The Manger

[Illustration]

As soon as the floor of three stalls has been concreted and while the

concrete is yet green, build the concrete manger wall upon the new

stall floor. The projecting 7 inches of the 2 by 12-inch board already

in place serves as the outer wall form. “Toe nail” two 1 by 6-inch

boards together at their edges, thus providing a 7-inch height for the

other manger wall form and a bearing plate to rest on the green stall

floor. Set this wall form so as to leave a 6-inch space for the manger

wall. Cross-brace these wall forms upon each other and if necessary

drive an occasional nail through the bearing plate into the new

concrete. Fill the space between the forms with concrete, setting the

stanchion fasteners at the same time. Continue in the same manner until

the stall floors are finished. If desired, the back wall of the manger

may be given a dish shape for a swinging stanchion.

[Illustration]

Then commence the work on the other side of the barn, constructing the

floor of the alleyway and stall in exactly the same manner.

Concrete Construction for the Home and the Farm · 第 81 / 131 题