CHAPTER XLI

WIRING OF BUILDINGS

In laying out the circuits for a dwelling house, the cut out cabinets

should be located first. In many houses only one cut out cabinet is

necessary, but in large houses it is convenient to have one on each

floor, with vertical mains running through them from the top to the

bottom of the house.

If only one distributing point be used, it should be either in the

cellar or attic and risers run to the different floors.

=Ques. How should the distributing centers or cut out cabinets be

located?=

Ans. They should be installed near a partition that is so located as

to make the running of risers easy, and should be on an inside wall to

guard against dampness.

=Ques. What instructions are usually given the electrician who does the

wiring?=

Ans. In many cases simply a plan showing the location and number of

lights, from which he must figure out how to install them using the

least amount of material and labor consistent with a good installation

that will pass inspection.

=Ques. What provision should be made in rooms where lamps are suspended

from the ceiling?=

Ans. A switch should be placed at a point where it will be convenient

for any one entering to turn on the light.

=Ques. Where are receptacles usually placed?=

Ans. In the baseboard.

A receptacle is a convenient device which permits any one to

connect a lamp to the electric lighting system by inserting a

plug which is connected by flexible cord to the lamp.

[Illustration: FIG. 991.—Ceiling button. If a lamp be needed not more

than 3 feet from the direct line of the wires, it can be hung where

required by means of a _ceiling button_, as shown in the figure, but

the lamp cord must not be used to run lamps in this way more than two

or three feet from the rosette.]

=Ques. What provision should be made in wiring a hallway?=

Ans. The switching arrangement should be so designed that the lights

may be turned on or off either from the hall or floor above.

=Ques. What is this arrangement called?=

Ans. _A two way switch_, as shown in fig. 992.

=Ques. How can a two way switch be distinguished?=

Ans. It has three binding screws, two on one end and one on the other.

[Illustration: FIG. 992.—Two way lighting circuit permitting control

from two points. This is the usual arrangement for hall when it is

desired that the lights may be turned on or off from either floor. The

circuit contains two two way switches connected by "travellers." From

the diagram it is seen that the light may be controlled from either

switch. It is a bad arrangement to have travellers and return wire

located near each other, as it is possible by this method to connect

two individual circuits together and possibly overload one of the two

feed wires of each circuit. However, should each feed wire run to a

fuse direct, without any other lamps than those contained in the three

way circuit being connected, it is not objectionable and becomes a

convenient method in many cases.]

[Illustration: FIG. 993.—Four way lighting circuit, permitting

control from three points. This arrangement consists of a four way

switch connected between two two way switches as shown. In making the

connections it should be noted that the travellers connecting one side

of the four way switch to the two way switches should be crossed. On

the opposite side of the four way switch, the connections are direct.

For the various positions of the switches, the corresponding circuits

through them are as follows: ABDGHJ—ABDEIJ—ACFGHJ—ACFEIJ.]

=Ques. How may a group of lights be controlled from three points?=

Ans. By the use of a 4 way switch and two 2 way switches connected as

shown in fig. 993.

=Ques. Before laying out the wiring system for a building, what should

be done?=

Ans. It is necessary to ascertain whether power will be supplied from

the central station, or whether a private plant is to be installed.

[Illustration: FIG. 994.—Two wire multiple system as used with

isolated plant.]

=Ques. What wiring system should be used with a private or isolated

plant?=

Ans. The two wire multiple system as shown in fig. 994.

=Ques. When the central station is to supply power as an auxiliary in

case of break down, how should the connection be made?=

Ans. The supply from the central station should be connected to the

wiring system through a double throw switch, as in fig. 995, so that

either source may be thrown into circuit.

=Ques. How are the connections made when the auxiliary supply is

brought in through a three wire system?=

Ans. A double throw three pole switch is used as shown in fig. 995.

[Illustration: FIG. 995.—Double throw switch for use in isolated

plants when auxiliary power is used from the central station in case of

breakdown.]

=Ques. When power from an outside source only is to be used what must

be determined before wiring?=

Ans. The system of wiring of the supply. If a three wire system be

used, the general arrangement will be as shown in fig. 997.

[Illustration: FIG. 996.—Double throw three pole switch for use in

isolated plants where auxiliary power is brought in through three wire

system. The side of the switch controlling the current is bridged as

shown.]

=Ques. Would it be expensive to change a regular three wire system to a

two wire system?=

Ans. It would require the reinforcement of all mains and feeders by an

additional wire. This wire would be connected with the neutral wire so

as to make the capacity of the neutral equal to the sum of the other

two. If a three wire two wire system had been originally installed, no

change in the wiring system would be necessary. The only change would

be at the service end of the switchboard, and the doubling of the size

of the center fuses.

