VETO MESSAGES.

EXECUTIVE MANSION, _Washington, April 4, 1888_.

_To the House of Representatives_:

I return herewith without approval House bill 2477, entitled "An act for

the relief of Nathaniel McKay and the executors of Donald McKay."

It is proposed by this bill to allow the beneficiaries named therein to

present to the Court of Claims for determination certain demands made

by them against the Government on account of the construction of two

ironclad monitors called the _Squando_ and the _Nauset_ and a

side-wheel steamer called the _Ashuelot_.

The contracts for building these vessels were made early in 1863. It was

agreed that they should be completed within six or eight months. It was

also provided in these contracts that the Government "should have the

privilege of making alterations and additions to the plans and

specifications at any time during the progress of the work, as it may

deem necessary and proper," and that if said alterations and additions

should cause extra expense to the contractors the Government would "pay

for the same at fair and reasonable rates."

It thus appears that the time allowed for the completion of these

vessels was with the assent of the contractors made exceedingly short;

that notwithstanding this fact they consented to permit such alterations

of plans as must almost necessarily prolong the time, fixing no limit to

such extension, and that in the same breath they fix their measure of

compensation for such alterations and an extended time consequent

thereon at "a fair and reasonable rate" for the extra expense caused

thereby.

Almost immediately upon the beginning of their work alterations and

changes were made in the original plans for these vessels, and they were

repeated and continued to such a degree that the completion of the

vessels was delayed many months.

In the latter part of the year 1864 and early in the year 1865 payments

in excess of the contract price were made by the Navy Department to the

contractors under the provisions of the contract above recited. The

contract price for the _Squando_ was $395,000. The contractors

claimed extra compensation amounting to $337,329.46, and there was

allowed $194,525.70. The contract price of the _Nauset_ was

$386,000, the extra compensation claimed was $314,768.93, and the amount

allowed $192,110.98. The contract price of the side-wheel steamer

_Ashuelot_ was $275,000, the extra compensation claimed was

$81,447.50, and the amount allowed was $22,415.92. The different sums as

thus adjusted were received by the contractors in settlement of their

claims for extra expense, and receipts in full were given by them to the

Government.

A number of other contractors had done like work for the Government and

claimed to have demands growing out of the same for extra compensation.

Evidently with the view of investigating and settling these claims, on

the 9th day of March, 1865, the Senate passed the following resolution:

_Resolved_, That the Secretary of the Navy be requested to organize

a board of not less than three persons, whose duty it shall be to

inquire into and determine how much the vessels of war and steam

machinery contracted for by the Department in the years 1862 and 1863

cost the contractors over and above the contract price and allowance

for extra work, and report the same to the Senate at its next session;

none but those that have given satisfaction to the Department to be

considered.

This board was appointed by the Secretary of the Navy on the 25th

day of May, 1865, and consisted of a commodore, a chief engineer,

and a paymaster in the Navy. Its powers were broad and liberal, and

comprehended an inquiry touching all things that made up "the cost to

the contractors" of their work in excess of the contract price and

allowances for extra work.

The board convened on the 6th day of June, 1865, and sat continuously

until the 23d day of December following, and made numerous awards to

contractors. The parties mentioned in the bill now under consideration

were notified on the 9th and 15th days of June, 1865, to prepare and

submit testimony to the board in support of their claims, and they

repeatedly signified their intention to do so.

Donald McKay was the contractor for the construction of the monitor

_Nauset_ and the steamer _Ashuelot_. The proceedings of the

board show that on the 11th day of August, 1865, he notified the board

that the only claim he made for loss was on the hull, boiler, and

machinery of the _Ashuelot_, which he would be prepared to present

in about six weeks.

Neither of these parties presented any statement to the board, and no

claim of theirs was passed upon.

