Cost

The approximate cost of the chimney can be determined by using actual

local cost of materials and wages as follows:[F]

6,100 brick at $15.00 per thousand $91.50

27 sacks of cement[G] at $0.70 per sack 18.90

16 bags of lime at $0.50 per bag 8.00

5 cubic yards of sand[G] at $2.25 per cubic yard 11.25

1 cubic yard of gravel at $2.00 per cubic yard 2.00

98 hours, mason's time, at $1.00 per hour 98.00

49 hours, laborer's time,[H] at $0.30 per hour 14.70

28 linear feet of 8½- by 13-inch flue at $1.00 per foot 28.00

20 linear feet of 13- by 13-inch flue at $1.15 per foot 23.00

20 linear feet of 8½- by 8½-inch flue at $0.40 per foot 8.00

1 8-inch thimble .60

1 6-inch thimble .40

2 clean-out doors }

Damper, lintel mantel, ash dump} 65.00

-----

Total net cost [I] 369.35

[F] The prices used in this example are merely illustrative.

[G] Includes material for footing and cap.

[H] Includes labor for footing and cap.

[I] Where the chimney is built by contract, 10 to 15 percent should be

added for profit and overhead.