The total amount according to the several Acts is as follows:--

Under the Act of 1859,--

For 1,000 feet of heading, $50,000 00

Under Act of 1860,--

For balance of heading, say 2,588-1/2 feet, at $30 per foot, 77,655 00

For 91 feet of enlargement, at $20 per foot, 1,820 00

-----------

Total amount earned, $129,475 00

The amount of State scrip which under the statute had been earned by the

progress made in constructing the railroad may now be considered.

The first payment of $50,000 under the Act of 1854, should have been for

seven miles of completed railroad. The certificate of the engineer, upon

which it was paid, gave (see page 82 of House document No. 185 for

1860,) the length of rails laid as upwards of seven miles; nothing in

the certificate showed then any part of it was completed road, and upon

investigation then made it proved that while most of it was done, a part

near the west end of the tunnel "was not ten feet wide," and would cost

several thousand dollars to complete it. It is clear that this payment

had not then been earned in the manner provided by the statute.

The second payment was on account of the road, under the Act of 1859,

for grading three miles of road, "said three miles being all situated

within four miles of the point of commencement;" Page 30 of House

document No. 185 for 1860 says of this grading, "the continuous line is

interrupted by fourteen gaps of cuts and fills;" it is thus made up of

fifteen separate pieces, avoiding all but the cheapest part of the work,

and costing, as the contractor who did the work certifies, between

$8,000 and $9,000. Under, to say the least, a somewhat liberal

construction of the Act, $50,000 was said to have been earned by doing

this grading.

All further deliveries of scrip have been under the Act of 1860,

which provides that the $650,000 to be delivered on account of the

road east of the tunnel shall be in proportion to the progress made

upon the work. On page 15, (Senate document No. 93 for 1863,) the

cost of the work done and materials furnished upon the road east of

the tunnel is stated at $463,047 90

Deduct amount first expended, as testified by the contractor,

for which the $50,000 was paid, say 8,500 00

Amount expended under the $650,000 appropriation,

including the cost of worthless bridging and masonry, $454,547 90

The cost of completing the grading, bridging, masonry and

superstructure upon this part of the road, as estimated by

Mr. Laurie in 1862, was $370,970 80

Deduct the cost of a small change in the line, and of

embankment washed away by the Deerfield River, 5,275 00

Sum required to complete the road upon the old line

where the work stopped, $365,695 80

Report of the Hoosac Tunnel and Troy and Greenfield Railroad, by the Joint Standing Committee of 1866. · 第 49 / 51 题