Handling of Materials

The storage space for all materials should be convenient to the

building, and where the team can reach it so that rehandling may be

avoided.

[Sidenote: Face Brick]

When face brick are delivered on the job, they should be

immediately compared with the sample, previously selected, for

color, size, and quality, to prevent any misunderstanding later

when they are laid in the wall. If shipped by freight, they

should be examined before being unloaded from the car. Face brick

should be stacked in neat piles, laid either on edge, face up and

protected with straw, or on their sides in such a way as to protect

the faces. Laborers, in carrying face brick to the mason, should

place them face up for the convenience of handling.

[Sidenote: Common Brick and Tile]

Except on large jobs, common brick are not usually stacked. They

are dumped in a pile which makes it easier to wet them down

thoroughly as explained later. Hollow tile should be stacked in

neat piles to prevent undue breakage, each size and shape being

piled separately.

[Sidenote: Lime and Cement]

Lump lime should always be stored in a covered box to keep it

dry. This box should have a hinged opening on one side, at the

bottom, from which the lime may be conveniently removed. Lump lime

should be slaked at least a week before used to allow for thorough

hydration and cooling. Hydrated lime and cement should be carefully

protected from the weather by stacking the sacks on planks laid on

the ground and by a covering of planks and tarpaulin.

[Sidenote: Sand]

The sand pile should be located as near the mortar box as possible

for convenience in handling. In case the sand needs screening, an

the sand pile should be located at such a distance from the mortar

box that when the sand is thrown through the sieve, it will form a

pile adjacent to the mortar box.

[Sidenote: Wetting Common Brick]

All brick, especially the softer grades of common brick, should be

thoroughly wetted just before being placed in the wall, but not

made so wet as to cause sliding on the mortar. The object of this

wetting is to prevent the bricks from absorbing moisture from the

mortar which must be allowed to dry slowly so as to obtain a good

bond. If they are laid dry, the bricks will quickly take up a

large amount of water from the mortar, preventing proper setting

and adhesion. Water increases the weight of brick and consequently

the labor of handling, so that some workmen are inclined to lay

them dry. This should not be allowed except in freezing weather,

when the conditions require quicker setting. Good mortar bond is

essential to a good wall.