RAPID CONSTRUCTION OF THE CANADIAN PACIFIC RAILWAY.

By E.T. ABBOTT, Member of the Engineers' Club of Minnesota. Read December

12, 1884.

During the winter of 1881 and 1882, the contract was let to Messrs.

Langdon, Sheppard & Co., of Minneapolis, to construct during the working

season of the latter year, or prior to January 1, 1883, 500 miles of

railroad on the western extension of the above company; the contract being

for the grading, bridging, track-laying, and surfacing, also including the

laying of the necessary depot sidings and their grading. The idea that any

such amount of road could be built in that country in that time was looked

upon by the writer hereof, as well as by railroad men generally, as a huge

joke, perpetrated to gull the Canadians. At the time the contract was let,

the Canadian Pacific Railway was in operation to Brandon, the crossing of

the Assiniboine River, 132 miles west of Winnipeg. The track was laid,

however, to a point about 50 miles west of this, and the grading done

generally in an unfinished state for thirty miles further. This was the

condition of things when the contract was entered into to build 500

miles--the east end of the 500-mile contract being at Station 4,660

(Station being at Brandon) and extending west to a few miles beyond the

Saskatchewan River.

The spring of 1882 opened in the most unpromising manner for railroad

operations, being the wettest ever known in that country. Traffic over the

St. Paul, Minneapolis & Manitoba Railroad, between St. Paul and Winnipeg,

was entirely suspended from April 15 to the 28th, owing to the floods on

the Red River at St. Vincent and Emerson, a serious blow to an early

start, as on this single track depended the transportation of all

supplies, men, timber, and contractors' plant, together with all track

materials (except ties), all of these things having to come from or

through St. Paul and Minneapolis. The writer hereof was appointed a

division engineer, and reported at Winnipeg the 15th of April, getting

through on the last train before the St. Vincent flood. No sooner was the

line open from St. Paul to Winnipeg than the cotillon opened between

Winnipeg and Brandon, with a succession of washouts that defied and

defeated all efforts to get trains over, so it was not until the fifth day

of May that I left Winnipeg to take charge of the second division of 30

miles.

By extremely "dizzy" speed I was landed at the end of the track, 180 miles

from Winnipeg, on the evening of the 9th (4 days). My outfit consisted of

three assistant engineers and the necessary paraphernalia for three

complete camps, 30 days' provisions (which turned out to be about 20), 11

carts and ponies, the latter being extremely poor after a winter's diet

on buffalo grass and no grain. On the 18th day of May I had my division

organized and camps in running order. The country was literally under

water, dry ground being the exception, and I look upon the feat of getting

across the country at all as the engineering triumph of my life.

On May 20 a genuine blizzard set in, lasting 24 hours, snowed five inches,

and froze the sloughs over with half an inch of ice, a decidedly

interesting event to the writer, as he was 18 miles from the nearest wood,

therefore lay in his blankets and ate hard tack. I stabled my ponies in

the cook tent, and after they had literally eaten of the sod inside the

tent, I divided my floor with them.

On 28th day of May I saw the first contractor, who broke ground at station

7,150. On the 1st of June I was relieved from this division, and ordered

to take the next, 50 miles west. On the 13th day of June ground was broken

on this division, at station 8,070, or only about 62 miles west of the

east end of the 500-mile contract. It looked at this time as though they

might build 150 miles, but not more. But from this time on very rapid

progress was made. On July 17 the track reached station 7,000, making

however up to this time but about 50 miles of track-laying, including that

laid on the old grade; but large forces were put on to surfacing, and the

track already laid was put in excellent condition for getting material to

the front. The weather from this until the freezing-up was all that could

be desired. Work ceased about the 1st of January, 1883, for the season,

and the final estimate for the work was as follows: 6,103,986 cubic yards

earth excavation, 2,395,750 feet B.M. timber in bridges and the culverts,

85,708 lineal feet piling, 435 miles of track-laying. This work was all

done in 182 working days, including stormy ones, when little, if anything,

could be done, making a daily average of 33,548 yards excavation, 13,150

feet B.M. timber, 471 feet piling, 2-38/100 miles track-laying. We never

had an accurate force report made of the whole line, but roughly there

were employed 5,000 men and 1,700 teams.

The admirable organization of the contractors was something wonderful. The

grading work was practically all done by sub-contractors, Messrs. Langdon,

Sheppard & Co. confining themselves to putting in the supplies and doing

the bridge work, surfacing, and track-laying. The grading forces were

scattered along about 150 miles ahead of the track and supply stores,

established about 50 miles apart, and in no case were sub-contractors

expected to haul supplies over 100 miles. If I remember rightly, there

were four trains of about forty wagons each, hauling supplies from the end

of track to the stores.

