CHAPTER X.

THE COST OF DRAINAGE.

Draining no more expensive than Fencing.--Engineering.--Guessing

not accurate enough.--Slight Fall sufficient.--Instances.--Two

Inches to One Thousand Feet.--Cost of Excavation and

Filling.--Narrow Tools required.--Tables of Cubic contents of

Drains.--Cost of Drains on our own Farm.--Cost of Tiles.--Weight

and Freight of Tiles.--Cost of Outlets.--Cost of Collars.--Smaller

Tiles used with Collars.--Number of Tiles to the Acre, with

Tables.--Length of Tiles varies.--Number of Rods to the Acre at

different Distances.--Final Estimate of Cost.--Comparative Cost of

Tile-Drains and Stone-Drains.

A prudent man, intending to execute a work, whether it be "to build a

tower," or drain a field, "sitteth down first and counteth the cost,

whether he hath sufficient to finish it." There is good sense and

discretion in the inquisitiveness which suggests so often the inquiry,

"How much does it cost to drain an acre?" or, "How much does it cost a

rod to lay drains?" These questions cannot be answered so briefly as

they are asked; yet much information can be given, which will aid one

who will investigate the subject.

The process of drainage is expensive, as compared with the price of land

in our new settlements; but its cost will not alarm those who have been

accustomed to see the improvements made in New England upon well

cultivated farms. Compared with the labor and cost of building and

maintaining FENCES upon the highways, and in the subdivisions of lots,

common in the Eastern States, the drainage of land is a small matter.

We see in many places long stretches of faced walls, on the line of our

roads near towns and villages, which cost from two to five dollars per

rod. Our common "stone walls" in these States cost about one dollar per

rod to build originally; and almost any kind of wooden fence costs as

much. Upon fences, there is occasion for annual repairs, while drains

properly laid, are permanent.

These suggestions are thrown out, that farmers may not be alarmed

without cause, at the high cash estimates of the cost of drainage

operations. Money comes slowly to farmers, and a cash estimate looks

larger to them than an estimate in labor. The cost of fencing seems no

great burden; though, estimated in cash, it would seem, as in fact it

is, a severe charge.

Drainage can be performed principally by the same kind of labor as

fencing, the cost of the tiles being a small item in the whole expense.

The estimates of labor will be made at one dollar per day, in

investigating this matter.

This would be the fair cash value of work by the day, perhaps; but it is

far more than farmers, who have work in hand on their own farms, which

may be executed in the leisure season after haying, and even into the

Winter, when convenient, will really expend for such labor. Few farm

operations would pay expenses, if every hour of superintendence, and

every hour of labor by man and boy and beast, were set down at this high

rate.

The cost of the tiles will, ordinarily, be a cash item, and the labor

may be performed like that of planting, hoeing, haying, and harvesting,

by such "help" hired by the mouth or day, or rendered by the family, as

may be found convenient.

The cost of drainage may be considered conveniently, to borrow a

clerical phrase, "under the following heads."

1. _Laying out, or Engineering._--In arranging our Spring's work, we

devote time and attention to laying it out, though this hardly forms an

item in the expense of the crop. Most farmers may think themselves

competent to lay out their drainage-works, without paying for the

scientific skill of an engineer, or even of a surveyor.

It is believed, however, that generally, it will be found true economy,

to procure the aid of an experienced engineer, if convenient, to lay out

the work at the outset. Certainly, in most cases, some skill in the use

of levelling instruments, at least, is absolutely essential to

systematic work. No man, however experienced, can, by the eye, form any

safe opinion of the fall of a given tract of land. Fields which appear

perfectly level to the eye, will be found frequently to give fall enough

for the deepest drainage. The writer recently had occasion to note this

fact on his own land.

