it frequently cuts through the small watercourses which run from the
well to the fields. In such cases, either a syphon or a supplementary
well is provided at Government cost. If several watercourses, all from
the same well, are cut through, it is generally possible to combine them
for the purpose of the crossing. The wishes of the cultivators in this
matter are met as far as possible.
The procedure as regards laying out the line on the ground, digging
trial pits, correcting the line and preparing the estimate are the same
as for the case of a canal.
[Illustration: FIG. 13.]
10. =Best System of Distributaries.=--Let AB (Fig. 13) represent a
portion of a distributary, the irrigation boundary CD being two miles
from AB. In order to irrigate a rectangular plot ACDB, the main and
branch watercourses would be arranged somewhat as shown by the full and
dotted lines respectively. Generally, the whole supply of the main
watercourse would be sent in turn down each branch, the other branches
being then dry. The average length open is AGE. The ends of the branches
lie on a line drawn say 200 feet from the lines BD and DC, since it is
not necessary for the watercourses to extend to the outside edges of the
fields. Within the field there are small field watercourses which
extend to every part of it. By describing three rectangles on AC, making
AB greater than, equal to and less than AC, it can be seen that the
average length of watercourse open is least--relatively to the area of
the block--when AB is equal to AC, i.e., when the block served by the
watercourse is square as in the figure. If AB is 4 times AC, the average
length of watercourse open is increased--relatively to the area of the
block--in about the ratio of 3 to 2. Moderate deviations from a square
are of little consequence.
Suppose two parallel distributaries to be 4 miles apart, each of them
being an average Indian one, say sixteen miles long with a gradient of
one in 4,000, and side slopes of ¹⁄₂ to 1, the bed width and depth of
water at the head being respectively 13·5 feet and 2·9 feet, and at the
tail 3 feet and 1 foot. The discharge of the distributary, with N =
·0225, will be 72 c. ft. per second. The discharge available for the 2
mile strip along one bank will be 36 c. ft. per second. If the duty is
300 acres per c. ft. the area irrigated in this strip will be 10,800
acres, or 1,350 acres for each of the eight squares like ACDB. Each main
watercourse would then have to discharge 4·5 c. ft. per second.
Supposing its gradient to be 1 in 4,000 and its side slopes ¹⁄₂ to 1 and
N to be ·0225, its bed width would be 3 feet and depth of water 1·45
feet. Its wet border would be 6·3 feet, and its average length 5280√2 +
5280 - 200 or 12,546 feet. Its wetted area would be 79,040 square feet,
and the total wetted area of the 16 watercourses--on the two sides of
the distributary--would be 1,264,640 square feet. The wetted border of
the distributary itself is 19·5 feet at the head and 5 feet at the tail,
average 12·25 feet, and its wetted area is 5,280 × 16 × 12·25 or
1,034,880 square feet.
If the distributaries were two miles apart, there would be twice the
number of distributaries, and each square would be one square mile
instead of four. Each watercourse would have to discharge 1·125 c. ft.
per second. It would have a bed width of 2 ft., depth of water ·8 ft.,
wet border 3·8 feet, length 6,173 feet, and wetted area 23,457 feet. The
total wetted area of the 64 water courses would be 1,501,248 square
feet, or 18 per cent. more than before. Each distributary would
discharge 36 c. ft. per second, the bed width and depth at the head
being 10 feet and 2·24 feet, and at the tail 2 feet and ·75 feet. The
wet border at the head and tail would be 14·5 and 3·5 feet, mean 9 feet,
and the wetted area of the two distributaries would be 1,520,640 square
feet or 50 per cent. more than before. Supposing that, in the case of
the larger distributary considered above, the 2-mile square was
considered too large, and that rectangles 1 mile wide were adopted, so
that the watercourses were a mile apart, their number would be doubled
and their length and size reduced. Their total wetted area would not be
greatly affected, but the difference in the wetted areas of the two
small distributaries as compared with the one large one, would be the
same as before. In practice, of course, distributaries are not always
parallel, nor are the blocks of irrigation all squares, and frequently,
owing to peculiarities in the levels of the ground or the features of
the country, or the boundaries of villages, it is necessary to align the
watercourses in a particular manner, or to construct more than one
watercourse where one would otherwise have sufficed, but the above
calculations show in a general way the advantages of large watercourses
and of not placing the distributaries too near together.
It is commonly said that a watercourse discharging more than 4 or 5 c.
ft. per second is objectionable because the cultivators, if there are
too many of them on one watercourse, cannot organize themselves in order
to work it and keep it in order. This matter is much exaggerated. On the
inundation canals of the Punjab a watercourse often discharges 10 c. ft.
per second, and is several miles long and requires heavy clearances, but
the people have no particular difficulty in managing it. Kennedy, a
great authority on questions of irrigation, states that the length of a
watercourse may be three miles. This, if the angle made by a watercourse
with the distributary is 45°, gives rather more than two miles as the
width of the strip to be irrigated.
Suppose that a distributary instead of being two miles from each side of
the irrigated strip, ran along one side of it, and was four miles from
the other side. If the block were square, as before, the side of a
square would be 4 miles, and each watercourse would have to discharge 18
c. ft. per second, which is far too much. The blocks would have to be
rectangles, each being only one mile wide measured parallel to the
distributary. It has been already seen that the length of watercourse in
this case is greater than when the block is square and each side is two
miles. Thus centrality in the alignment of the distributary is an
advantage.
A minor distributary has been defined (CHAPTER II., Art. 3) as being one
discharging not more than 40 c. ft. per second, but the term has come to
be used to designate a branch of a major distributary, and in that sense
it will be used in this article. When the shape of the area commanded by
a distributary is such that watercourses exceeding 2 miles in length
would otherwise be required, one or more minors are often added.
Frequently it is a question whether to let some of the watercourses be
more than two miles long, or to construct a minor and thus shorten the
watercourses to perhaps only one mile. Which method is best has not been
definitely settled. It is known that the loss of water in watercourses
is heavy, but if a minor is added the loss in it has to be considered.