As can be readily seen, the vital point of the whole work, and the problem

to solve, was food for men and horses. 1,700 bushels of oats every day and

15,000 pounds of provisions, Sundays and all, for an entire season, which

at the beginning of the work had to come about 170 miles by rail, and then

be taken from 50 to 150 miles by teams across a wilderness, is on the face

of it considerable of an undertaking, to say nothing about hauling the

pile-drivers, piles, and bridge-timber there. To keep from delaying the

track, sidings 1,500 feet long were graded, about 7 miles apart. A

side-track crew, together with an engine, four flats, and caboose, were

always in readiness; and as soon as a siding was reached, in five hours

the switches would be in, and the next day it would be surfaced and all in

working order, when the operating department would fill it with track

material and supplies. From the head of the siding to the end of the track

the ground was in hands of track-laying engine, never going back of the

last siding for supplies or material, and my recollection is that there

were but six hours' delay to the track from lack of material the whole

season, at any rate up to some time in November. The track-laying crew was

equal to 4 miles per day, and in the month of August 92 miles of track

were laid. The ties were cut on the line of the road about 100 miles east

of Winnipeg, so the shortest distance any ties were hauled was 270 miles;

the actual daily burden of the single track from Winnipeg west was 24 cars

steel, 24 cars ties, aside from the transportation of grain and

provisions, bridge material, and lumber for station houses. The station

buildings were kept right up by the company itself, and a depot built with

rooms for the agent every 15 miles, or at every second siding. The

importance of keeping the buildings up with the track was impressed on the

mind of the superintendent of this branch, and, as a satire, he

telegraphed asking permission to haul his stuff ahead of the track by

teams, he being on the track-layers' heels with his stations and tanks the

whole season. The telegraph line was also built, and kept right up to the

end of the track, three or four miles being the furthest they were at any

time behind.

It might be supposed that work done so rapidly would not be well done, but

it is the best built prairie road I know of on this continent. It is built

almost entirely free from cuts, and the work is at least 20 per cent.

heavier than would ordinarily be made across the same country in the

States, on account of snow. 2,640 ties were laid to the mile, and the

track ballasting kept well up with the laying; so well, in fact, and so

well done, that as 100 mile sections were completed schedule trains were

put on 20 miles an hour, and the operating department had nothing to do

but make a time table; the road was _built_ by the construction department

before the operating department was asked to take it. The engineering was

organized in divisions of 30 miles each, and as each was finished the

parties moved ahead again to the front, the engineers usually finding men

sitting on their shovels waiting for the work to be laid out for them. It

was as much as the locating parties could do to keep out of the way of the

construction. The roadbed was built 14 ft. wide in embankment and 20 in

the very few cuts there were, there being no cuts of any moment except

through the Coteaus and the Saskatchewan crossing, and these have since

been widened out on account of snow, so that the road can be operated the

year round and the bucking-snow account cut no figure in the operating

expenses.

The country is a virgin desert. From Winnipeg to the Pacific Ocean there

are a few places that might attain to the dignity of an _oasis_--at

Brandon, Portage la Prairie, etc.--but it is generally what I should call

worthless; 100 miles to wood and 100 feet to water was the general

experience west of the Moose jaw, and the months of June, July, and August

are the only three in the year that it is safe to bet you will not have

sleighing. I burned wood and used stakes that were hauled by carts 85

miles, and none any nearer. It is a matter of some pride that both the

engineering and the construction were done by what our Canadian neighbors

kindly termed "Yankee importations." However, there was one thing that in

the building of this road was in marked contrast to any other Pacific road

ever constructed, that is, there was no lawlessness, no whisky, and not

even a knock-down fight that I ever heard of the whole season, and even in

the midst of 12,000 Indians, all armed with Winchester rifles and plenty

of ammunition, not one of the locating or construction parties ever had a

military escort, nor were any depredations ever committed, except the

running off of a few horses, which were usually recovered; and I think

there were but two fatal accidents during the season, one man killed on

the Grand Coule Bridge, and another from being kicked by a horse.

The track was all laid from one end, and in no case were rails hauled

ahead by teams. Two iron cars were used, the empty returning one being

turned up beside the track to let the loaded one by.

The feat in rapid construction accomplished by this company will never be

duplicated, done as it was by a reckless expenditure of money, the orders

to the engineers being to _get there_ regardless of expense and

horse-flesh; if you killed a horse by hard driving, his harness would fit

another, and there was no scrutiny bestowed on vouchers when the work was

done; and I must pay the tribute to the company to say that everything

that money would buy was sent to make the engineers comfortable. It was

bad enough at best, and the Chief Engineer (J.C. James) rightly considered

that any expense bestowed on the engineering part of the work was a good

investment.

* * * * *