A low wet spot had many times been looked at, as a place which should be

drained, both to improve its soil, and the appearance of the land about

it; but to the eye, it seemed doubtful whether it was not about as low

as the stream some forty rods off, into which it must be drained. Upon

testing the matter carefully with levelling instruments, it was found

that from the lowest spot in this little swamp, there was a fall of

seven and a half feet to the river, at its ordinary height! Again, there

are cases where it will be found upon accurate surveys, that the fall is

very slight, so that great care will be requisite, to lay the drains in

such a way that the descent may be continuous and uniform.

Without competent skill in laying out the work, land-owners will be

liable not only to errors in the fall of the drains, but to very

expensive mistakes in the location of them. A very few rods of drains,

more than are necessary, would cost more than any charge of a competent

person for laying them out properly.

Again, experience gives great facility in judging of the underground

flow of water, of the permeability of soil, of the probability of

finding ledges or other rock formation, and many other particulars which

might not suggest themselves to a novice in the business.

The laying out of drains is important, not only with reference to the

work in hand, but to additional work to be executed in future on

adjoining land, so that the whole may be eventually brought into one

cheap and efficient system with the smallest effective number of drains,

both minors and mains, and the fewest outlets possible; with such wells,

or other facilities for inspection, as may be necessary.

In the English tables of the cost of drainage by the Drainage Companies,

an estimate of $1.25 per acre is usually put down for "superintendence,"

which includes the engineering and the supervision of the whole process

of opening, laying and filling, securing outfalls, and every other

process till the work is completed. The general estimate of the cost of

drainage is about $25.00 per acre, and this item of $1.25 is but a small

per centage on that amount. The point has been dwelt upon here, more for

the purpose of impressing upon land-owners, the importance of employing

competent skill in the laying out of their drainage works, than because

the expense thus incurred, forms any considerable item of the cost of

the whole work.

2. _Excavation and Filling._ The principal expense of drainage is

incurred in the excavation of the ditch, whether it be for tiles or for

stones. The labor of excavation depends much upon the nature of the soil

to be moved.

"Draining on a sound clay," says the writer of a prize essay,

"free from stones, may be executed at a cheaper rate per rod, in

length, than on almost any other kind of soil, as, from the

firmness of the clay, the work may be done with narrow spades, and

but a small quantity of soil requires to be removed. The draining

of wet sands or grounds, or clays in which veins of sand abound, is

more expensive than on sound clays, because a broader spade has to

be used, and consequently a larger amount of soil removed; and

draining stony or rocky soils is still more expensive, because the

pick has to be used. This adds considerably to the expense."

Great stress is laid, by all experienced persons, upon using narrow

spades, and opening ditches as narrow as possible.

It is somewhat more convenient for unskillful laborers to work in a wide

ditch than in a narrow one, and although the laborers frequently protest

that they cannot work so rapidly in narrow ditches, yet it is found

that, in contract work, by the rod, they usually open the ditches very

narrow.

Indeed, it will be found that, generally, the cost of excavation bears a

pretty constant proportion to the number of cubic feet of earth thrown

out.

It will surprise those unaccustomed to these estimates, to observe how

rapidly the quantity excavated, increases with the increased width of

the ditch.

To enable the reader accurately to compute the measurement of drains of

any dimensions likely to be adopted, a table and explanations, found in

the Report of the Board of Health, already quoted, are given below. The

dimensions, or contents of any drain, are found by multiplying together

the length, depth, and _mean_ width of the drain.

"Thus, if a drain is 300 yards long, and the cutting 3 feet deep,

20 inches wide at the top, and 4 inches wide at the bottom, the

mean width would be 12 inches (or the half of the sum of 20 and 4),

and if we multiply 300, the length, by 1, the depth in yards, and

by 1/3, the mean width in yards, and the product would be 100 cubic

yards. The following table will serve to facilitate such

calculations.

_Table showing the number of Cubic Yards of Earth in each Rod (5-1/2

Yards in length), in Drains or Ditches of various Dimensions._

=================================================

DEPTH. | MEAN WIDTH.