[Illustration: FIG. 997.—Three wire convertible, or three wire

two wire system; used to advantage where power is supplied from an

outside source and brought in through the three wire system. The only

difference between the three wire convertible, and the straight three

wire system is that the center, or neutral, wire of the mains and

feeders should have a current capacity equal to the other two. The

reason for this is that it allows the system to be readily changed

over to a two wire system for use in connection with a private plant.

It sometimes happens that after using power from the local electric

illuminating company for some time, conditions arise which make it

expedient for the owners to install a private electric plant. If a

straight three wire system had been originally installed, the mains and

the feeders when used on a two wire system would not be heavy enough

by 25 per cent., as the neutral wire of a straight three wire system

is the same in size as one of the two outer wires, and theoretically

carries one-half the current or less.]

=Ques. Is a three wire system desirable with an isolated plant?=

Ans. It is more expensive to install than one for a two wire system, as

it is necessary to add a balancer in connection with a 240 volt dynamo.

This balancer set should have one-tenth the capacity of the plant. Such

an equipment has its advantages when 240 volt motors and 120 volt lamps

are connected to the system. With this plant no changes in the motors

are necessary, whereas in a straight 120 volt system, the motors would

have to be changed from 240 to 120 volt machines.

[Illustration: FIG. 998.—Diagram showing reinforcement of neutral

wire necessary to change regular three wire system to two wire system.

The capacity of the neutral wire must equal that of the sum of the two

other wires.]

=Ques. After deciding on the system of wiring to be used, how should

the electrician proceed with the work?=

Ans. He should lay out the mains, feeders and branches of the wiring

system. The outlets are first located and then the distributing

centers. There is no fixed rule or plan by which to go, but the current

density and source of supply are the main points to be considered in

locating these centers. He must also consider the construction of the

building and select runways and shafts which provide easy runs for

feeders.

=Ques. How should panel boards be placed?=

Ans. Panel boards in loft buildings or in any building requiring 8

to 10 circuits to a floor should be distributed one to a floor. In

private houses it is sometimes advisable to install only one panel for

the entire house. This is good practice for a three-story house not

requiring over twelve circuits.

[Illustration: FIG. 999.—Diagram showing current required on each

floor of building. A sketch of this kind is useful in laying out the

feeder system. In the building here shown it will be seen that the

basement and first floor require the most power. In such a case a

feeder is run for these floors, and a sub-feeder from the basement

to the first floor. It is not worth while to reduce the size of the

sub-feeder unless the amount of current used on the sub-feeder be a

small percentage of that used in the feeder. Another reason is that

in changing the size of a wire, the underwriters require a fuse to be

inserted. This makes it necessary to install a larger panel with larger

trim, etc., and the consequent expense easily offsets any gain made by

installing a smaller wire.]

In a building covering a large area it is often advisable to

install two panels or centers to a floor, with two sets of

feeders. It is advisable to keep circuit lengths down to 100

feet or less, and the judicious laying out of circuit centers

will save many feet of wiring.

=Ques. How should the arrangement of feeders for a large building be

determined?=

Ans. A good method is to draw an elevation of the building as in fig.

999, and note on each floor the current requirements.

The best plan is to furnish a feeder for every floor,

especially in large installations. In smaller installations one

or two feeders are sometimes all that are required.

[Illustration: FIG. 1,000.—Diagram showing arrangement of switches in

wiring system where provision is made that any circuit can be fed from

an outside source in case of overload or accident.]

=Ques. How should feeders for motors be installed?=

Ans. They should be independent of the lighting feeders.

=Ques. What is the largest size of feeder that should be used?=

Ans. Feeders requiring over 2 inch pipe should not be used. It is

better to subdivide them, especially if there be many bends or offsets,

since two inch pipe is about the limiting size for economical handling.

=Ques. How should feeders be arranged?=

Ans. They should radiate from a distributing panel, having a proper

sized switch and fuse for each feeder.

If the system of wiring be such that auxiliary power is taken

from a local lighting company, it is a good plan to have each

circuit controlled by a double throw switch so that in case of

overload any circuit can be fed from the illuminating company's

mains as in fig. 1,000.

[Illustration: FIG. 1,001.—Sectional view showing method of cutting a

pocket or opening in floor for the insertion of wires.]

=Ques. How should feeders and mains be run?=

Ans. It is advisable to install them in iron pipe even though the

circuit wires be run otherwise. Since the former carry the main supply

of current it is important to have them well protected as they usually

run up side walls.

The underwriters make numerous restrictions against open or

moulding work on brick walls and require good protection, and

this is an additional reason for piping the mains and feeders.

