DETAILED EXPENDITURE STATEMENT--GRADING GOBLE SECTION

Engineering $ 2,925.64

Guarding S. P. & S. Ry. tracks 527.02

Right-of-way damages 73.56

Rental on State Industrial Ry. track furnished

contractor 138.00

Payments to contractor for work as follows:

Clearing and grubbing $ 2,085.00

Common excavation, 20,106.5 cu. yds. at 45c 9,047.92

Intermediate excavation, 3,534.9 cu. yds.

at 70c 2,474.43

Solid rock excavation, 11,947.2 cu. yds.

at $1.15 13,739.28

12-inch reinforced concrete pipe, 560 lin.

ft. at $1.50 840.00

24-inch reinforced concrete pipe, 92 lin. ft.

at $3.30 303.60

36-inch reinforced concrete pipe, 80 lin. ft.

at $5.30 424.00

Overhaul per 100 lin. ft., 18,032 cu. yds. at

2c 360.64

Force account--

Replacing trestle for Warren Packing Co.'s

plant, Goble 256.00

Borrowing approximately 400 cu. yds. rock to

cover dirt fill 506.08

Removal of overhanging rock near Goble Creek

bridge 6,454.32

Widening grade and building fill from Goble

postoffice to Goble Creek bridge 5,853.31

Cutting off rock point to give safe sight

distance around curve 47.12

Removal of slide west of Goble Creek 18.66

Placing 400 feet drain tile in quicksand 137.01

Placing timber foundation for culvert 51.05

--------

Total paid to contractor $ 42,598.42

-----------

Grand total cost $ 46,262.64