-------+------+------+------+------+------+------

Inches.|7 In. |8 In. |9 In. |10 In.|11 In.|12 In.

-------+------+------+------+------+------+------

30 |0.89 |1.02 |1.146 |1.27 |1.40 |1.53

33 |0.98 |1.12 |1.26 |1.40 |1.54 |1.68

36 |1.07 |1.22 |1.375 |1.53 |1.68 |1.83

39 |1.16 |1.324 |1.49 |1.655 |1.82 |1.986

42 |1.25 |1.426 |1.604 |1.78 |1.96 |2.14

45 |1.34 |1.53 |1.72 |1.91 |2.10 |2.29

48 |1.426 |1.63 |1.833 |2.04 |2.24 |2.444

51 |1.515 |1.73 |1.95 |2.164 |2.38 |2.60

54 |1.604 |1.83 |2.06 |2.29 |2.52 |2.75

57 |1.69 |1.935 |2.18 |2.42 |2.66 |2.90

60 |1.78 |2.036 |2.29 |2.546 |2.80 |3.056

=================================================

=================================================

DEPTH. | MEAN WIDTH.

-------+------+------+------+------+------+------

Inches.|13 In.|14 In.|15 In.|16 In.|17 In.|18 In.

-------+------+------+------+------+------+------

30 |1.655 |1.78 |1.91 |2.04 |2.164 |2.29

33 |1.82 |1.96 |2.10 |2.24 |2.38 |2.52

36 |1.986 |2.14 |2.29 |2.244 |2.60 |2.75

39 |2.15 |2.32 |2.48 |2.65 |2.81 |2.98

42 |2.32 |2.495 |2.674 |2.85 |3.03 |3.21

45 |2.48 |2.67 |2.865 |3.055 |3.246 |3.438

48 |2.65 |2.85 |3.056 |3.26 |3.46 |3.667

51 |2.81 |3.03 |3.25 |3.46 |3.68 |3.896

54 |2.98 |3.20 |3.44 |3.666 |3.895 |4.125

57 |3.14 |3.38 |3.63 |3.87 |4.11 |4.354

60 |3.31 |3.564 |3.82 |4.074 |4.33 |4.584

=================================================

"Along the top of the table is placed the mean widths in inches,

and on the left-hand side the depths of the drains, extending from

30 inches to 5 feet. The numbers in the body of the table express

cubic yards, and decimals of a yard. In making use of the table, it

is necessary first to find the mean width of the drain, from the

widths at the top and bottom. Thus, if a drain 3 feet deep were 16

inches wide at the top, and 4 inches at the bottom, the mean width

would be half of 16 added to 4, or 10; then, by looking in the

table for the column under 10 (width), and opposite 36 (inches of

depth), we find the number of cubic yards in each rod of such a

drain to be 1.53, or somewhat more than one and a half. If we

compare this with another drain 20 inches wide at the top, 4 inches

at the bottom, and 4-1/2 feet deep, we have the mean width 12, and

looking at the table under 12 and opposite 54, we find 2.75 cubic

yards, or two and three-quarters to the rod. In this case, the

quantity of earth to be removed is nearly twice as much as in the

other, and hence, as far as regards the digging, the cost of the

labor will be nearly double. But in the case of deep drains, the

cost increases slightly for another reason, namely, the increased

labor of lifting the earth to the surface from a greater depth."

Under the title of the "Depth of Drains," other reasons are suggested

why shallow drains are more easily wrought than deeper drains. The

widths given in English treatises, and found perfectly practicable

there, with proper drainage-tools, will seem to us exceedingly narrow.