=Ques. How much load should be placed on the branch circuits?=

Ans. In laying out the branch circuits, it is not good practice to use

up the underwriters' circuit allowance of 660 watts.

[Illustration: FIG. 1,002.—View of outlet pocket showing base board,

and cover supports in position.]

If a circuit be wired with the full allowance of lamps, no

additions could be made without violating the underwriter's

requirements.

=Ques. If concealed wiring is to be installed in a finished building

what should be done first?=

Ans. The outlets should be marked on the ceilings and walls with a

pencil cross at the spot, marking also the location of switches, etc.

=Ques. If an outlet is to be placed at the center of a room, how is the

center of the ceiling located?=

Ans. It is first located on the floor, then transferred to the ceiling

by means of a plumb bob.

=Ques. What is the first operation in making a ceiling outlet?=

Ans. A small hole is bored through the ceiling and the bit pushed up

till it comes in contact with the flooring of the room above, this

flooring is also bored, as in fig. 1,001.

[Illustration: FIG. 1,003.—View of completed pocket and ceiling outlet

showing method of bringing out the wires.]

A long bit about ¼ inch in diameter and about 18 inches long

is used. The hole bored in the floor above will show where to

take up the board to install the wires.

=Ques. How is a pocket opened above the hole bored for ceiling outlet?=

Ans. One-quarter inch holes are bored to insert a keyhole saw through

the joint between two boards at each end of the pocket, and as near

the beams as possible, then the board is cut at an angle as indicated

in fig. 1,001. Having sawed across the board at both ends, it is pried

out with a chisel as shown.

=Ques. How are the holes bored through the beams for the tubes?=

Ans. They are bored about two inches from the top with a 9/16 inch bit,

slanting downward just enough to give clearance for the brace.

[Illustration: FIG. 1,004.—Device for examining partition interiors. A

pocket flash lamp and a little mirror are the only apparatus required

to inspect the interior of a wall or partition which would ordinarily

be inaccessible. For fishing wires, retrieving cable and inspecting

finished work, the lamp and mirror will be found most useful. The

mirror has only to be introduced in the outlet hole in the wall, the

flash lamp and eye being held behind it as illustrated. The mirror

reflects the light of the lamp onto the place to be illuminated, at

the same time reflecting the image back to the eye near the lamp. The

usefulness of this little device is as great as its simplicity.]

=Ques. How are the knobs fastened?=

Ans. Screws may be used but stout wire nails are satisfactory and are

inserted with less labor.

Leather nail heads are slipped on the nails to protect the

porcelain.

=Ques. How is a ceiling outlet completed after the work has reached the

stage shown in fig. 1,002?=

Ans. A baseboard is next installed as in fig. 1,003 to have a secure

hold for the screws used in fastening the fixtures. Two holes are then

bored diagonally with a 11/16 inch bit inserting the bit in the small

hole bored in the ceiling as in fig. 1,001. The outlet wires are then

tied around the knobs and the upper ends being bared and tapped on to

the main wire. A piece of loom is slipped on each outlet wire after

which it is thrust through the outlet as in fig. 1,003.

[Illustration: FIG. 1,005.—Plan showing one floor of a dwelling house

wired with conduits. The numbers on the various outlets indicate the

number of lamps supplied. The wiring is carried out on the loop system,

and it will be noticed that no branches are taken off between outlets.

Four circuits are used in order that there may not be more than ten

lamps on any one circuit.]

=Ques. How are the mains secured to the knobs?=

Ans. By taking a turn around the intermediate knobs and a dead end

hitch at the end knobs, or they may be hitched at each knob. The main

may be secured also by use of a tie wire.

=Ques. What is the difference between a splice and a tap?=

Ans. A splice is the joining of two wires at their ends; a tap is the

joining of the end of one wire with an intermediate point of another

wire.

[Illustration: FIG. 1,006.—Wiring for heating appliances in two story

house; plan of basement.]

=Ques. What precaution should be taken in making joints?=

Ans. All wires joined together should be soldered as this insures good

electrical contact.

Unsoldered wires are both unreliable and dangerous, since they

will corrode from dampness, thus increasing the resistance of

the joint so that it may become heated.

=Ques. How should joints be finished after soldering?=

Ans. They should be covered with rubber tape twisted tightly while it

is hot. When the rubber has melted it will adhere to the joint and

can be moulded with the fingers. Adhesive tape is then wound over the

rubber, the insulation thus being made equal to that which was removed

to unite the wires.

[Illustration: FIG. 1,007.—Wiring for heating appliances; plan of

first floor.]