The loss must be high in any channel in which the ratio of wet border to
sectional area is small. The minor also costs money in construction and
in maintenance. On the whole the matter, as far as concerns cost and
loss of water, is, perhaps, almost evenly balanced, but as regards
distribution of the supply a system without minors is preferable. The
off-take of a minor is generally far from the canal, i.e., in a more or
less out-of-the-way place, and it is impossible to see that the
regulation is properly carried out. Irregularities and corruption are
sure to arise. Even if the supply is fairly distributed as between the
minor and the distributary it is almost certain that the regulator, if a
double one, will be manipulated for the illegal benefit of outlets in
the distributary upstream of the bifurcation. There are sure to be some
such outlets not very far distant. In any case each minor adds one, if
not two, to the already very large number of gauges which have to be
entered daily in the sub-divisional officer’s register (CHAPTER III.,
Art. 3), and adds also to the mileage of channel to be inspected and
maintained. These considerations should, in many cases, though of course
not in all, turn the scale against the construction of a minor. At one
time it became usual to construct minors even when watercourses more
than two miles long would not otherwise have resulted. This custom was
condemned some years ago, and is not likely to be re-established. Most
of the difficulties just mentioned can, in the case of a minor which is
not too large, either absolutely or relatively to the main distributary
downstream of the off-take, be got over by making the minor head like a
watercourse outlet, building it up to the proper size, removing the
regulating apparatus and abolishing the reading of the gauge, but in
this case the minor is not likely to be bigger than a large watercourse.
Such minors should not be constructed, and any existing ones should,
after the head has been treated as above, be made over to the people and
considered as watercourses.
11. =Outlets.=--The top of the head and tail walls of an outlet are
level with the F.S. levels in the distributary and watercourse
respectively. The steps in the head wall enable the cultivators to go
down either to stop up the outlet or to remove any obstruction. The
stepping is arranged so as to fall inside the side slope ultimately
proposed. It is usual, in some places, to have the entrance to the
“barrel” of the outlet made of cast iron. The cast iron pieces are made
of various standard sizes. This to some extent prevents the “barrel”
being built to a wrong size. A discrepancy between the size of the
masonry barrel and that of the iron would be noticed, but if the masonry
barrel is built too large the iron head does not always restrict the
discharge. The action is the same as in a “diverging tube” well known in
hydraulics.
For sizes up to about 50 or 60 square inches the barrel should be nearly
square. For larger sizes the height should exceed the width. Up to
about 100 or 120 square inches the width can be kept down to 7 or 8
inches so that an ordinary brick can be laid across to form the roof.
For larger outlets the height can be from 1·5 to 3 times the width, and
the roof can be made of large bricks, concrete blocks or slabs of stone
or of a flat arch of brickwork or by corbelling, but in this last case
there should be two complete courses above the top of the outlet. The
less the width the cheaper the roof, the easier the adjustment of size
and the less the tendency to silt deposit during low supplies. If pipes
are used they should be laid in concrete. If cast iron head pieces are
to be used there should be several sizes of one width and the widths of
the masonry outlets should be made to suit these widths.
A masonry outlet is not generally built till the watercourse has been
sometime in use. The exact position of the outlet should then be so
fixed that the watercourse shall run out straight or with a curve and
should not be crooked.
The width between parapets should be, for a driving road or one to be
made into such, 10 ft. (if the bank is wider, it should be narrowed just
at the outlet site) and for a non-driving road, 8 feet to 3 feet
according to the ultimate width of the bank. Earth backing should be
most carefully put in and rammed, otherwise a breach may occur and the
outlet be destroyed.
Various attempts have been made to provide gates or shutters for
outlets. The chief result has been trouble and increased cost. If
grooves are made and shutters provided, the shutters are soon broken or
lost by the people. Hinged flap shutters are objectionable because they
are often closed by boys or by malicious persons or by neighbours who
wish to increase the supply in their own outlet. The cultivator, when he
wishes to reduce the supply or to close the outlet, can easily do this
by obstructing the orifice with a piece of wood or an earthenware vessel
or a bundle of brushwood or grass.
As regards temporary outlets, wooden outlets if large (unless made of
seasoned wood and therefore costly) are liable to give great trouble.
Water escapes round the outside or through the joints. Pipes may do well
if laid in puddle but are brittle and costly if of large size. The
irrigators may interfere both with wooden outlets and pipes and they are
liable to be displaced or broken. A temporary outlet, if small, can be
made of bricks laid in mud. The joints can be pointed with lime mortar.
When the outlet is made permanent the same bricks are used again. But
all kinds of temporary outlets are liable to give trouble especially in
light or sandy soil. There is much to be said in favour of building
masonry outlets at the first, making a barrel only, _i.e._, omitting the
head and tail walls and taking the chance of having to alter the size.
The alteration is not very expensive. The head and tail walls are built
when the size has been finally settled. The adjustment can be made by
raising or lowering the roof. This should be done over the whole length
of the outlet but lowering can be done temporarily over a length of 3
feet at the tail end of the outlet. This can be done even when the
distributary is in flow. A reduction over a short length at the upstream
end of a barrel does not, as already remarked, necessarily reduce the
discharge much.
On inundation canals the rules regarding outlets have to be modified.
Great numbers of watercourses take off directly from the canals. In such
cases, especially near the head of a canal, the ground to be watered is
often 5 to 8 feet above the canal bed and it is wholly unsuitable to
place the outlet at bed level. The cost of the tail wall would be
excessive. The floor level in such cases must be at about the lowest
probable cleared bed level of the watercourse, say, in order to be safe,
a foot or half a foot below the usual cleared bed of the watercourse, so
that water need never be prevented from entering the watercourse. The
irrigators should be consulted as to the floor level and their wishes be
attended to as far as possible. For lift outlets the floor should be at
the bed level of the canal or distributary. If this bed is to be raised
in the course of remodelling, the floor should be at the old bed level
until the bed has actually been raised, unless there is a weir which
raises the water. It is necessary that lift outlets should work however
small the canal supply may be. In a distributary or small canal, the
head wall should be built up to F.S. level but in a canal with deep
water the head wall should reach up to just above the roof of the outlet
and be submerged in high supplies. The stepping of the head wall should
be set back if the channel is to be widened and should project into the
channel if the channel is to be narrowed. The centre line of the channel
near the outlet site must always be laid down and the outlet built at
right angles to it and also at the correct distance from it.
