Engineering $ 468.38
Construction--
Common excavation, 1,925 cu. yds. at 30c $ 577.50
Intermediate excavation, 1,071.9 cu. yds. at
48c 514.51
Solid rock excavation, 1,039.7 cu. yds. at
$1.25 1,299.62
Overhaul per 100 lin. ft., 905 cu. yds. at 3c 27.15
12-inch corrugated iron pipe, 228 lin. ft. at
$1.00 228.00
Force account--
Excavation for cribbing and placing rip-rap 61.93
8-foot extension to 36-inch culvert 54.63
Widening old roadbed, removal of slides and
general improvement work not subject to
measurement 3,082.56
Culvert pipe furnished by State 36.33
---------
5,882.23
----------
Total cost $6,350.61