CHAPTER II.

_Preliminary Studies and Investigations._

The preliminary studies and investigations which should be made prior

to the construction of any dam for the storage of water have to do with

(1) the Catchment Area, (2) the Reservoir basin, and (3) the Dam site.

Catchment Area.

It is thought desirable to define a number of terms as we proceed,

for the purpose of correcting erroneous usage and for a clearer

understanding of the subject. The catchment area of a reservoir is that

portion of the country naturally draining into it. The watershed is

the boundary of the catchment area and may be correctly defined as the

divide between adjacent drainage systems. In regard to the catchment

area it is necessary to determine:

1. Its extent and area in square miles.

2. Its topography or the character of its surface.

3. Its hydrography or precipitation and run-off.

4. Its geology, or the character of its soils and subsoils,

and the nature and dip of its rock strata.

5. Its flora, or the extent to which it is clothed with forest

trees or other vegetation.

All of these elements affect the volumes of maximum run-off, which is

the one important factor in the construction of earth dams that must

not be underestimated.

If the proposed dam or reservoir is to be located upon a main drainage

line; that is, upon a river or stream, it is necessary to know both the

flood and low-water discharge of the stream. Frequently no reliable

data on this subject are available, and the engineer must then make

such a study of the whole situation as will enable him to estimate the

minimum and maximum flow with considerable accuracy.

There are numerous factors entering into the solution of this first

problem, such as the shape and length of the catchment area, its

general elevation, the character of its surface, whether mountainous,

hilly or flat, barren or timbered.

Good topographic maps, if available, furnish valuable data on these

subjects and it is to be regretted that only a comparatively small

portion of the United States has been thus mapped in detail.

The results of stream measurements, if any have been made in the

catchment basin, are especially important: These are usually few in

the high areas, on account of their inaccessibility. The year 1902

marked a notable beginning of such measurements in California. In many

parts of the arid region of the United States, the best storage-sites

are situated in the upper or higher portions of the drainage systems.

This is especially true of the streams on the Pacific Slope having

their source in the High Sierras. As regulators of stream-flow and for

power purposes such storage is peculiarly valuable, while storage for

irrigation and domestic uses may be located nearer the valleys and the

centers of population.

Frequently the engineer is required to build his dam where no such

data are available. In such instances he should endeavor to secure

the establishment of rain gauges and make measurements of the flow of

the main stream and its principal tributaries at various places to

obtain the desired information. Even this may not suffice, owing to the

limited time at his disposal, and he must resort to the use of certain

empirical rules or formulas, and make such comparisons and deductions

from known conditions and results as will best answer his purpose.

The engineer should know, approximately at least, the normal yield of

the catchment area, the duration of the minimum and maximum seasonal

flow, and the floods he may have to provide against during the

construction of his dam. These data are absolutely necessary to enable

him to provide ample wasteways for his reservoirs. Many of the failures

of earth dams have been the result of over-topping the embankment,

which would have been averted by an ample wasteway. The most notable

example of this kind in recent years was that of the South Fork Dam, at

Conemaugh, Pennsylvania, in 1889, resulting in what is generally known

as the “Johnstown Disaster.”

There are several empirical rules and formulas for calculating the run

off from catchment areas and for determining the size of spillways

necessary to discharge this flow with safety to the dam. The proper

formula to apply in any given case, with the varying coefficients

of each, involves a thorough knowledge on the part of the designing

engineer of the principles upon which the different factors are based.

It is unwise and often hazardous to make use of any important hydraulic

formula without knowing the history of its derivation. Experiments

are not always properly conducted, and often the deductions therefrom

are unreliable. A presentation and discussion of these formulas would

require more space than can be given in this study, and the technical

reader must therefore consult for himself, as occasion may require, the

various authorities cited. Formulas for the discharge or run-off from

catchment areas, as determined by Messrs. Craig, Dickens, Ryves and

others, are given by most writers on the subject of hydraulics.

Reservoir Basin.

The next subject of inquiry relates to the reservoir basin. It is

necessary that its area and capacity at different depths should be

definitely known, and this information can only be obtained by having

the basin surveyed and contoured. A map should be made showing contours

at intervals of 2 to 10 ft., depending upon the size of the basin and

the use to which the reservoir is to be put. Reservoir basins have been

classified according to their location as follows:

1. Natural lakes.

2. Natural depressions on main drainage lines.

3. Natural depressions on lateral drainage lines.

4. Arbitrary and artificially constructed basins.

Natural lakes may need to be investigated more or less thoroughly to

determine the character of their waters, whether saline, alkaline

or fresh. It may also be necessary to know their normal depth and

capacity, and to make a study of their outlet if they have one. In some

instances the storage capacity of a lake may be enormously increased by

means of a comparatively low and inexpensive embankment.