Mr. Parkes gives the width of the top of a four-foot drain 18 inches,

of a three-and-a-half foot drain 16 inches, and of a three-foot drain 12

inches. He gives the width of drains for tiles, three inches at bottom,

and those for stones, eight inches. Of the cost of excavating a given

number of cubic yards of earth from drains, it is difficult to give

reliable estimates. In the writer's own field, where a pick was used to

loosen the lower two feet of earth, the labor of opening and filling

drains 4 feet deep, and of the mean width of 14 inches, all by hand

labor, has been, in a mile of drains, being our first experiments, about

one day's labor to three rods in length. The excavated earth of such a

drain, measures not quite three cubic yards. (Exactly, 2.85.)

In work subsequently executed, we have opened our drains of 4 foot

depth, but 20 inches at top, and 4 inches at bottom, giving a mean width

of 12 inches. In one instance, in the Summer of 1858, two men opened 14

rods of such drain in one day. In six days, the same two men opened,

laid, and filled 947 feet, or about 57-1/2 rods of such drain. Their

labor was worth $12.00, or 21 cents per rod. The actual cost of this job

was as follows:

847 two-inch tiles, at $13 per 1,000 $11.01

100 three-inch " " for main 2.50

70 bushels of tan, to protect the joints .70

Horse to haul tiles and tan .50

Labor, 12 days, at $1 12.00

-------

Total $26.71

This is 46-1/2 cents per rod, besides our own time and skill in laying out

and superintending the work. The work was principally done with Irish

spades, and was in a sandy soil. In the same season, the same men

opened, laid, and filled 70 rods of four-foot drain, of the same mean

width of 12 inches, in the worst kind of clay soil, where the pick was

constantly used. It cost 35 days' labor to complete the job, being 50

cents per rod for the labor alone. The least cost of the labor of

draining 4 feet deep, on our own land, is thus shown to be 21 cents per

rod, and the greatest cost 50 cents per rod, all the labor being by

hand. One-half these amounts would have completed the drains at 3 feet

depth, as has been already shown.

But the excavation here is much greater than is usual in England, Mr.

Parkes giving the mean width of a four-foot drain but 10-1/2 inches,

instead of 14 or 12, as just given. Mr. Denton gives estimates of the

cost, in England, of cutting and filling four-foot drains, which vary

from 12 cents per rod upwards, according to the prices of labor, and

other circumstances.

In New England, where labor may be fairly rated at one dollar per day,

the cost of excavating and filling four-foot drains by hand labor, must

vary from 20 to 50 cents per rod, according to the soil, and half those

amounts for drains of three-foot depth.

Of the aid which may be derived from the use of draining plows, or of

the common plow, or subsoil plow, our views may be found expressed under

the appropriate heads. That drains will long continue to be opened in

this vast country by hand labor, is not to be supposed, but we give our

estimates of the expenses, at this first stage of our education in

drainage.

3. _Cost of the Tiles._ Under the title of "The Cost of Tiles," we have

given such information as can be at present procured, touching that

matter. It will be assumed, in these estimates, that no tiles of less

than 1-1/2 inch bore will be used for any purpose, and for mains, usually

those of three-inch bore are sufficient. The proportion of length of

mains to that of minors is small, and, considering the probable

reduction of prices, we will, for the present, assume $10 per 1,000 as

the prices of such mixed sizes as may be used.

Add to this, the freight of them to a reasonable distance, and we have

the cost of the tiles on the field. The weight of two-inch tiles is

usually rated at about 3 lbs. each, though they fall short of this

weight until wet.

4. _Outlets._ A small per-centage should be added to the items already

noticed, for the cost of the general outfall, which should be secured

with great care; although, from such examination as the writer has made

in this country, and in England also, in the large majority of cases,

drains are discharged with very little precaution to protect the

outlets. Works completed under the charge of regular engineers, form an

exception to this remark; and an item of 37 cents per acre, for iron

outlets and masonry, is usually included in the estimated cost per acre

of drainage.

5. _Collars._ It is not known to the author that collars have been at

all used in America, except at the New York Central Park, in 1858; round

pipes, upon which they are commonly used abroad, when used on any, not

being yet much in use here.

