Engineering $ 162.88
Construction:
Clearing and Grubbing $ 125.00
Common Excavation, 692 cu. yds. at .53 366.76
Intermediate Excavation, 2,552 cu. yds. at .63 1,607.76
Solid Rock Excavation, 1,954 cu. yds. at $1.20 2,344.80
Overhaul per 100 lin. ft., 3,159 cu. yds. at .03 94.77
12" Plain Conc. Pipe, 168 lin. ft. at $1.00 168.00
--------
4,707.09
--------
Total Cost $ 4,869.97