Engineering $ 1,944.67

Construction--

Clearing and grubbing $ 500.00

Common excavation, 10,231 cu. yds. at 60c 6,138.60

Intermediate excavation, 8,689.4 cu. yds.

at 80c 6,951.52

Solid rock excavation, 7,722.2 cu. yds.

at $1.25 9,652.75

12-inch reinforced concrete pipe, 391 lin. ft.

at $1.25 488.75

36-inch reinforced concrete pipe, 56 lin. ft.

at $4.00 224.00

6-inch porous drain tile, 585 lin. ft. at 10c 58.50

Class A concrete, 48 cu. yds. at $15.00 720.00

Class C concrete, 2 cu. yds. at $12.00 24.00

Rubble masonry, 2 cu. yds. at $1.25 2.50

Overhaul per 100 lin. ft., 54,862 cu. yds.

at 2c 1,097.24

Crushed rock for drain tile, 30 cu. yds. 46.20

18-inch concrete pipe in place, 45 lin. ft. 87.15

-----------

$ 25,991.21

Less 15 per cent retained pending completion 3,898.68

-----------

22,092.53

-----------

Total expended to November 30, 1918 $ 24,037.20

Paid by State--engineering 1,944.67

Paid by County--construction 22,092.53

-----------

Total $ 24,037.20

This work is estimated to cost complete $ 27,500.00

[Illustration: BITUMINOUS PAVEMENT ON THE PACIFIC HIGHWAY SOUTH OF

OREGON CITY IN CLACKAMAS COUNTY. GRADED AND PAVED IN 1918]