D. N. CARPENTER, Esq., _President, pro tem., T. & G. R. R; Co._

DEAR SIR:--By a vote passed on the 7th of January last, I am requested

to return an estimate of the payments and credits to which H. Haupt &

Co. were entitled under their contract at the time of the suspension of

the work on the Troy and Greenfield Railroad.

The contract thus alluded to recites that "The compensation to be

allowed to H. Haupt & Co. shall be as provided in the resolutions of the

board of directors of the Troy and Greenfield Railroad Company, passed

July 10, A. D. 1857, to wit:

"The whole of the State bonds that may be issued in aid of the Troy and

Greenfield Railroad Company shall be exclusively appropriated to work

done, or to be done, upon the tunnel, in compliance with the terms and

conditions of the Act authorizing the loan of credit; and any State

scrip that may,' at any time, be delivered to the treasurer of the

company shall be promptly handed to the contractors.

"The payments for graduation, bridging, masonry, and superstructure of

the road, exclusive of the tunnel, shall be two millions of dollars,

with the addition of such sums as may be required for right of way, if

this item shall be paid by the contractors. Of this amount, nine hundred

thousand dollars shall be in the mortgage bonds of the company, and the

balance shall be in cash, to as great an extent as cash subscription can

be procured; the remainder in stock, at par.

"The bonds and stock of the Troy and Greenfield Railroad Company shall

be issued to H. Haupt & Co. whenever required, but not to a greater

extent than they would be entitled to receive for the work done,

estimating' it by the proportion which it bears to the whole amount done

and to be done."

This contract is so clear and precise in its terms that but one

construction can be placed upon it, though it is evident that such terms

were predicated upon a different state of affairs than existed at the

time of suspension. By this contract, all State payments are to be

exclusively appropriated to the work on the tunnel, while the stock and

bonds are as exclusively devoted to the graduation, bridging, masonry,

and superstructure of the railroad. The amount of compensation the

contractors would thus be entitled to, is the issue of State scrip from

July 10th, 1857, to the time of suspension, and the $2,000,000 of stock

and bonds, less the amount required to finish the railroad. From this

must be deducted such payments as may have been made from time to time,

concerning which I have no data, but which your treasurer's books must

show. Any sums that may have been paid by the contractors for right of

way, are to be added to the amount due.

The cost of finishing the railroad must be estimated. For the road east

of the tunnel, my estimate of the cost of finishing was, September 12,

1861, $102,394; to this we should add one-half mile of railroad and

bridge over the Deerfield, $20,000. For the unfinished portion west of

the tunnel, I have no data of my own; I have, therefore, taken for the

purpose the estimate of D. L. Harris, which is the highest I can

find--$40,000.

We thus have as the cash cost of completing the graduation, masonry,

bridging, and superstructure of the road, $162,394, which is to be

deducted from the $2,000,000 of stock and bonds, leaving the amount the

contractors are entitled to, $1,857,606, less payments made, plus the

amount of right of way, &c.

This is in exact accordance with the strict construction of the contract

which I previously have remarked was predicted upon a different

condition of affairs than existed at the time of suspension.

I deem it my duty in this connection respectfully to suggest whether, in

view of the changes made in the issue of State scrip, which was paid

upon the road as well as upon the tunnel, the contractors should not

make proper reductions of the stock and bonds due them, taking into

consideration as an offset to this such losses as they have been

subjected to by the adverse action of the State authorities. This

suggestion, however, is volunteered. My duty under the vote of the board

is simply to decide what amount the contractors are entitled to receive

under an exact and literal construction of the contract.

Report of the Hoosac Tunnel and Troy and Greenfield Railroad, by the Joint Standing Committee of 1866. · 第 44 / 51 题