Occasionally there is a wide berm, say 20 ft. or even 50 ft., between a
channel and its bank. In such a case the outlet should be built to suit
the bank. The long open cut is however objectionable because the people
clear it and heap the spoil in Government land. Sometimes the bank,
especially if it is crooked, can be shifted so as to come close to the
channel at the outlet site. Sometimes the outlets on inundation canals
are large. For outlets of more than 2·5 square feet in area, grooves
should be provided so that the cultivators can use a gate if necessary.
12. =Masonry Works.=--The positions and descriptions of all the masonry
works of a proposed canal or distributary are of course shown on the
longitudinal section of the channel and from this the discharges and
water levels are obtained. The principles of design to be followed[19]
for bridges, weirs, falls, regulators and syphons, are discussed in
_River and Canal Engineering_. It is mentioned that there is no special
reason for making the waterway of a regulator exactly the same as that
of the stream, and that the waterway may be such as to give the maximum
velocity considered desirable, and that the foundations of a bridge
should be made so deep that it will be possible to add a floor, at a
lower level than the bed of the stream--with the upstream and downstream
pitching sloping up to the bed--so as to increase the waterway and so
save pulling down the bridge in case the discharge of the channel is
increased. It remains to consider certain points affecting Irrigation
Canals.
[19] So far as concerns their capacity for dealing with flowing water.
The span of a bridge, where there are no piers, is generally made as
shown by the dotted lines in Figure 14, so that the mean width of
waterway is the same as that of the channel. The arches, in Northern
India, used at one time to be 60° as shown by the upper curved line, but
in recent years arches of 90° as shown by the lower curved line, have
frequently been adopted, the springing of the arch being below the F.S.
level, so that the stream is somewhat contracted. The 90° arch gives a
reduced thickness and height of abutment. It causes increased
disturbance of the water, and this may necessitate more downstream
protection. An advantage of having the springing not lower than the F.S.
level is that this admits of a raising of the F.S. level in case the
channel is remodelled, and this arrangement is still common on
distributaries.
[Illustration: FIG. 14.]
When a fall and bridge are combined, the bridge is placed below the fall
as this gives a lower level for the roadway. The side walls of the fall
are produced downstream to form those of the bridge.
The roads in India are generally unfenced and the banks of canals close
to bridges, on both sides of the canal and both above and below the
bridge, are generally more or less worn down by cattle, which, when
being driven home in the evening and out to graze in the morning, go
down to the stream to drink. In order to prevent this damage the banks
are sometimes pitched, above the bridge as well as below it, but the
cattle generally make a fresh “ghát” further away. The best plan is to
allow a “ghát” on one bank either above or below the bridge and to
protect the other three places.
In the Punjab the widths of roadways between the kerbs and parapets of
bridges respectively have been fixed as follows:--
--------------+----------------+-------------------
KIND OF ROAD.| NEAR TOWNS.[20]|IN THE COUNTRY.[21]
--------------+------+---------+--------+----------
|Kerbs.|Parapets.| Kerbs. | Parapets.
--------------+------+---------+--------+----------
Provincial | 22 | 23·5 | 16 | 17·5
District | 18 | 19·5 | 14 | 15·5
Village | 14 | 15·5 | 8·5 | 10
--------------+------+---------+--------+----------
[20] The figures show the maximum. The general width should be the
same as for neighbouring bridges on the same road.
[21] The parapets should be whitewashed so as to be visible at night.
[Illustration: FIG. 15.]
Fig. 15 shows a head regulator for a distributary. The scale is 10 feet
to an inch. It has a double set of grooves for the insertion of the
planks with which the regulation is effected. Only one set of grooves is
ordinarily used, but when the distributary has to be closed for silt
clearance and all leakage stopped, both sets of grooves can be used and
earth rammed in between the two sets of planks. The floor is shown a
foot lower than the bed of the distributary. This reduces the action of
the water on the floor, and enables the bed of the distributary to be
lowered if ever the occasion for this should arise. This is a good
rule--in spite of the fact that in re-modellings the tendency is for the
beds to be raised--for all regulators or bridges, a raised sill being
added (in regulators) to reduce the length of the needles or the number
of the planks. Such sill should, where needles are to be used, be fairly
wide, especially if regulation is to be done while the masonry is
somewhat new. The distributary shown has a bed width of 10 ft. The span
of the two openings in the head might have been four feet each, but are
actually five feet, and this enables the distributary to be increased in
size at any time. The pitched portion of the channel tapers. Unless
needles are used, instead of horizontal planks, spans are not usually
greater than 5 or 6 feet. Longer spans would give rise to difficulties
in manipulating the planks. Sometimes distributary heads are built skew,
but there is seldom or never any good reason for this. A curve can
always be introduced below the head to give the alignment the desired
direction.[22] The small circles shown on the plan are “bumping posts.”
On the left is shown a portion of the small raised bank at the edge of
the road.
[22] The curve can be quite sharp (see CHAP. I., Art. 2), and can be
made, if necessary, within the length of the pitching.
[Illustration: FIG. 16.]
Figure 16 is a double regulator with needles. The scale is 30 feet to an
inch. The spans are 15 feet. The roadway is on arches, but the
regulating platform on steel beams. The needles are seen at the upstream
sides of the regulators. They are worked from the platforms to which
access is obtained through the gaps in the upstream parapets. The
regulating platform should generally be only just clear of the F.S.
level, and therefore lower than the roadway.
[Illustration: NEEDLE REGULATOR AND BRIDGE.
Needles lying on Bank.
_To face p. 85._]
Frequently the roadway of a bridge or small regulator is carried, not on
arches, but on steel beams. The railings may be of wood or of gas pipe
with the ends plugged, running through angle iron posts. In the case
of such a regulator the roadway is sometimes so light that camels are
not allowed to cross over. This causes unnecessary hardship. Bridges are
not too numerous. If the regulation is done by gates, both road and
platform are carried on arches.
