.

Keep the point sharp and make clear, distinct signs.

LESSON 5. (CLASS ROOM--FOUR HOURS.)

PROBLEM.--Contours, the Vertical Interval, Use of the Slope Board, Map

Distance, Visibility and Profiles.

A contour is an imaginary line on the surface of the earth all points

of which have the same elevation from a base or datum level, sea level

usually being this base. Slice an apple into pieces 1/2-inch thick;

where the cuts come may represent the contour lines. Take these

individual slices, beginning at the bottom and outline them on a sheet

of paper with a pencil (having run a nail through the apple first to

keep each piece in place). The resulting circles will represent the

apple's outline at 1/2-inch intervals.

Contours are always at equal elevations from each other, and the

Vertical Interval (known by the abbreviation V.I.) is the measure

between successive contour lines. In military maps the V.I. is always

the same for each map scale:

1 inch to the mile, the V.I. is 60 feet.

3 inch to the mile, the V.I. is 20 feet.

6 inch to the mile, the V.I. is 10 feet.

12 inch to the mile, the V.I. is 5 feet.

Note that the V.I. changes in proportion to the scale, a map on a 3

inch to the mile scale is 3 times as large as one on a scale of 1 inch

to the mile, while the V.I. is 1/3 as great, hence the former shows 3

times as many contours as the latter.

Map Distance means the horizontal distance between two contour lines

on a map and indicates a certain degree of slope. As the scale

increases the V.I. decreases in proportion and the M.D. therefore

remains the same for the same degree of slope whatever the scale of

the map. By computation we find that a one degree slope rises one foot

for every 57.3 feet horizontal distance, so a one degree slope would

have a 20 foot rise in 1,146 feet horizontal distance, this distance

equals .65 of an inch on the map if the scale is 3" to 1 mile.

The term "Map Distance" is also loosely used to denote distance

between points as measured on the map. Care should be taken to

distinguish between these two meanings.

Distances between contours, scale 3" to 1 mile: 1/2° slope = 1.3", 1°

slope =.65", 2° slope =.32", 3° slope =.22". These distances are

already on the alidade and if you get a slope of 2° with the slope

board and have the distance from your station on the map to the point

of aim either by pacing, intersection or resection, apply the M.D.

scale as many times as it will go. This will give the number of

contour lines crossing the traverse and the difference in elevation.

The spacing of the contours may not be even between your station and

the point of aim in which case the position of the contours must be

estimated by eye.

If your elevation above the datum or sea level is unknown at the start

assume any elevation which is great enough to put the datum lower than

the lowest spot of the area to be sketched.

The sketching board is easily made to serve as a slope board in this

manner. Hang a plumb bob about an inch below the center of a straight

edge of the board while pointing at the horizon, using the back of the

board. Mark a point 5.7" directly below and draw a semicircle through

it with the same radius. Now mark the point below the center zero and

from it divide the arc using chords one tenth of an inch long. This

will give a scale reading in degrees. By sighting along the top of the

board at some object at the height of the eye from the ground the

degree of slope is shown by the plumb bob on the scale below. Care

must be exercised to prevent the wind from disturbing the reading. A

protractor may be used in the same manner by sighting along the top

and using a plumb bob to record the angle.

In reading maps it is important to know whether points are visible

from each other due to intervening ridges or other topographical

features. This can be told by laying off accurately the distance on

the map between the points in question and using as datum the lowest

of the 3 points, then draw vertical lines, from the 2 higher points,

making them in proportion to their elevation with any convenient

scale. Draw a line between the first and last points and, if the

intervening vertical cuts this line the second point is not visible

from the first. Take for example, two points A and B, 1,760 yards

apart, by the map, A 500 feet and B 450 feet above sea level, the

intervening point C is 475 feet above sea level and 500 yards from B.

As B is the lowest we will call its elevation zero or at datum, then

elevation of A is 50 feet and C 25 feet.

[Illustration: Plate #10]

Another method of deciding visibility is by proportion. Measure the

distance between the three points A, B, and C, and obtain their

elevations above the datum (lowest of the 3) and using similar

triangles. Take the same case as above, letting X represent the point

above which the view is clear at 1,260 yards from point A, the line of

sight passes through this point.

1760 (A--B) : 500 (B--C) : : 50 (elev. A) : X

solving, X = 14.2

Now, since the ground at point C is 25 feet above the base and the

line of sight passes within 14.2 feet of the base at this place, an

observer at A is unable to see B.

