Engineering $ 1,423.30
Construction:
Common Excavation, 11,397 cu. yds. @ .40 $ 4,558.80
Intermediate Excavation, 6,017.4 cu. yds. @ .70 4,212.18
Solid Rock Excavation, 2,816.5 cu. yds. @ 1.35 3,802.27
12-inch Corr. Iron Pipe, 682 Lin. ft. @ .40 272.80
24-inch Corr. Iron Pipe, 40 Lin. ft. @ 1.00 40.00
Rubble Masonry, 22.3 cu. yds @ 10.00 223.00
----------
13,109.05
----------
$14,532.35