The regulators on inundation canals, and some on perennial canals, are
not strong enough to admit of the flow of water being entirely stopped,
so that the depth of water would be perhaps 10 feet upstream and nil
downstream. This might cause the overturning of the piers, or the
formation of streams under the floor. In such cases a maximum
permissible heading up is decided on. Such orders are, in India, liable
to be lost sight of in course of time, and they are, at least on
inundation canals, where sudden emergencies often occur, hardly
reasonable. An engine driver is not told that he must never entirely
close his throttle valve. Regulators should be so designed that the
water can be completely shut off.
The following remarks show the chief points in favour of needles and
horizontal planks respectively.
_Advantages of Needles._ Needles can be placed or removed by one man.
Needles do not require hooks, etc., which are liable to be broken or
lost.
A needle regulator requires few piers, and is therefore cheap.
Water falling over planks throws a strain on the floor.
Regulation with needles is easy and rapid. A jammed plank, especially
if low down and not horizontal, may give great trouble.
_Advantages of Planks._ Floating rubbish is not liable to collect
above the Regulator because the water flows over the planks.
By means of double grooves and earth filling, leakage can be quite
stopped.
For large works the advantages are generally with needles, but for small
works, _e.g._ distributary heads and shallow water, with planks. Needles
14 feet long are not too long for trained men. Planks are more likely
than needles to arrest rolling sand, and this can be taken into
consideration in designing double regulators. See number 8 of Kennedy’s
rules, Article 5. When planks are used there should be two sets of
grooves. Planks are very suitable for escape heads which have only
occasionally to be opened, earth being filled in between the two sets of
planks.
[Illustration: FIG. 16A]
Regarding notched falls, in the case of small distributaries the notches
are so narrow that they are extremely liable to be obstructed either
accidentally by floating rubbish or wilfully by persons whose outlets
are upstream of them. Weirs are not open to this objection, and are
frequently adopted. There is not the least chance of their causing any
silting worth mentioning. A simple weir if made of the proper height for
the F.S. discharge, will cause a slight heading up with ³⁄₄ths of the
F.S. discharge, and this unfairly benefits any outlets for a
considerable distance upstream of the weir. This difficulty can be got
over by making the weir as in Fig. 16A.
[Illustration: BRIDGE AND NOTCH FALL.
In this case the usual practice of placing the bridge downstream of the
fall has not been followed.
The gauge well is seen on the left bank.
_To face p. 87._]
For cisterns below falls the usual rule for the depth is
K = H + ∛H √D
where H is the depth of water in the upstream reach, and D is the
difference between the upstream and downstream water levels. Another
rule for distributaries is
H + D
K = -----
3
the length of the cistern being 3 H and its width the bed width of the
channel.
At “incomplete” falls, i.e., where the tail water level is above the
crest, it is not unusual to construct a low-level arch, which forms a
syphon. The object is to allay the surging of the surface water.
The question of skew bridges has been dealt with in Art. 3. Another
question is that of the heights of bridges. Irrigation channels,
especially the smaller ones, are very frequently at a high level, and
bridges have ramps which are expensive to make and to maintain, and are
inconvenient. The lowering of distributary bridges in such cases, so
that they become syphons, or nearly so, has often been advocated and is
frequently desirable. The bed should slope down to the floor and up
again. The heading up can be reduced by giving ample waterway, but it
will not be necessary to do this if there is head to spare. The fall in
the water surface can be recognised and shown on the longitudinal
section. The structure becomes one of the incomplete falls above
described. The crown of the arch can, if desirable, be kept above F.S.
level, so that floating rubbish will not accumulate.
The width between the parapets of a regulator can be 10 feet in the case
of a driving road. It may be less, according to the width of the bank,
in other cases.
The upper layer of the floor of a bridge or regulator is of brick on
edge. Below this there is a layer of brick laid flat, and below this,
concrete of a thickness ranging from ·5 feet to 3 feet. The thicknesses
of piers range from 1·5 to 3 feet.
The bricks used for canal work in Northern India are 10 inches long,
4⁷⁄₈ inches wide, and 2³⁄₄ inches thick. The thicknesses of walls are
about ·83, 1·25, 1·7, 2·1, 2·5 feet, and so on.
The slopes of ramps should be about 3 in 100 for district roads, and 5
in 100 for village roads.
Railings should be provided along the tops of high walls and top of
pitching near to public roads or canal patrol roads. Bumping posts
should be provided for all parapets, and should not be so placed as to
seriously obstruct the roadway.
The quarters for the regulating staff should, when convenient, be in the
fork between the two principal branches. They may be on the bank--with
foundations on pillars carried down to ground level--but not in such a
position as to obstruct the road or any road likely to be made. Rests
consisting of two parallel timbers bolted to blocks of masonry reaching
up a foot from the ground, should be provided for the needles or planks.
The bolt head should be countersunk so as not to damage the needles and
planks when they are hurriedly laid down.
When two or more works are close together they should be made to
conform, and the whole site should be considered with reference to a
neat and suitable arrangement of works, ramps and roadways. If an outlet
is near to a minor or distributary head the parapets of the two should
be in line. If two masonry works of any kind are near together it is
often suitable to pitch the intervening space. If there are outlets or
distributaries on opposite banks they should be exactly opposite each
other. Where a road crosses a bridge or regulator, the bank should be at
the same level as the road, the bank being gradually ramped back to its
original level. The space in front of any quarters should have a slight
slope for drainage, but otherwise be at one level and be connected with
the road or bank by proper ramps. The berm or bank should be made at the
exact level of the top of any pitching or side wall which adjoins it.
Wing walls are frequently made too short, so that the earth at their
ends forms a steep slope and is worn away, and the bank or roadway is
cut into. The walls should extend to such a point that the earth at
their ends cannot assume a slope steeper than the slope of the bank.
It is obvious that for every masonry work there should be a large scale
site plan[23] showing all roads, ramps, and adjoining works, both
existing and proposed roads being shown for some little distance from
the work.
[23] It is, or was until recently, in some parts of India, the custom
to omit the preparation of site plans, and to leave the fixing of the
exact site of a work and the arrangement of ramps and other details to
the judgment of the assistant engineer who was building it. Much
unsightly work resulted. A chief engineer in the Punjab recently
issued some orders on the subject.
