Engineering $ 635.30
Construction:
Common Excavation, 3935.6 cu. yds. @ .60 $ 2,361.42
Intermediate Excavation, 549.4 cu. yds. @ .75 412.05
Solid Rock Excavation, 9837.6 cu. yds. @ 1.40 13,772.64
Overhaul per 100 lin. ft., 363 cu. yds. @ .03 10.89
12-inch Corr. Iron Pipe, 20 lin. ft. @ .73 14.60
15-inch Corr. Iron Pipe, 108 lin. ft. @ .83 89.64
21-inch Corr. Iron Pipe, 60 lin. ft. @ 1.00 60.00
Rubble Masonry, 1.58 cu. yd. @ 12.50 19.75
Guard fence, 100 lin. ft. @ .85 85.00
1 90-foot Bridge & approaches:
Superstructure and trestle (Lump
sum) $ 5,100.00
Class "A" Concrete in piers, 49.24
cu. yds. @ $34.00 1,674.16
----------
$ 6,774.16
----------
$ 23,600.15
-----------
$ 24,235.45