The area of reservoir basin, mean depth, temperature of the water,

exposure of wind and sunshine, losses by seepage and evaporation, all

have a bearing upon the available water supply and influence the design

of the dam and accessories to the reservoir.

In determining the character and suitability of materials for

constructing a dam it is necessary to make a careful study of the

soil and geological formation. This is best accomplished by digging

numerous test pits over the basin, especially in the vicinity of the

proposed dam site; borings alone should never be relied upon for this

information. For such an investigation the advisability of borrowing

material for dam construction from the reservoir basin is determined.

The porous character of the subsoil strata, or the dip and nature of

the bed rock, may forbid the removal of material from the floor of the

basin, even at a remote distance from the dam site.

The area to be flooded should be cleared and grubbed more or less

thoroughly, depending again upon the use for which the water is

impounded. In no instance should timber be left standing below the

high-water level of the reservoir; and all rubbish liable to float and

obstruct the outlet tunnel and spillway during a time of flood should

be removed.

The accessories to a reservoir, to which reference has been made, may

be enumerated as follows:

1. Outlet pipes or tunnel.

2. Gate tower, screens and controlling devices.

3. Sluiceways for silt or sand.

4. Wasteway channel or weir.

5. Cover, settling basin, aerating devices, etc.

Some of these are necessary and common to all classes of reservoirs,

while others are employed only in special cases, as for domestic water

supplies. All reservoirs formed by earth embankments must have at least

two of these, namely a wasteway, which is its safety valve, and outlet

pipes or outlet tunnel.

It may be stated that the proper location and construction of the

outlet for a reservoir are of vital importance, since either to

improper location or faulty construction may be traced most of the

failures of the past. It is almost impossible to prevent water under

high pressure from following along pipes and culverts when placed in an

earth dam. The pipes and culverts frequently leak, and failure ensues.

Failure may result from one or more of the following causes:

1. By improper design and placement of the puddle around the pipes.

2. By resting the pipes upon piers of masonry without continuous

longitudinal support.

3. By reason of subsidence in the cuts of the embankments and

at the core walls, due to the great weight at these points.

4. Leakage due to inherent defects, frost, deterioration, etc.

Mr. Beardsmore, the eminent English engineer who built the Dale Dyke

embankment at Sheffield which failed in 1864, and who was afterwards

requested to study and report upon the great reservoirs in Yorkshire

and Lancashire, said, after examination and careful study of reservoir

embankment construction, that “in his opinion there were no conditions

requiring that a culvert or pipes should be carried through any portion

of the made bank.” The writer would go even further and say that the

only admissible outlet for a storage reservoir formed by a high earth

dam is some form of tunnel through the natural formation at a safe

distance from the embankment.

Dam Site.

The third preliminary study (that relating to the dam site itself) will

be considered under three heads:

1. Location.

2. Physical features, materials, etc.

3. Foundation.

LOCATION.–The location for a dam is generally determined by the use

which is to be made of it, or by the natural advantages for storage

which it may possess. If it be for water power it is very frequently

located upon the main stream at the point of greatest declivity. If for

storage it may be, as we have seen, at the head of a river system, on

one of its tributaries, or in a valley lower down.

The type of dam which should be built at any particular locality

involves a thorough knowledge, not alone of the catchment area and

reservoir basin, but also accurate information regarding the geology of

the dam site itself. It would be very unwise to decide definitely upon

any particular type of dam without first obtaining such information.

Too frequently has this been done, causing great trouble and expense,

if not resulting in a total failure of the dam.

The conditions favorable for an earth dam are usually unfavorable for a

masonry structure, and vice versa. Again, there may be local conditions

requiring some entirely different type.

Dams situated upon the main drainage lines of large catchment areas are

usually built of stone or concrete masonry, and designed with large

sluiceways and spillways for the discharge both of silt and flood

waters. It need scarcely be remarked that, as a rule, such sites are

wholly unsuited to earthwork construction. It is said, however, that

“every rule has at least one exception,” and this may be true of those

relating to dam sites, as will appear later under the head of new

types.