For each kind of masonry work there is usually a type design. A few of
its dimensions, which are fixed, are marked on it. The other dimensions
are variable. It would be a great advantage to add to the design a
tabular statement to show how these dimensions should vary under
different circumstances.
[Illustration: FIG. 17.]
[Illustration: FIG. 18.]
13. =Pitching.= The object of pitching upstream of bridges or regulators
or downstream of bridges where there may be little or no scouring
action, may be partly to protect the bank from damage by cattle or wear,
or to prevent sandy sides from falling in. In such cases there may be
pitching of the sides only, and it may be of brick on edge laid dry and
under this one brick flat resting on rammed ballast (Fig. 17).
Downstream of regulators or weirs and downstream of bridges if
contracted or having piers which cause a rush of water, especially if
the soil is soft, the side pitching may be as above, but with the bricks
over one-sixth of the area placed on end and projecting for half their
length. This “roughened pitching” tends somewhat to reduce the eddying.
The bed protection should be solid concrete or blocks of concrete or
masonry. Immediately downstream of regulators or weirs where there is
great disturbance, both side and bed pitching may consist of solid
concrete or of concrete or masonry blocks (Fig. 18).
[Illustration: FIG. 19.]
Three kinds of toe walls are shown in Figures 17, 19 and 20. The kind
shown in Fig. 19 contains, for a given depth below the bed, far more
masonry than the one shown in Fig. 17. It is also liable to be displaced
and broken if scour occurs.
[Illustration: FIG. 20.]
The earth should in all cases be carefully cut to the proper slope, so
that no made earth has to be added. If the slope has already fallen in
too much, well rammed earth should be added. The flat brick and rammed
ballast can be varied as the work proceeds, more being used in soft
places and less in hard.
In some parts of the Punjab, large bricks, the length, breadth, and
thickness being about twice the corresponding dimensions of an ordinary
brick, are made, and are extremely useful and cheap for pitching. Where
the soil is sandy such bricks can be burned without cracking.
Sometimes the curtain wall which runs across the bed at the downstream
end of the pitching is carried into the banks and built up so as to form
a profile wall (Fig. 21). This is not very suitable, because the
pitching of the sides is apt to settle and leave the profile wall
standing out. It is better to lay a row of blocks on the slope. If a
hole tends to form in the bed downstream of the curtain wall, blocks of
masonry or concrete can be laid and left to take up their own positions
(Fig. 22).
[Illustration: FIG. 21.]
[Illustration: FIG. 22.]
When scour of the bed or sides occurs downstream of pitching, it is
sometimes said that any extension of the pitching downstream is followed
by extension of the scour. This may happen if the cross section of the
stream downstream of the pitched section has become greater than the
pitched section. In this case there is eddying, due to abrupt
enlargement of the stream where the pitching ends. The increased width
and lowered bed level (not counting mere local hollows) of the stream
should be adhered to in the pitching. Where the masonry of the regulator
ends and the pitching begins, there will be an abrupt or tapered
enlargement, but the eddies--at very low supplies there may be a
fall--cannot do harm.
This principle of enlarging the pitched cross section can be followed,
even in a new channel, if the soil is light and scour is feared, and for
this reason the matter is mentioned in the present Chapter instead of
in Chapter III. It was once the custom to splay out the sides of a
channel, downstream of a regulator or weir, so as to form a sort of pool
in which the eddies exhausted themselves, but this gives curved banks
and requires extra land and is not a very convenient or neat
arrangement. Where scour of the sides is likely to occur, or has
occurred, immediately downstream of the pitching the latter may be
turned in as shown in Fig. 23.
[Illustration: FIG. 23.]
Pitching has constantly to be replaced or extended owing, generally, to
failure to pitch a sufficient length or to ram well the earth under the
pitching, or to use properly rammed ballast or flat brick, or to give
proper bed protection, or to the use of dry brick pitching when a
stronger kind is needed.
The side slopes of pitching should be 1 to 1. They can be ¹⁄₂ to 1 in
rare cases, _e.g._, when there is no room for 1 to 1, or in continuation
of existing ¹⁄₂ to 1 pitching. No absolute rule can be laid down as to
the length to be pitched, but in a Punjab distributary it is often about
5 times the bed width.
14. =Miscellaneous Items.= On Indian canals the chainage[24] is marked
at every thousand feet. Five thousand feet is called a “canal mile.”
The distance marks are often cast iron slabs, fixed in a cylindrical
block of brickwork about 2·1 feet in diameter and 1·5 feet high, the
upper edge being rounded to a radius of ·4 feet. The wedge-shaped bricks
for these blocks are specially moulded. The iron slab should project
about eight inches and have about a foot embedded in the brickwork.
[24] In India, instead of the simple word “chainage” the term “reduced
distance” is used. It is the distance reduced to a common starting
point as levels are reduced to mean sea level. The expression is
puzzling to non-professionals and new comers.
On a canal having a wide bank the distance mark is put at the outer edge
of the patrol bank, earth being added, if necessary, to increase the
width. On a distributary with a narrow bank the mark should be on the
opposite bank not the patrol bank. To enable the miles to be easily
distinguished the masonry block can be sunk only ·5 foot in the ground,
the others being sunk a foot. In all cases the masonry block rests on a
pillar, 1·7 feet square, of bricks laid in mud, carried down to the
ground level.
Profile walls (Fig. 21, page 92) used occasionally to be built at
frequent intervals along a distributary. They will not prevent scour
occurring, if the stream is tending to scour, unless very close
together. Such walls are of some use as showing whether the channel is
altering, but they are expensive and have to be altered if, as often
happens, the channel is remodelled. It is a much better plan to lay down
blocks--about 1¹⁄₄ foot cubes--of masonry or concrete, along the centre
line at every 500 feet, with their upper faces level with the bed. If
the bed scours they may be displaced but otherwise they are useful not
only for showing what silt, if any, has deposited, but for showing the
centre line of the channel. Without them the centre line is liable to be
altered in silt clearances or berm cuttings. To enable a block to be
readily found and to be replaced in proper position if displaced, there
should be two small concrete pillars exactly opposite to it and
equidistant from it, one on either bank of the channel. Such blocks and
pillars may with advantage be placed at quite short intervals on curves.