The matter of profiling is very simple. Merely mark where the contours

cut the edge of a piece of co-ordinate paper and extend the proper

elevations, then pass a line through these points, remembering that

the surface of the ground has a natural curve.

LESSON 6. (FIELD WORK--FIVE HOURS.)

PROBLEM.--By use of the slope scale on the sketch board and the

contour interval scale on the alidade, each man will secure vertical

data on the flat sketch made in the fourth lesson. Certain critical

elevations will be determined and marked with red flags before hand.

The elevations of two points on the ground will be furnished, one as

the datum and the other as a check. Draw in contours of this sketch

with the help of drainage lines and elevations already secured.

The chief points to be considered are to take slopes from points

established on the sketch; to take several sights and average the

angle of slope; to properly lay off the elevation by using the slope

scale on the alidade; and finally to put in the contours along these

lines of sight _on the spot_ thus allowing for difference in

topography between the point of sight and the station from which the

elevation is taken. Careful note must be made of the drainage systems

as these are the keynotes to the sketch and finally the contours are

connected together, keeping in mind always that no contour stops

unless it makes a closed curve or goes off the map. Remember also

that contours make fingers pointing up stream and are blunt around

hill sides. Contours cross streams to opposite points and break at

roads, continuing on the other side. Uniform slopes have

equally-spaced contours. Do not try to measure every slope, two

intersecting elevation sights on a hill will check the height. Put the

intervening contours in by eye.

LESSON 7. (CLASSROOM--FOUR HOURS.)

PROBLEM.--Completing the map sketch previously made and making a

landscape sketch.

It is important to complete a map and no matter how good it is, if

certain points are omitted, the value of the work is very much

decreased. The sketcher must clear the sketch of all unnecessary lines

and notes and make his lettering clear on the map. Be sure that the

following items are on the sketch before it is turned in.

1. Location of the ground shown.

2. Line of magnetic north shown by an arrow, and if declination is

known, the true north also.

3. Graphic scale and representative fraction--R.F.

4. Vertical interval--V.I.

5. Sketcher's name and organization to which he belongs.

6. Date.

A landscape sketch is a place sketched with details shown in

perspective. The horizon is always of military importance and should

be shown as well as intervening crests, woods, houses, etc. Landscape

sketching in trench warfare is a necessary accomplishment of the

observer. The beginner will at first be confused by a mass of details,

but he must note only the outline of the features sketched. First draw

the sky line and crests, then fill in the other details with fewest

lines possible. Unnecessary shading tends to detract from the

clearness of the sketch. There will be great difficulty in getting the

perspective, note the size of objects, the further away they are the

smaller they seem. Make them so. In making the sketch, hold the pad in

front with one eye closed, the upper edge of the pad horizontal; a

string 20 inches long is tied to the pad and held between the teeth to

insure the same distance from the eye each time. Moreover, if it is

desired to locate objects by deflection of an angle from a reference

point, this can be done by using _mils_. One mil is 1-6400 of a

circle. At 20 inches a half-inch interval subtends 25 mils.

[Illustration: Plate #11]

The paper is oriented by bringing the sector desired along the upper

edge of the pad. The points desired are then in proper positions, both

horizontally and vertically.

Place a mark at the upper edge for points desired. The sky line should

be located first. Now carry these lines down, having drawn three

horizontal lines about 1/2 inch apart, beginning with the highest

point on the top line. Marks locating the other features are likewise

transposed in vertical and horizontal portions.

Now draw sky line connecting transposed marks, then such other points

as crests, trenches, houses, etc. After practice most other features

can be drawn in without reorienting, the sky line having been drawn.

The vertical elevation should be slightly exaggerated. Objects in the

background should be drawn in lightly while nearby features are

indicated by _heavy lines_. Avoid details, draw only silhouette, shade

only in showing woods.

LESSON 8. (FIELD WORK--FIVE HOURS.)

PROBLEM.--Make complete area sketch including contours, with no data

furnished other than the initial elevation.

Before commencing the work summarize the important points involved.

1. If possible select a base line.

2. Locate as many points by intersection as possible.

3. Make traverse by road, check locations by resection.

4. At good observation points observe and complete the sketch as far

as possible.

