The 3.22-mile section of the Oregon-Washington Highway known as the

Jones Hill Grade, lies about ten miles east of Heppner, and extends over

the divide between Hinton and Butler Creeks. The State location involved

the construction of an entirely new road. This improvement was paid for

in full by the County, the total cost being $25,050.26.

R. H. Baldock, resident engineer for the State Highway Department, was

the engineer in charge.

Construction quantities are shown in the following statement:

Rock Excavation, 6,200 cu. yds. at $3.98 $ 18,504.26

Common Excavation, 7,300 cu. yds. at .59 4,350.00

Culverts 2,200.00

----------

Total cost $ 25,054.26