The rest houses for the use of officials on tour are generally at
intervals of about 8 to 14 miles. There is generally a rest house near
to a large regulator and frequently there is one near to a small
regulator. This facilitates inspection work and discharge observations
and it saves money, because the house can be looked after by one of the
regulating staff. Not infrequently the house is placed just too far away
from the regulator. Similarly if a rest house is near a railway station
it should be within a quarter of a mile of it--always provided that this
does not bring it too near to villages or huts--and not a mile or more
away as is sometimes the case. It is also a mistake to place a rest
house off the line of channel unless perhaps when it is on a district
road which crosses the channel.
CHAPTER III.
THE WORKING OF A CANAL.
1. =Preliminary Remarks.= A large canal is under a Superintending
Engineer and it often constitutes his sole charge. It consists generally
of three to five “divisions,” each under an Executive Engineer. A
division has two to four subdivisions, each under a Subdivisional
Officer. A subdivision is divided, for purpose of engineering work and
maintenance, into several, generally three or four, sections, each
consisting of some 20 miles of canal and some 40 miles of distributary,
and being in charge of a native overseer or suboverseer, and for
purposes of water distribution and revenue, into a few sections each
having, perhaps, some 30,000 acres of irrigation and being in charge of
a native zilladar. As far as possible the boundaries of divisions and
subdivisions are co-terminous with those of the branches of the canal. A
distributary is always wholly within a subdivision. At every regulator
there is a gauge reader, who, supplied when necessary with permanent
assistants, sees to the regulation of the supply. If there is a
telegraph office at the regulator the telegraph “signaller” may have
charge of the regulation. The zilladar has a staff of some ten or twelve
patwaris, who record in books the fields watered and who are in touch
with the people and know when the demand for water is great, moderate or
small, and for what kind of crops it is needed. In each division there
is generally a Deputy Collector who is a native official, ranking as a
Subdivisional Officer. His duty is to specially supervise the revenue
staff in the whole division. Both he and the Subdivisional Officer have
magisterial powers which are exercised in trying petty cases connected
with the canal.
Along a main canal and its branches there is nearly always a “canal dak”
or system of conveyance of bags containing correspondence for the
officials stationed on the canal or touring along it. Along the main
line, and most of the way down the branches, there is a line of
telegraph for the special use of the canal officials. The telegraph
offices are at the chief regulators, with tapping stations, for the use
of officials on tour, at the rest houses near to which the line runs.
However carefully a canal has been designed, alterations in the channels
from silting and scour soon take place and they go on more or less
without cessation. In a distributary, especially if the gradient has of
necessity been made somewhat flat, there is quite likely to be a deposit
in the upper reach. The deposit is generally greatest at the head and
decreases, in going downstream, at a fairly uniform rate. It may extend
for half-a-mile or less or more. Or a deposit may occur on the sides,
which grow out and contract the channel. This often occurs over a great
length of a distributary or even over the whole of it. Sometimes a
distributary scours its bed, or the sides may fall in somewhat.
Clearances of the silt and cutting of the berms are effected at
intervals. Falling in of the sides may be stopped by means of bushing,
and scour of the bed may be stopped by raising the crest of a fall or by
introducing a weir, but in the meantime the changes cause the discharge
tables for the distributary to become more or less erroneous. In many
cases silt deposits in the upper part of the distributary during the
summer months when the river water is heavily silted and scours away
again in the winter, the régime of the channel being, on the whole,
permanent. The changes which occur in the branches and main canal are
similar to the above and the remedies adopted are similar. On some of
the older canals the scour was so serious that many intermediate weirs
had to be constructed. The remarkable silting in the head reach of the
Sirhind Canal has been described in _River and Canal Engineering_,
Chapter V. The remedy consisted in keeping the gates of the
under-sluices properly closed so that a pond was formed in which the
river silt deposited. When necessary the canal is closed, the sluices
opened, and the silt scoured away. For a plan of the headworks see fig.
24.
In working a canal, it is necessary to arrange so that the water sent
down any channel is as nearly as possible in accordance with the demand.
The zilladar supplies the Subdivisional Officer, every week or ten days,
with an “indent” showing how much water is required in each distributary
and the Subdivisional Officer makes indents on the subdivision next
above. The officer in charge of the headworks thus knows what the demand
is. When it is more than the supply available, the water is dealt out to
the various divisions according to rules approved of by the
Superintending Engineer of the canal.
[Illustration: FIG. 24.]
Every gauge-reader has to be given definite instructions as to the gauge
reading to be maintained, until further orders, in each distributary. At
the places where the large branches take off, the gauge reader is
instructed what gauge to maintain in each. In the event of too much
water arriving, he turns the surplus into the escape if there is one. If
there is no escape he has usually to raise the gauge readings of the
branches by equal amounts. By means of the telegraph, adjustment is
promptly effected at the headworks.
It has already been mentioned that rain may cause an abrupt reduction
in, or even cessation of the demand for water. At the same time it
increases the actual supply. Rain, or the signs of rain, in any part of
a canal system ought always to be reported to the other parts. Owing to
changes in the channels, to fluctuation in the water level of the river,
especially during the night, to rain or to changes in the temperature
and moisture of the air and to lack of continuous attention on the part
of the gauge reader, particularly at night, there is a constant, though
perhaps small, fluctuation in the water level in all parts of a canal.
It may happen that--owing to enlargement of the channels by scour, or to
other causes--the channels of a canal system are able to carry more
water than was intended. In such cases the channels are usually run with
as much as they can carry. This may give a lavish supply and a lowered
duty, but it increases the irrigated area. To restrict the supply would
cause loss of revenue. Sometimes however, it is restricted to prevent
water-logging of the soil. The proper procedure is to extend the canal
to other tracts.
In India the farmers pay for the water, not according to the volume
used, but according to the area irrigated. Different rates per acre are
charged for different kinds of crops according to the varying amounts
of water which they are known to require. Sugarcane, which is sown in
the spring and stands for nearly a year before being cut, thus extending
over the whole of the kharif and most of the rabi, is assessed at the
highest rate. Next comes rice which crop, though only four or five
months elapse between its sowing and reaping, requires a great quantity
of water. Gardens which receive water all the year round also pay a high
rate. Other kharif crops are cotton and millet. The chief rabi crops are
wheat, barley and “gram.”
