TABLE III.

-------------------+------------------------------------------------

| QUANTITIES OF MATERIAL IN 1 CU. FT. OF CONCRETE

+---------+--------------+-----------------------

MIXTURE | Cement, | Sand, | Stone or Gravel,

| Barrel | Cu. Yard | Cu. Yard

-------------------+---------+--------------+-----------------------

1 : 2 : 4 Concrete| .058 | .0163 | .0326

1 : 2½ : 5 Concrete| .048 | .0176 | .0352

-------------------+---------+--------------+-----------------------

=Example=

Suppose the work consists of a concrete silo requiring in all 935 cubic

feet of concrete, of which 750 cubic feet is to be 1: 2: 4 concrete,

and 185 cubic feet is to be 1: 2½: 5 concrete. Also enough sand and

cement is needed to paint the silo inside and outside, in all 400

square yards of surface, with a 1: 1 mixture of sand and cement. One

cubic foot of 1: 1 mortar will paint about 15 square yards of surface

and requires 0.1856 barrels of cement and 0.0263 cubic yards of sand.

=Solution, Etc.=

Concrete Construction for the Home and the Farm · 第 19 / 131 题