Construction engineering $548.12
Excavation and embankment 137.24
Drainage 21.11
Quarrying and crushing (6,504 cu. yds. crushed) 9,627.92
Spreading and rolling (6,504 cu. yds.) 5,913.53
Hauling (6,504 cu. yds) 4,371.62
Camp construction and operation 545.61
Corral construction and operation 313.82
----------
Total cost $21,478.97