COST STATEMENT--RAINIER-GOBLE MACADAM (STATE FORCES)

===============================+========+========+============+=====

Item | Unit | Amount | Cost | Unit

| | | | Cost

-------------------------------+--------+--------+------------+-----

Engineering | | | $ 382.85 |

Intermediate Excavation |Cu. yds.| | 1,078.97 | .72

Quarrying and crushing |Cu. yds.| 2,555 | 3,828.71 | 1.29

Hauling stone |Cu. yds.| 2,555 | 3,243.99 | 1.27

Placing and rolling |Cu. yds.| 2,555 | 2,979.22 | 1.17

Camp construction and operation| | | 719.27 |

General construction | | | 197.34 |

| | | ---------- |

Total | | | $12,430.35 |

-------------------------------+--------+--------+------------+-----