Wild Horse Paving

The State Highway Commission on June 29, 1917, let a contract to the

Warren Construction Company for paving a ten mile section of the Wild

Horse Road northeast of Pendleton and one mile of the Old Oregon Trail

leading west from Pendleton. The pavement laid was bitulithic and the

subgrade was an old macadam road built by the County. The macadam road

was of insufficient width for supporting a 16 foot pavement, which

condition required widening of the grade, re-ditching and the placing of

extra crushed rock for base.

The widening of the road bed was done with County funds expended under

the direction of the State Highway Department. The work of widening the

grade cost the County, $9,975.00 for the 11 miles.

[Illustration: ON THE PAVED ROAD BETWEEN PENDLETON AND ADAMS IN UMATILLA

COUNTY. PAVED IN 1917]

Paving work begun in July, 1917, and an excellent pavement of the

standard two-inch bitulithic type was secured, with a six inch crushed

rock base. The total cost of this work was $162,626.56 or $14,784.22 per

mile. M. O. Bennett was the engineer in charge and Chas. Noble was the

inspector on this work. Following is a detailed cost statement: