Item Cost

Engineering $ 5,998.96

General construction 11,759.14

Clearing and grubbing 892.37

Excavation and embankment 22,529.95

Drainage structures 3,596.27

Miscellaneous structures 1,454.76

Quarrying and crushing 43,714.47

Placing, rolling, sprinkling, etc. 46,502.97

Camp construction and operation 111.51

-----------

Total $136,560.40

This work includes 25,405 cubic yards of excavation, 22,170 cubic yards

of crushed rock macadam and 10,298 cubic yards of rubble base, besides

numerous small structures, drains, etc.

Third biennial report of the Oregon State Highway Commission · 第 116 / 292 题