In a general way, the location of high earth dams is governed by the

configuration of the ground forming the storage basin. It may not be

possible, however, to decide upon the best available site without

careful preliminary surveys and examinations of the geological

formation.

All earth dams must be provided with a wasteway, ample to discharge the

maximum flood tributary to the reservoir. Whatever type of wasteway be

adopted, no reliance should ever be put upon the outlet pipes for this

purpose. The outlet should only figure as a factor of safety for the

wasteway, insuring, as it were, the accuracy of the estimated flood

discharge. The safety of the dam demands that ample provision be made

for a volume of water in excess of normal flood discharge. This most

necessary adjunct of earth dams may be an open channel, cut through

the rim of the reservoir basin, discharging into a side ravine which

enters the main drainage way some distance below the dam. It may be

necessary and possible to pierce the rim by means of a tunnel where its

length would not prohibit such a design. Lastly, there may be no other

alternative than the construction of an overfall spillway, at one or

both ends of the embankment. This last method is the least desirable of

any and should be resorted to only when the others are impracticable;

even then, the volume of water, local topography, geology, and

constructive materials at hand must be favorable to such a design. If

they are not favorable it may be asked, “what then?” Simply do not

attempt to build an earth dam at this site.

PHYSICAL FEATURES, MATERIALS, ETC.–An investigation of the location

and the physical features of the dam site should include a careful and

scientific examination of the materials in the vicinity, to determine

their suitability for use in construction. An earth embankment cannot

be built without earth, and an earth dam cannot be built with safety

without the right kind of earth material.

Test pits judiciously distributed and situated at different elevations

will indicate whether there is a sufficient amount of suitable

material within a reasonable distance of the dam. The type of earth

dam best suited for any particular locality, and its estimated cost,

are thus seen to depend upon the data and information obtained by

these preliminary studies. Economical construction requires the use of

improved machinery and modern methods of handling materials, but far

more important even than these are the details of construction.

FOUNDATION.–We may now assume that our preliminary studies relating to

the location and physical features of the dam site are satisfactory.

We must next investigate the foundation upon which the dam is to be

built. This investigation is sometimes wholly neglected or else done in

such a way as to be practically useless. To merely drive down iron rods

feeling for so-called bed rock, or to make only a few bore-holes with

an earth auger should in no instance be considered sufficient. Borings

may be found necessary at considerable depths below the surface and

in certain classes of material, but dug pits or shafts should always

be resorted to for moderate depths and whenever practicable. Only by

such means may the true character of the strata underlying the surface,

and the nature and condition of the bed rock, if it be reached, become

known. If a satisfactory stratum of impermeable material be found it is

necessary also to learn both its thickness and extent. It may prove to

be only a “pocket” of limited volume, or if found to extend entirely

across the depression lengthwise of the dam site it may “pinch out”

on lines transversely above or below. Shafts and borings made in the

reservoir basin and below the dam site will determine its extent in

this direction, knowledge of which is very important.

Fig. 1, showing a longitudinal section of the site of the Yarrow Dam of

the Liverpool Water-Works, England, illustrates the necessity of such

investigation. A bore hole at station 2 + 00 met a large boulder which

at first was erroneously thought to be bed rock. The hole at station 3

+ 50 met a stratum of clay which proved to be only a pocket.

The relative elevation of the different strata and of the bed rock

formation, referred to one common datum, should always be determined.

These elevations will indicate both the dip and strike of the rock

formation and are necessary for estimating the quantities of material

to be excavated and removed, including estimates of cost. They furnish

information of value in determining the rate of percolation or

filtration through the different classes of material and the amount

of probable seepage, as will appear later. The cost of excavating,

draining and preparing the floor or foundation for a dam is often very

great, amounting to 20 or 30% of the total cost.

Fig. 2 is a transverse section of the Yarrow Dam. This particular dam

has been selected as fairly representative of English practice and

of typical design. It is one of the most widely known earth dams in

existence.

[Illustration: FIG. 1.–LONGITUDINAL SECTION OF YARROW DAM SITE.]

[Illustration: FIG. 2.–CROSS-SECTION OF YARROW DAM.]

At the Yarrow dam site it was necessary to go 97 ft. below the original

surface to obtain a satisfactory formation or one that was impermeable.

A central trench was excavated to bed rock, parallel to the axis of the

dam, and filled with clay puddle to form a water-tight connection with

the rock, and prevent the water in the reservoir from passing through

the porous materials under the body of the embankment. This interesting

dam will be more fully described later, when the different types of

earth dams are discussed.