Paving--Multnomah County Line to Newberg

A complete description of the paving of the 15.7 mile section of the

West Side Highway between the Multnomah County Line and Newberg is given

in the Chapter devoted to Washington County. It should be mentioned

here, however, that 3.2 miles of this pavement is within Yamhill County,

and was built by the State at a cost of $57,500.00. The construction of

the subgrade was paid for by Yamhill County, part of it having been done

by County forces and the balance of it by the paving contractor under a

cost plus 10 per cent agreement with the County. For the work done under

this agreement, the contractor was paid $6,153.05.

Third biennial report of the Oregon State Highway Commission · 第 291 / 292 题