The working force at the West Shaft in July was,--

Engine-men and firemen, 4

Carpenters, 2

Blacksmith and helpers, 8

Masons, 2

Truckman, 1

Pump-man, 1

Manual laborers, 105

---

Total, 123

November 1st the working force at this point,

including one resident civil engineer, was 103

At this point there is one engine of 100-horse power and one of 40-horse

power, and one compressor having four cylinders of a diameter of 13

inches and 24 inches stroke. The West heading from this shaft was

advanced 293 feet, and the East heading 1,042, on the first day of

December, 1866. The progress for the year ending November 1, 1866, at

the heading at this point was 636.7, being a fraction over 53 feet per

month. For the last four months, ending December 1, 1866, the progress

was 322.1, being a fraction over 64 feet per month, which exceeds by

four feet per month the highest estimate for hand-drilling by the

engineers in 1862, and by thirty and one-third feet the estimate of Mr.

Latrobe. The progress of the work at this heading during the last six

months, making allowance for the influx of water in November, having

exceeded the highest estimate for hand-drilling, should be regarded as

evidence alike of the skill of the miners and the good management of the

engineer and his subordinates.

_Table showing the progress at West Shaft, East Heading, from November

1, 1865, to December 1, 1866._

=======================================

DATE. Distance from Progress,

shaft, feet. feet.

---------------------------------------

Nov. 1, 1865, 367.5

Dec. 1, 1865, 414.4 46.9

Jan. 1, 1866, 459.4 45.0

Feb. 1, 1866, 503.0 43.6

Mar. 1, 1866, 546.5 43.5

April 1, 1866, 584.8 38.3

May 1, 1866, 623.3 38.5

June 1, 1866, 682.1 58.8

July 1, 1866, 746.1 64.0

Aug. 1, 1866, 810.5 64.4

Sept. 1, 1866, 871.4 60.9

Oct. 1, 1866, 945.4 74.0

Nov. 1, 1866, 1,004.2 58.8

Dec. 1, 1866, 1,042.0 37.8

=======================================

The West heading at this shaft was at first driven 6 feet by 11. It has

been found advisable to enlarge it to the dimension of 10 feet 6 inches

by 15 feet. This work has been performed by contract. The first letting

was at the rate of four dollars per cubic yard, the State furnishing the

materials used and removing the stone. The contractors at this rate

could not pay their expenses. It was raised to six dollars per yard

which was found not to pay, and in July the price was advanced to seven

dollars and fifty cents. The State pay the men, charging the same to the

contractors, and keep their time. Good progress is made and the work is

done to the satisfaction of the engineer.

The East heading at this point was being enlarged also by contract, from

6 feet by 15, to 10-1/2 by 15. The work commenced on the 15th of July,

1866; the price paid is seven dollars per cubic yard; the contractors

load their own stone and also that coming from the heading. The State

provides the materials used, and hoist the stone to the surface. While

the work of the miners at the East heading and of the contractors upon

both enlargements was progressing in a very satisfactory mariner, the

whole was arrested by an unexpected and somewhat sudden influx of

Report of the Hoosac Tunnel and Troy and Greenfield Railroad, by the Joint Standing Committee of 1866. · 第 23 / 51 题