The captain at the shafts four times a month reports,--

The days' work of the engine-men.

The revolutions of the engine.

Number of pounds of coal used.

of feet of wood used.

of gallons of sperm oil used.

of gallons of kerosene oil used.

of pounds of tallow used.

of pounds of waste used.

of pounds of tar used.

of cages raised.

of cars of stone raised.

Size of pump-plunger used.

Length of stroke.

Number of strokes.

of gallons of water raised.

of boilers in use.

The materials furnished for the construction of the work are charged in

their distribution to twenty-three accounts, as will be seen by the

tabular statement of its cost. Requisitions for materials are signed by

the immediate overseer, captain or foreman; they are handed to the

superintendent for approval, and by him forwarded to the engineer. If

the requisition is approved by both, the materials are ordered, and when

furnished the applicant signs upon a duplicate his receipt for the same.

This course is pursued as well for materials taken from the State lands

as for those purchased. Suitable blanks for returns, requisitions, &c.,

are furnished to the several points, and the evidence of all the

transactions is preserved in the office of the engineer. In addition to

the above, a return of all material broken, or laid aside, is made to

the engineer, at whose office a substantial account of all materials on

hand, either in use, or out of use, may be found.

The organization of the working force, and the mode adopted for supplies

and expenditures at the various points, appear well adapted to an

efficient and economical prosecution of the enterprise.

Report of the Hoosac Tunnel and Troy and Greenfield Railroad, by the Joint Standing Committee of 1866. · 第 17 / 51 题