The force employed at this point in July last was--

Mechanics in iron, 4

Engine-men, 2

Masons, 10

Manual labor, 58

Engine and compressor men, including firemen, 6

Carpenters, 5

Blacksmiths and helpers, 8

Statisticians, 2

Runners of machine-drills, 6

Sawyer, 1

Manual laborers, 63

---

Total in July, 165

The first day of November there were employed here 115 men. There are

at this point, besides the shops and saw mill above mentioned, 2 small

offices, 1 boarding-house, 2 carpenters' shops, 2 powder-houses,

1 temporary blacksmith's shop, 1 temporary horse-stable, 3 sheds,

1 engine-house, 1 barn, 1 instrumental station-house (all used by the

State,) and 2 cottages; 6 first-class shanties, 13 common shanties,

10 temporary shanties, 1 store under school-room; with 1 cottage,

1 old store and 8 shanties, built by H. Haupt & Company, which are

rented. The cost of the shanties at the East End, excluding the

Deerfield Dam, was, in July, 1866, . . . . . . . $28,052 94

In November, 1866, . . . . . . . 31,688 99

The rents at the East End received by the State

from shanties are, . . . . . . . 1,698 00

per annum. All rents are collected monthly.

A resident engineer was stationed at the East End in charge of the work.

The progress of the excavations at the East End heading for the year

ending December, 1866, has been 569 feet; at the rate of 47.42 per

month.

The progress during the six months ending May, 1866, was 338 feet; an

average per month of 56 feet 4 inches. One week was lost in June in

introducing the machine-drills, in consequence of which the progress

that month was reduced to 50 feet 6 inches. During the five months

ending November 30, the progress has been 219-1/2 feet; being an average

of 43.9 feet per month. It will be seen by the table, that in July, the

first month after the introduction of the drill machines, the progress

attained was only 26.5 feet. As the men became better acquainted with

them, the progress was increased to 48 feet in August, and in September

it rose to 54.5, having nearly attained the average progress of the six

months preceding their introduction. Had there been an adequate supply,

there can be little doubt that the progress would have continued to

increase, and would have shown the superiority of the machine-drill over

hand-labor; but the supply fell off, and the progress in October was

reduced to 34 feet and 6 inches.

_Table showing the progress at East End Heading, from November 1, 1865,

to January 1, 1867._

===========================================

| Distance from | Progress.

DATE. | Portal. |

----------------+---------------+----------

Nov. 1, 1865, | 2,839.0 |

Dec. 1, 1865, | 2,904.0 | 65.0

Jan. 1, 1866, | 2.950.5 | 46.5

Feb. 1, 1866, | 3,005.0 | 54.5

Mar. 1, 1866, | 3,052.0 | 47.0

April, 1, 1866, | 3,115.0 | 63.0

May 1, 1866, | 3,176.5 | 61.5

June 1, 1866, | 3,227.0 | 50.5

July 1, 1866, | 3,253.5 | 26.5

Aug. 1, 1866, | 3,301.5 | 48.0

Sept. 1, 1866, | 3,356.0 | 54.5

Oct. 1, 1866, | 3,394.5 | 38.5

Nov. 1, 1866, | 3,431.0 | 36.5

Dec. 1, 1866, | 3,473.0 | 42.0

===========================================

Report of the Hoosac Tunnel and Troy and Greenfield Railroad, by the Joint Standing Committee of 1866. · 第 19 / 51 题