Pendleton-Pilot Rock Section--Grading and Macadamizing

Upon the completion of the survey by the State Highway Department of the

section of the Oregon-Washington Highway between Pendleton and Pilot

Rock, the Umatilla County Court started grading. Where the construction

is light the road grader was used to great advantage. Through the aid of

the Division Office of the State Department new right-of-way was secured

in some places and the alignment of the road naturally improved.

During September and October, 1918, the section between Pendleton and

the County Poor Farm was graded and macadamized on a six per cent

development over Grave Yard Hill. This work, both grading and

macadamizing is of excellent character and will soon be opened to

traffic. W. C. Crews, engineer for the State Department made the

relocation on this section and was resident engineer during

construction. The following is a statement showing quantities and total

and unit costs:

Item and quantity Total cost Unit cost

Excavation, 4,795 cu. yds $3,164.70 $ .66

Gravel, 2,000 cu. yds 2,600.00 1.30

Concrete Bridge 1,600.00

----------

Total cost $7,364.70

An additional four miles from the County Poor Farm south was graveled by

the County with an expenditure of $2,000.00.