CONSTRUCTION COSTS AND CONTRACTORS.

Everything is relative. Looking at the total, some may think that the

cost of the Industrial Canal is large. So it is--compared with the cost

of an irrigation ditch through a 20-acre farm. But comparing the cost

with the wealth it is invested to produce--has already begun to

produce--it dwindles to a mere percentage. And a comparison of

construction costs on the Industrial Canal with similar work done

elsewhere during the same time is very much in favor of the former.

Witness the following figures shown in the books of the engineering

department of the Dock Board:

Dredging, including the canal prism and the excavation of the sites of

the bridge foundations, siphon and lock, averaged .2784 cents a cubic

yard. The highest cost was in the lock section, from which 609,302

cubic yards were excavated at an average cost of .3796 cents a cubic

yard. On the siphon and Florida Walk bridge section, including two

other deep cuts, the 814,919 cubic yards excavated cost an average of

.2607 cents a cubic yard. On the Louisville & Nashville bridge section,

the 1,023,466 cubic yards excavated cost an average of .2363 cents a

cubic yard. From there to the lake, 1,673,787 cubic yards, the average

cost was .2411 cents. Dredging costs were below the original estimates

when labor and supplies were 50 per cent cheaper.

The 90,000 cubic yards of concrete in the lock cost an average of

$22.50 a cubic yard. This includes cost of material, mixing, building

forms, pouring and stripping forms. Mixing and pouring, from the time

the material was handled from the storehouse or pile, averaged $1.20 a

cubic yard. It would be hard to find cheaper concrete on a work of

similar magnitude anywhere, say the engineers.

On the siphon the concrete work cost more, because it was a

subterranean job, with elaborate shaping. The price there was $35 a

cubic yard, in place, including material and form work.

To drive the 17,000 bearing piles and 7,000 traveling piles on which

the lock is floated, cost an average of 15 cents a running foot. This

does not include the cost of the piling.

Construction steel cost .12 cents a pound, and erection around 4 cents.

These were standard prices.

The lock gates, weighing 5,285,000 pounds, cost $845,600, in place.

This does not include opening and closing machinery.

Three of the bascule bridges crossing the Canal, weighing 1,600,000

pounds each, cost $250,000 each, erected. The fourth bridge, near the

lock, weighing 1,000,000 pounds, cost $200,000, erected. This is for

superstructure only--it does not include the foundation.

The emergency dam bridge, weighing 350,373 pounds, and its 108,256

pounds of turning machinery, cost $96,728, in place. Hoisting machinery

cost $40,000 more.

The eight girders of the emergency dam, weighing 90 tons each, at $240

a ton, cost $172,800.

Machinery for working the ten lock gates, the eight filling gates, and

the six capstans--twenty-four 52-horse power electric motors--cost

$21,479, f.o.b. New Orleans.

The plant for unwatering the lock, consisting of one pump with a

capacity of 15,000 gallons a minute, and two with a capacity of 250

gallons each, cost, erected, $11,000.

Total mechanical equipment used on the Industrial Canal weighs 14,500

tons. Its cost, including power-house, electrical connections, etc., is

$1,516,000.

Plant and equipment for building the Canal, including locomotives,

cranes, piledrivers, dredges, tools, etc., cost $781,232. Depreciation,

up to February, 1921, is set at $266,874, leaving a balance of

$514,358, carried as assets. Much of this has already been sold, and

more will be disposed of.

Following are the firms that executed contracts on the Industrial

Canal:

The Industrial Canal and Inner Harbor of New Orleans History, Description and Economic Aspects of Giant Facility Created to Encourage Industrial Expansion and Develop Commerce · 第 31 / 35 题