Every field irrigated is booked by a patwari who is provided with a
“field map” and “field book” for each village (perhaps 6 or 8) in his
beat. The map enables him to recognise at a glance the field in which he
is standing. It has a number in the map and, by referring to this number
in the field book, he finds the area of the field. The patwari is also
provided with a “field register” in which he books each field which is
watered, showing its area and the kind of crop grown, the date of
booking and the name of the owner and tenant. He goes about entering up
all new irrigation and his proceedings are subjected to rigorous check
by the zilladar and Deputy Collector, and also by the engineering staff.
At the end of the crop the entries are abstracted into a “demand
statement” in which all the fields cultivated by one person are brought
together and, the proper rates being applied to them, the sum payable by
this person is arrived at. The demand statement goes to the Collector of
the district, who levies the money and pays it into the Treasury to the
credit of the canal concerned. There is a special charge for any land
watered in an “unauthorised manner.” This includes taking water when it
was another man’s turn, or taking it from an outlet which has been
wilfully enlarged or--in some districts--from another man’s outlet even
with his consent. The sizes of the outlets are carefully apportioned to
the land allotted to them and the area which they irrigate is constantly
being looked into in order to see if the size is correct or needs
altering. If a man borrows water from another outlet such borrowing may
or may not come to light but in any case confusion as to outlet sizes
results.
The water rates charged for ordinary authorised irrigation are decidedly
low. In one district there was a case in which a man, being unable to
get as much water as he needed from his own outlet, took water for some
fields, by permission, from a neighbour’s outlet. This being found out
he was charged for those fields at double the usual rate. He continued
regularly to use the water and to pay the double rate. There were
several cases of this kind in that one district.
Since payment for the water is not made according to the volume used,
the cultivators are more or less careless and wasteful in using it. As a
rule they over-water the land and frequently damage or spoil it by
water-logging. They do not always keep in proper order the banks of the
watercourses. The banks often breach and water escapes. Any area thus
flooded is charged for if it is seen by an official. The engineers have
power to close such a watercourse until it is put in order, but this
would cause loss of revenue and is not often done. The real remedy for
all this is, as already stated, rigid restriction of the supply. The
people will then learn--they are already learning--to use water more
economically.
When the crop in any field or part of a field fails to come to maturity,
the water rate on it is remitted. The failed area is known, in the
Punjab, as “kharába.” On some canals the failed areas are liable to be
large and an irrigation register, in order to be complete, has to show
them or, what is the same thing, to show both the gross and the net
areas, the latter being the area left after deducting the kharába or
remitted area.
2. =Gauges and Regulation.=--In every canal, branch and major or minor
distributary there is a “head gauge” below the head regulator. At every
double regulator there is a gauge in each branch and also an upstream
gauge. These gauges are used for the regulation of the supply. The zeros
of the gauges are at the bed levels. Tables are prepared showing the
discharges corresponding to each gauge reading--except in the case of
upstream gauges--at intervals of ·1 foot.
The question often arises whether it is necessary to have a gauge near
the tail of a distributary. If the outlets have not been properly
adjusted and if water does not reach the tail in proper quantity, a tail
gauge is absolutely essential and its readings should be carefully
watched by the Sub-divisional Officer. To take no action until
complaints arise or until the irrigation returns at the end of the crop
show that some one has suffered, is not correct. When it is known that
sufficient water always reaches the tail, a tail gauge is not necessary.
There may be intermediate gauges on a canal or branch or distributary.
For convenience of reading they are usually at places where a
distributary or minor takes off or where there is a rest house. They
serve to show whether the water level at that place alters while that
at other places is stationary, and thus give indications of any changes
occurring in the channel. The number of such intermediate gauges should
be rigorously kept down. In fact hardly any are necessary. The gauge
register which the Subdivisional Officer has to inspect daily, is, in
any case, voluminous enough.
At a double regulator it is never necessary, except as a very temporary
arrangement in case of an accident, to partially close both channels at
once. One or the other should be fully open. The upstream gauge reading
shows whether this rule is being adhered to. If the bed levels of all
three channels at the regulator are the same, the reading on one or
other of the downstream gauges should be about the same--for the fall in
the water passing through an open regulator is generally negligible--as
that of the upstream gauge. In other cases the difference in the bed
levels has to be taken into account.
Immediately downstream of the off-take of a channel, there is, unless
the water flows in without any appreciable fall, much oscillation of the
water. For this reason the gauge is frequently fixed some 500 feet down
the channel. This is anything but a good arrangement. The gauge-reader’s
quarters are close to the off-take and he will not keep going down to
the gauge. Moreover an official coming along the main channel cannot see
the gauge. The gauge should be close to the head and in a gauge well
where oscillations of the water are reduced to very small amounts. The
upstream gauge requires no well.[25]
[25] For further details as to gauges see Appendix G.
All gauges should be observed daily, in the morning, and the reports
sent by canal dak, post or wire at the earliest possible moment. This
should be rigidly enforced. The register should be posted and laid
before the Subdivisional Officer daily with the least possible delay. It
is only in this way that the Subdivisional Officer can keep proper
control of the water, and detect irregularities. Sometimes trouble
arises owing to the gauge reports not coming in regularly. The
suboverseer can be made responsible for seeing to this matter as regards
all the gauge readers in his section. Gauge readers often reduce the
supply in a branch or distributary at night for fear of a rise occurring
in the night and causing a breach. This is to save themselves the
trouble of watching at night. They are also bribed to tamper with the
supply and run more or less in any channel or keep up the supply for a
longer or shorter time. All regulation should be rigorously checked by
the suboverseer, zilladar and Subdivisional Officer. Irregularities can
be speedily detected if proper steps are taken such as going to the
regulator unexpectedly. The watermarks on the banks can also be seen. If
any man is found to have delayed entering a gauge reading in his book or
despatching the gauge report it is evidence of an intention to deceive.
The suboverseer or zilladar should be required to enter in his note-book
all the checks he makes and the Subdivisional Officer should see the
entries and take suitable steps.
