Construction--
Clearing and grubbing $ 200.00
Common excavation, 1,167.3 cu. yds. at 75c 875.47
Intermediate excavation, 2,127.6 cu. yds.
at $1.00 2,127.60
Solid rock excavation, 829.5 cu. yds. at
$1.85 1,534.58
12-inch plain concrete pipe, 26 lin. ft.
at $1.50 39.00
15-inch plain concrete pipe, 76 lin. ft. at
$1.80 136.80
18-inch reinforced concrete pipe, 84 lin. ft.
at $2.00 168.00
Class C concrete, 5 cu. yds. at $15.00 75.00
Drainage structures under roadbed to protect
embankment and private water supply 82.25
---------
5,238.70
---------
Total cost $5,746.68
Paid by State $ 507.98
Paid by County 5,238.70
---------
Total $5,746.68