Macadamizing--Cascade Locks to Hood River

On July 4, 1918, a contract was awarded to A. D. Kern of eighteen miles

of gravel surfacing between Hood River and the Multnomah County Line on

the basis of cost plus fifteen per cent on labor and supplies and twelve

and one-half per cent on equipment; provided, that no percentage should

be paid on any cost over $50,000. This work also includes the building

of shoulders on the one mile of pavement built by S. Benson in 1916

adjacent to the Multnomah County Line. The gravel for this work was

taken from pits at Cascade Locks, Herman, Sonny and Hood River, was

loaded by steam shovels, screened at two of the pits and hauled by auto

trucks. As a result there is now a gravel surface between Hood River and

Cascade Locks. A total of 23,396 cubic yards was placed upon the road at

an average cost of $2.88 per cubic yard which represents total cost of

excavating, screening, hauling, spreading and rolling.