Engineering $ 2,444.57

Construction--

Standard Bitulithic pavement, 70,170 sq.

yds. at $1.26 $ 88,414.20

Stone Shoulders, 68,208 lin. ft. at .051/2 3,751.44

Hauling and placing broken stone furnished by

State, 6,1681/4 cu. yds., at $1.18 7,278.54

Broken stone, loose measure, 12,8721/4 cu.

yds., at $2.37 30,507.23

Installing wooden headers at railroad crossing 24.06

Filling low places after rolling, clearing

debris after forest fire 59.53

Excavating spongy place in subgrade and

refilling 67.10

Loading and hauling to bring outside 2 ft. of

roadbed to grade; no material nearby 154.14

Grading 800 feet north from New Era, and

dismantling and loading crusher 1,726.40

-----------

Total due contractor for work done to

November 30, 1918 $131,982.64

Less 15 per cent retained pending completion 19,797.40

-----------

$112,185.24

Less plant rock and miscellaneous items

furnished by State 12,514.96

-----------

$99,670.28

----------

Total expended to November 30, 1918 $102,114.85

This work is estimated to cost complete $135,000.00

Third biennial report of the Oregon State Highway Commission · 第 95 / 292 题