In the estimates of Mr. Denton, in his tables, collars are set down at

about half the cost of the mixed tiles. The bore of them being large

enough to receive the end of the tile, increases the price in proportion

to the increase in size. It is believed, however, that a smaller size of

tiles may prudently be used with collars than without, because the

collars keep the tiles perfectly in line, and freely admit water, while

they exclude roots, sand, and other obstructions. A drain laid with one

and a half inch tiles with collars is, no doubt, better in any soil than

two-inch tiles without collars. Some compensation for the cost of

collars may thus be found in the less price of the smaller tiles.

6. _Laying._ The cost of laying tiles is so trifling as hardly to be

worth estimating, except to show its insignificance. The estimate, by

English engineers, is two cents per rod for "pipe laying and finishing."

What is included in "finishing," does not appear. From the personal

observations of the writer, it is believed that an active man may lay

from 60 to 100 rods of tiles per day, in ditches well prepared. Indeed,

we have seen our man James, lay twelve rods of two-inch tiles, in a

four-foot ditch, in forty-five minutes, when he was not aware that he

was working against time. This is at the rate of sixteen rods an hour,

which would give just 160 rods, or a half-mile, in a day of ten hours.

7. _Number of Tiles to the Acre._ The number of tiles used depends, of

course, upon the distances apart of the drains, and upon the length of

the tiles used.

The following table gives the number of tiles of various length, per

acre, required at different intervals:

========================================================================

Intervals between |Twelve inch|Thirteen inch|Fourteen inch|Fifteen inch

the Drains, | Pipe. | Pipe. | Pipe. | Pipe.

in feet. | | | |

------------------+-----------+-------------+-------------+-------------

15 | 2904 | 2680 | 2489 | 2323

18 | 2420 | 2234 | 2074 | 1936

21 | 2074 | 1915 | 1778 | 1659

24 | 1815 | 1676 | 1555 | 1452

27 | 1613 | 1489 | 1383 | 1290

30 | 1452 | 1340 | 1244 | 1161

33 | 1320 | 1219 | 1131 | 1056

36 | 1210 | 1117 | 1037 | 968

39 | 1117 | 1031 | 957 | 893

42 | 1037 | 958 | 888 | 829

========================================================================

The following table gives the number of rods per acre of drains at

different distances:

=====================================================================

Intervals between the Drains, in feet. | Rods per acre.

------------------------------------------+--------------------------

15 | 176

18 | 146-2/3

21 | 125-5/7

24 | 110

27 | 97-7/9

30 | 88

33 | 80

36 | 73-1/3

39 | 67-9/13

42 | 62-6/7

=====================================================================

It may be remarked here, that tiles, moulded of the same length, vary

nearly two inches when burned, according to the severity of the heat. It

may be suggested, too, that the length of the tile, in the use of any

machine, is entirely at the option of the maker. It is not, perhaps, an

insult to our common humanity, to suggest to buyers the propriety of

measuring the length as well as calibre of tiles before purchasing. In

the estimates which will be made in this detail, it will be assumed that

tiles will lay one foot each, with allowance for imperfections and

breakage. This is as near as possible to accuracy, according to our best

observation; and, besides, there is convenience in this simple estimate

of one tile to one foot, which is important in practice.

We have now the data from which we may make some tolerably safe

estimates of the cost of drainage. With labor at one dollar per day, and

tiles at $10 per 1,000, or one cent each, or one cent a foot, and

ditches four feet deep, opened and filled at one-third of a day's labor

to the rod, we may set down the principal items of the cost of drainage

by the rod, as follows:

Cutting and filling per rod 33-1/3 cts.

Tiles 16-2/3 "

----

50

This is putting the tiles at one cent a foot, and the labor at two cents

a foot, or just twice as much as the cost of tiles, and it brings a

total of half a dollar a rod, all of them numbers easily remembered, and

convenient for calculation.

