Engineering $ 4,872.94
Culvert Pipe furnished by State 3,846.45
Payments to Contractor for Work as follows:
Clearing and Grubbing $ 3,500.00
Common Excavation, 29,426 cu. yds. at .45 13,241.70
Intermediate Excavation, 21,258 cu. yds. at
.45 9,566.10
Solid Rock Excavation, 21,558 cu. yds. at
$1.25 26,947.50
Overhaul, per 100 lin. ft., 6,767 cu. yds.
at .02 135.34
12" Concrete Pipe, 1,077 lin. ft. at .55 592.35
18" Corr. Galv. Iron Pipe, 581.5 lin. ft. at .40 232.60
24" Corr. Galv. Iron Pipe, 162.5 lin. ft. at .50 81.25
30" Corr. Galv. Iron Pipe, 127.5 lin. ft. at .60 76.50
36" Corr. Galv. Iron Pipe, 166.5 lin. ft. at .75 124.87
Class "A" Concrete, 44.67 cu. yds. at $22.50 1,005.07
Class "C" Concrete, 66.72 cu. yds. at $18.00 1,200.96
6" Porous Drain Tile, 400 lin. ft. at .40 160.00
Trestle Timber, 45,968 f. b. m., at $45.00 2,068.56
Metal Reinforcement, 2,506 lbs. at .15 375.90
Extra Clearing, 1.75 acres at $100.00 175.00
Painting Railings on Coyote Creek and Dry Gulch
Bridges (Force Account) 74.94
Gravel Backfilling for Drain Tile (Force Account) 23.50
Culvert Pipe furnished by State 3,846.45
---------
Total Paid to Contractors 59,582.14
----------
Total Cost of Work $68,301.53