Item | Unit | Amount | Cost | Unit
| | | | Cost
-------------------------------+--------+--------+------------+-----
Engineering | | | $ 382.85 |
Intermediate Excavation |Cu. yds.| | 1,078.97 | .72
Quarrying and crushing |Cu. yds.| 2,555 | 3,828.71 | 1.29
Hauling stone |Cu. yds.| 2,555 | 3,243.99 | 1.27
Placing and rolling |Cu. yds.| 2,555 | 2,979.22 | 1.17
Camp construction and operation| | | 719.27 |
General construction | | | 197.34 |
| | | ---------- |
Total | | | $12,430.35 |
-------------------------------+--------+--------+------------+-----