Divide Overcrossing

For the elimination of the dangerous grade crossing of the Pacific

Highway with the Southern Pacific Railway at Divide, the Highway

Department made surveys and prepared plans for an overhead crossing at

that point. The Public Service Commission of Oregon ordered that this

overhead crossing be built, forty per cent of the cost to be paid by the

Railway Company, thirty per cent by the State and thirty per cent by the

County.

Bids were received for the construction of the structure and approach

fills on September 10, 1918, but before work was begun, the United

States Highways Council ordered that construction be delayed until after

the war on account of the shortage in steel and cement. Work will,

therefore, not be undertaken until the 1919 season.

The structure designed for this overcrossing is a three span reinforced

concrete viaduct, providing clearance for the double tracking of the

railway. The cost of the structure and the approach fills is estimated

to be $19,500.00. In connection with this, about 1.3 miles of new grade

must be built to connect with the present road, no part of the cost of

which will be shared by the Railway Company. This grading is estimated

to cost $9,000.00. As soon as the grading is completed, it will be

macadamized by the Highway Commission.