By reference to the table giving the number of rods to the acre, the

cost of labor and tiles per acre may be at once found, by taking half

the number of rods in dollars. At 42 feet distance, the cost will be

$31.42 per acre; at 30 feet distance, $44; and at 60 feet, half that

amount, or $22 per acre.

Our views as to the frequency of drains, may be found under the

appropriate head.

Our estimate thus far, is of four-foot drains. We have shown, under the

head of the "Depth of Drains," that the cost of cutting and filling a

four-foot drain is double that of cutting and filling a three-foot

drain. There is no doubt, that, after all the good advice we have given

on this subject, many, who "grow wiser than their teachers are," will

set aside the teachings of the best draining engineers in the world, and

insist that three feet deep is enough, and persist in so laying their

tiles.

This _shallowness_ will reduce the cost of labor about one half, so that

we shall have the cost of labor and tiles equal--one cent a foot, making

33? cents per rod, or one-third of a dollar, instead of one-half a

dollar per rod. To the cost of labor and tiles, we should add a fair

estimate of the cost of the other items of engineering and outlets.

These are trifling matters, which English tables, as has been shown,

estimate together, at about $1.67 per acre.

Briefly to recapitulate the elements of computation of the cost of

drainage, we find them to be these: the price of labor, the price of

tiles, and freight of them; the character of the soil, the depth of the

drains, and their distance apart, with the incidental expense of

engineering and of outfalls, and the large additional cost of _collars_,

where they are deemed necessary.

COMPARATIVE COST OF TILE AND STONE DRAINS.

It is not possible to answer, with precision, the question so often

asked, as to the comparative cost of drainage with tiles and stones.

The estimates given of the cost of tile drains, are based upon the

writer's own experience, upon his own farm mainly; and the mean width

of four-foot tile drains, may be assumed to be 14 inches, instead of

10-1/2 inches, as actually practiced in England.

For a stone drain of almost any form, certainly for any regular

water-course laid with stones, our ditch must be at least 21 inches wide

from top to bottom. This is just 50 per cent, more than our own

estimate, and 100 per cent., or double the English estimate for tile

drains.

It will require at least two ox-cart loads of stones to the rod, to

construct any sort of a stone drain, costing, perhaps, 25 cents a load

for picking up and hauling. In most cases, where the stones are not on

the farm, it will cost twice that sum. We will say 25 cents per rod for

laying the stones, though this is a low estimate. We have, then, for

cutting and filling the ditch, 50 cents per rod, 50 cents for hauling

stone, and for laying, 25 cents per rod, making $1.25 a rod for a stone

drain, against 50 cents per rod for tile drains.

Then we have a large surplus of earth, two cartloads to the rod,

displaced by the two loads of stone, to be disposed of; and in case of

the tiles, we have just earth enough. There are many other

considerations in favor of tiles: such as the cutting up of the ground

by teaming heavy loads of stones; the greater permanency of tiles; and

the fact that they furnish no harbor for mice and other vermin, as the

English call such small beasts. In favor of stones, is the fact, that

often they are on the land, and must be moved, and it is convenient to

dispose of them in the ditches.

Again, there are many parts of the country where tiles are not to be

procured, without great cost of freight, and where labor is abundant at

certain seasons, and money scarce at all seasons, so that the question

is really between stone drains and no drains.

Stone drains, if laid very deep, are far more secure than when shallow;

because, if shallow, they are usually ruined by the breaking in of water

at the top, in the Spring time, by the action of frost, and by the

mining of mice and moles. If laid four feet deep, and the earth rammed

hard above the stones, and rounded on the surface to throw off surface

water, they may be found efficient and permanent.

The conclusion, however, is, that where it can be procured, at any

reasonable cost, drainage with tiles will generally cost less than

one-half the expense of drainage with stones, and be incomparably more

satisfactory in the end.

Farm drainage The Principles, Processes, and Effects of Draining Land with Stones, Wood, Plows, and Open Ditches, and Especially with Tiles · 第 10 / 24 章