At each station keep the following points in view:

1. Back sight on previous station.

2. Select new sighting point ahead.

3. Determine elevation by slope board.

4. Put in contours where possible noting the drainage and critical

points of the general slope and the terrain.

5. Put in details along traverse just made of all topographical

features of military importance.

6. Determine your present elevation.

7. Make as many shots for intersection as you can and mark them.

8. Look for possible resection shots.

LESSONS 9 AND 10. (FIELD WORK--NINE HOURS.)

PROBLEM.--Make a road sketch of about 12 miles with scale of 3 inches

to the mile, V.I. 20 feet. This should include details of military

importance to a distance of 300 yards on either side of the road.

Keep in mind these points:

1. Start carefully and give attention to every part of the map.

2. Keep the board properly oriented.

3. Watch the water drainage systems.

4. Put down all necessary details at each _setup_.

5. Note high hills and towns not on immediate route, condition of

roads, fences, cultivation, hedges, cuts and fills, bridges (kind and

length), railroads, telegraph and telephone lines, schools, churches,

etc., notice particularly woods and points of concealment for hostile

troops.

Do the work at each station for elevation, contours and the noting of

necessary details so that the sketch will be complete as you go along.

Make certain that the title of the sketch, scale, orientation, etc.,

are all clearly indicated, for a road map may have to be completed by

another or may be called for suddenly when it will be useless without

these details.

Remember there are but two things absolutely essential to a good road

sketch; a good traverse and the location of the drainage system in its

relation to this traverse. With this control approximate contours can

be drawn by anyone having a knowledge of the principles of topography.

Never plot unimportant details. Prominent buildings and farm houses

are of value for locating oneself. Woods and orchards are shown for

tactical reasons but no one can expect to show every fence, ditch or

bit of cover that might hide a patrol.

Map Reading.

(GETTYSBURG 3" MAP--HUNTERSTOWN SHEET.) Plattsburg Barracks, N.Y.,

Sept. 17, 1917:

1. What is the shortest distance by road from Biglersville to Texas?

2. Describe the road between Texas and Table Rock.

3. Is it a cut or a fill along the railroad about 1/2 mile east of

Granite Hill Station?

4. What is meant by 931 on Chestnut Hill?

5. Can a man on the summit of hill 712 (about one mile southwest of

Plainview) be seen from the town of Plainview?

6. Point out two fords on the Conewago River.

7. Where is the highest point on the road from Plainview to

Heidlersburg?

8. Describe the fences along the road from Texas to Table Rock

Station.

9. Is Hill 566 S.W. from D. Wert visible from Henderson Meeting House?

10. Of what material is the bridge at Bridge School House constructed?

Harvard College:

1. Can a sentinel standing at 707 see road fork 535 (about 1,500 yards

south)?

2. An enemy patrol is marching north on the 544-616 road, and has

crossed the stream (750 yards north of 544.) Can this patrol see the

Red outguard at 707 from any point between stream and cross roads 616?

3. Can the sentinel at 712 see the road fork 518 (1,850 yards

southwest from 712)?

4. Can the sentinel at 712 see the cross roads 561 (about 1,200 yards

southeast)?

Assuming the height of a man as 5' 0" above the ground and trees and

buildings as 30' 0".

1. Is the ground at road fork 552 near D. Wirt visible to a patrol on

Hill 712? If not what is the obstructing point? Turn in profile, using

cross section paper.

2. Disregarding trees, is a man standing on Bridge 523 near Bridge

S.H. visible from Hill 712?

Solve by any method desired indicating the method.

1. Make a profile from location of the letter "U" of Chestnut Hill

near Center Mills to Hill 712, 2-1/2 miles to the south.

2. Is the location of the letter "B" of Beatrich visible from "U" of

Chestnut Hill? If not what obstructs?

1. Can a man on Hill 712 see a man at cross roads 554 in Hunterstown

(disregard trees)?

2. To a man standing at the point where contour 680 crosses the road

just south of 707, where does the roadbed first become invisible?

1. When the point arrives at Hill 647 can it see the road fork 610 to

the northwest?

2. When the flank patrol reaches Benders Church cross roads can it see

an enemy patrol at the house midway on the road 534-554 one mile to

the northeast?

3. Looking north along the Center Mills road from Hill 647, where does

the road first become invisible?

1. What does 1/21120 mean?

2. What direction is the general drainage system on this sheet?

Military Instructors Manual · 第 5 / 16 章