=Wiring for Heating Appliances.=—There are now on the market a great

number of heating appliances which absorb such small amounts of energy

that they can be used readily on the lighting circuit. These appliances

include the coffee percolator, chafing dish, heating pad, small water

heater, cigar lighter and many other miscellaneous devices. By adapting

these smaller devices to the lighting circuit, not only is the cost of

wiring decreased, but the convenience and cleanliness of the electrical

system is secured.

[Illustration: FIG. 1,008.—Wiring for heating appliances; plan of

second floor.]

The location of the outlets for the heating appliances is not of the

least importance. For many purposes, the flush receptacle in the

baseboard of the room answers many requirements. In other places, for

instance, a receptacle placed beneath the bracket lamp in the bathroom

upon the same circuit as the lamp, is very convenient as a connection

for the electric shaving mug or the massage motor. Similarly, a

suitable outlet placed near the head of the bed is most convenient for

operating a heating pad as it does not necessitate unscrewing a lamp at

night.

The house illustrated in figs. 1,006 to 1,008 is an example of

the use of a single electric heating circuit with a restricted

use of the lighting circuit for heating purposes.

[Illustration: FIG. 1,009.—Diagram illustrating wiring with

combination of moulding, flexible tubing or conduit in non-fireproof

building, where wiring had not been originally installed. In such cases

the moulding may be run in a cornice in the hall. When objectionable to

have the work exposed in the rooms, taps may be made in the moulding

opposite each room and the circuit extensions from the moulding to the

center outlets in the rooms may be run in flexible conduit, fishing

the wires from the moulding to the ceiling outlet. The use of wooden

moulding in new buildings is not to be recommended for the reason

that it is not usually fireproof, and it would be better to run the

conductors concealed in some form of conduit; if the circuit work

were installed at the time the building is erected, it would cost but

little more than moulding, and would be much more substantial. In some

cases, however, wooden moulding might be provided in a new building on

the ceiling as a means of affording facilities for making connections

to outlets over desks, tables, etc., where it would be impossible to

locate the outlet exactly before the building was plastered. In such

cases, the moulding could be installed on the ceiling at a distance of

18 to 24 inches from the walls, forming a rectangle on the ceiling.]

[Illustration: FIG. 1,010.—Feeder system for large hotel. The cellar,

basement, and ground floors are supplied by separate feeders, because

of the importance of having continuous and uninterrupted lighting

service at these floors. The three distributing centers at the cellar

are supplied by a single feeder. Three of the eight distributing

centers at the basement floor serve to supply the outside lights, as

described above. The distributing center for the outside street lamps

is supplied by a separate feeder from the main switchboard. Five of

the distributing centers at the basement floor serve for the basement

lights only; they are fed by two separate feeders, one of which serves

two centers and the other three centers as shown. Each of the three

centers at the ground floor is supplied by a separate feeder. The

upper floors, from the first to the fourteenth inclusive, are divided

into two symmetrical sections. Each section has its own distributing

center, and its own set of supply feeders. The feeder terminates at

the middle center of a group of three, and is extended by mains to the

corresponding centers at the floors immediately above and below. Each

feeder from the first to the twelfth floor inclusive serves to supply

three distributing centers.]

As can be seen in the basement plan, the main supply circuit enters

the basement and from this the heating circuit and lighting circuits

branch, as shown by the arrows. The heating circuit runs direct to

the basement laundry, a branch running to the flat iron. Connections

are made with the kitchen on the first floor and with the dining room

by branch circuits running through the partitions to the respective

rooms. The heating circuit at the dining room is provided with flush

wall receptacles, to which connection is made for the chafing dish and

percolator.

In the kitchen the electric baking outfit is arranged as shown. This

electric outfit is used for auxiliary cooking, such as a gas range

would be, and the oven, placed by itself on the opposite side of the

coal range, is controlled from the main table.

Upstairs the heating circuit, upon which the dining room appliances

are operated, is extended to supply current to the electric luminous

radiator, either in the chamber or bathroom.

The arrangements for the lighting circuits are shown in the figures.

Landing and basement lights are controlled by three way switches to

make them convenient.

In the living room a flush floor receptacle is installed so that the

reading lamp, chafing dish or coffee percolator can be operated without

necessitating the use of a long cord. A few of the electrical outlets

suitable for the purposes mentioned are illustrated.

Where several heating circuits are used it is essential that an

appliance taking a large current be not placed on the regular lighting

circuit. To guard against this possibility, special receptacles should

be installed, constructed for plugs which will not fit any other

receptacle.

Hawkins Electrical Guide v. 04 (of 10) Questions, Answers, & Illustrations, A progressive course of study for engineers, electricians, students and those desiring to acquire a working knowledge of electricity and its applications · 第 6 / 11 章