[Illustration]
To be healthy, stock need exercise—in winter as well as summer. But
few farms are provided with an exercise lot sufficiently well protected
against winter blasts to provide a safe exercising place.
The exercise lot should be located on the warm side of the buildings.
Erect the wind wall on the side from which the winter storms most often
come. Probably the most convenient way to build the wall will be in
sections of 10 feet in length. The wall will be 3 inches thick at top,
12 inches thick at the base, 7 feet above and 3 below ground, with the
slope side toward exercise lot.
To securely brace the sections of this wall, large posts (called
buttresses) are needed. These posts are the full height of the wall
and are 12 by 18 inches square. The narrow side is set with the line
of fence, and the buttresses are placed 11 feet apart from center to
center. The forms for these buttresses are the same as for gate
posts, with the exception that a beveled 2 by 4-inch timber is nailed
vertically to the inside of each side wall of the form, 3 inches from
the back board. This leaves a slot in the finished buttress, into
which the slab sections of the wall are later “keyed.” Through these
2 by 4’s, at points 3 and 15 inches below the tops, bore ⅝-inch holes
through which ½-inch reinforcement rods will be placed and allowed to
project into the wall proper about 18 inches.
[Illustration]
Locate the points for the centers of the buttresses, the first buttress
at the beginning of the wall. Dig a hole for each buttress 12 by 18
inches and 4 feet deep and erect the buttress forms. Fill the forms
with wet concrete, mixed 1: 2: 4. Do not forget to insert at the
proper time the 3-foot lengths of ½-inch rods in the ¾-inch holes
above mentioned. Brace the forms securely, to keep them in position.
After the first two buttresses are in place, dig out the 1 by 4-foot
foundation trench and, over it and between the buttresses, erect the
box forms for the slab sections, with the sloping side next to the lot.
These forms are made of 1-inch siding nailed to 2 by 4-inch studding
securely braced at bottom and tied together by cross-pieces at the top.
On the working side, add the siding as needed, so as to facilitate the
placing of the concrete.
Remove the side forms for buttress just before placing the forms for
wall proper. In the center of wall, within 6 inches of the top, embed a
10-foot length of ½-inch iron rod. After the wall is one week old, take
down the wall forms, erect them between the next two buttresses, and
proceed with the construction in the same manner.
Wind walls are often made with straight sides. While this takes more
concrete, the saving in erection of forms probably offsets this
additional cost.
The materials required for each 10-foot section of wall and 1 buttress
are two cubic yards crushed stone or screened gravel, 1 cubic yard
sand, 12 bags of Portland cement. Approximate cost, $15.00.
[Illustration]