On the 2d day of March, 1867, an act was passed directing the Secretary

of the Navy to investigate the claims of all contractors for building

vessels of war and steam machinery for the same under contracts made

after May 1, 1861, and before January 1, 1864. He was by said act

required "to ascertain the additional cost which was necessarily

incurred by each contractor in the completion of his work by reason of

any changes or alterations in the plans and specifications required and

delays in the prosecution of the work occasioned by the Government which

were not provided for in the original contract." It was further provided

that there should be reported to Congress a tabular statement of each

case, which should contain "the name of the contractor, a description of

the work, the contract price, the whole increased cost of the work over

the contract price, and the amount of such increased cost caused by the

delay and action of the Government as aforesaid, and the amount already

paid the contractor over and above the contract price."

Under this act Commodore J.A. Marchand, Chief Engineer J.W. King, and

Paymaster Edward Foster, of the Navy, were designated by the Secretary

of the Navy to make the investigation required. These officers on the

26th day of November, 1867, made a report of their proceedings, which

was submitted to the Senate with a tabulated statement of all the claims

examined by them and their findings thereon.

It appears by this report that the claims of the beneficiaries mentioned

in the bill herewith returned were examined by the board, and that

nothing was found due thereon under the terms of the law directing their

examination.

These claims have frequently been before Congress since that time. They

have been favorably reported and acted upon a number of times, and have

also been more than once strongly condemned by committees to whom they

were referred.

A resolution was passed in 1871 by the Congress referring these and

other claims of a like character to the Court of Claims for

adjudication, but it was vetoed by the President for reasons not

necessarily affecting the merits of the claims.

The case of Chouteau _vs_. The United States, reported in Fifth

Otto, page 61, which arose out of the contract to build a vessel called

the _Etlah_, appears to present the same features that belong to

the claims here considered. It is stated in the report of the House

committee on this bill that "the _Squando_ and _Nauset_ were

identical in the original plans and the changes and alterations thereon

with the _Etlah_ and _Shiloh_, built in St. Louis;" and yet

the Supreme Court of the United States distinctly decided in the

_Etlah_ case that the only pretext for further compensation should

be sought for in the contract, where the contractor had evidently been

content to provide for all the remedy he desired.

It seems, then, that the contractors mentioned in this bill, after

entering into contracts plainly indicating that changes of plans and

consequent delay in their work were in their contemplation, availed

themselves of the remedy which they themselves had provided, and

thereupon received about 50 per cent in the case of two of these vessels

of the contract price for extra work, giving the Government a receipt in

full. When soon thereafter opportunity was offered them to make further

claim of as broad a nature as they could desire, they failed to do so,

and one of them disclaimed any right to recover on account of one of the

vessels, though all are now included in the present bill. In 1867 the

claims were fully examined under a law of Congress and rejected, and the

Supreme Court in an exactly similar case finds neither law nor equity

supporting them.

If it be claimed that no compensation has been yet allowed solely for

the increase in the price of labor and material caused by delay in

construction, it is no hardship to say that as the contractors made

provision for change of plans and delay they must be held to have taken

the risk of such rise in price and be satisfied with the provision they

have made against it. Besides, much of the increase in the price of

labor and material is included in the extra cost which has already been

reimbursed to them.

But the bill does not provide that these contractors shall be limited in

the Court of Claims to a recovery solely for loss occasioned by increase

of the cost of labor and material during the delay caused by the

Government. By the terms of the proposed act the court is directed to

ascertain the additional cost necessarily incurred in building the

vessels by reason of any changes or alterations in the plans and

specifications and delays in the prosecution of the work. This, it seems

to me, would enable these contractors to open the whole question of

compensation for extra work.

It hardly seems fair to the Government to permit these claims to be

presented after a lapse of twenty-three years since a settlement in full

was made and receipts given, after the opportunity which has been

offered for establishing further claims if they existed, and when, as a

consequence of the contractor's neglect, the Government would labor

under great disadvantages in its defense.

I am of the opinion, in view of the history of these claims and the

suspicion naturally excited as to their merit, that no injustice will be

done if they are laid at rest instead of being given new life and vigor

in the Court of Claims.

A Compilation of the Messages and Papers of the Presidents. Volume 8, part 3: Grover Cleveland, First Term · 第 520 / 872 题