There was formerly a general order in the Punjab that the Subdivisional
Officer should write the gauge register with his own hand. Such an order
is not now considered necessary nor has the Subdivisional Officer,
now-a-days, time to comply with it. The register should however be
written by the clerk carefully and neatly and not be made over to anyone
else.
The regulation should usually be so effected that rushes of water in any
portion of the channel are avoided, but if scour occurs in a particular
part of the channel it may be necessary to try and obtain slack water
there. Until it is proved by experience that they are unnecessary,
soundings should be taken periodically downstream of large works. When a
branch or escape is closed the leakage should be carefully stopped. The
necessary materials should be always kept ready in sufficient quantity.
3. =Gauge Readings and Discharges.= For the head gauge of each
distributary and for certain gauges in the canals, discharge tables,
based on actual observations, are prepared. If changes occur in the
upper part of a channel, the discharge corresponding to a given gauge
reading is altered. One remedy for this is to have a second gauge
downstream of the “silt wedge” or scoured or narrowed reach. The indents
are then made out with reference to the second gauge, but any slight
adjustments due to fluctuation in the water level of the canal, are
effected by means of the head gauge. Unless the zilladar and
Subdivisional Officer are on the alert, the gauge reader is likely to
evade going to the lower gauge every morning, and to enter fictitious
readings for it, inferring them from the readings of the head gauge. If
there are any outlets between the two gauges, their discharge has to be
observed or estimated and added to the discharge of the distributary as
entered in the table corresponding to the readings on the second gauge.
The above system can be worked with advantage in cases where the
distributary bifurcates two or three miles from its off-take. The men in
charge of the two regulators can work together, one of them or an
assistant, going daily from one regulator to the other and back.
Usually, however, the vitiating of the discharge table at the head gauge
has to be faced, and the table to be constantly corrected. It is
impossible to frame beforehand any rule or formula which would give a
certain correction for a certain depth of silt deposit. Moreover, there
might or might not be a contraction of the channel due to deposit on the
sides. The usual plan is to observe a discharge some time during each
month. If the result is in excess of the tabular discharge, all the
discharges for that month are increased in the same proportion. They can
be booked according to the table and totalled, and the correction
applied to the total.
Discharges of canals and branches at their heads or at the boundaries of
divisions, are observed by the Subdivisional Officer about once a month.
Discharges of distributaries are observed about once a month, usually by
zilladars. They are also to some extent observed by the Subdivisional
Officer, but much is left to his discretion. Delta is worked out for
each distributary month by month, and also, of course, for each crop.
Thus a general duty “at distributary heads” can be obtained, and may be
used in new projects[26] instead of the duty at the canal head,
allowance being made for the water lost by absorption in the canal and
branches.
[26] See CHAP. IV., Art. 2.
It cannot be said that these important figures are obtained as carefully
as they could be. If the Subdivisional Officer personally observed the
discharge at each distributary head, even every other month, the
reliability of the results would be much increased. In addition to this
the discharges of canals and branches at the boundaries of subdivisions
should be observed and the results compared with the distributary
discharges, so as to show the loss by absorption. At first grave
discrepancies among the results would be found, but they would be
reduced as the causes of error became known. For the method of
investigating the causes of discrepant discharges see _River and Canal
Engineering_, CHAP. III., Art. 5.
A specimen of a Subdivisional Officer’s gauge register is given in table
I. The zilladar keeps a similar register. The columns headed G contain
the gauge readings, those headed D the discharges. Until some years ago
there were no columns for discharges. The daily discharges of the canal
and of the branches at their heads--and at intermediate points if they
were at the boundaries of divisions--were entered in the Executive
Engineer’s office and the duty was worked out at the end of each crop.
The zilladar merely indented for a certain gauge reading at the
distributary head, and the Subdivisional Officer could tell pretty
nearly what gauge reading he required in the canal at the beginning of
his subdivision. Since the year 1900 or thereabouts, the zilladars have
been required to learn a good deal about discharges. They have to know
how to observe the discharge of a distributary, and to learn how the
discharge of an outlet varies with the head or difference between the
upstream and downstream water levels. They are supposed to indent for
certain discharges, and not merely for certain gauge readings. All this
knowledge is useful to the zilladars and tends to increase their
efficiency, but a practice of constantly thinking in discharges instead
of in gauge readings is unnecessary. If the channels were of all sorts
of sizes matters would be different. Actually the size of a channel is
apportioned to its work, and the proportion of its full supply which it
is carrying at any moment is easily grasped by means of gauge readings
alone.
TABLE I--GAUGE AND DISCHARGE REGISTER.
--------------+-----+---------------------------------------
October, 1912.| | Main Line, Upper Bari Doab Canal.
| +-------------------------+------------+
| | Tibri Regulator | Dhariwal |
| +-----+---------+---------+------------+
| |Above| Main | Kasur | Nangal |
| | | Canal | Branch |Distributary|
| +-----+----+----+---------+-----+------+
|Date.| _G._|_G._|_D._|_G._|_D._| _G._| _D._ |
| |-----+----+----+----+----+-----+------+
| | | | | | | | |
| | | | | | | | |
| 1 | | | | | | 4·0| 100 |
| 2 | | | | | | 4·0| 100 |
| 3 | | | | | | 4·0| 100 |
| * | * | * | * | * | * | * | * |
| 29 | | | | | | 4·2| 110 |
| 30 | | | | | | 4·2| 110 |
| 31 | | | | | | 4·2| 110 |
--------------+-----+-----+----+----+----+----+-----|------+
Total | | | | | |127·1| 3255 |
--------------------+-----+----+----+----+----+-----|------+
No. of days in flow | | | | | | 31 | 31 |
--------------------+-----+----+----+----+----+-----+------+
Average | | | | | | 4·1| 105 |
--------------------+-----+----+----+----+----+-----+------+
--------------+-----+------------------------------------------------
October, 1912.| | Main Line, Upper Bari Doab Canal.
| +------------+-----------------------------------
| | Kunjar | Aliwal Regulator
| +------------+-----+---------+---------+---------
| | Kaler |Above|Amritsar | Lahore |Escape
| |Distributary| | Branch | Branch |
| +------+-----+-----+----+----+----+----+----+----
|Date.| _G._ | _D._| _G._|_G._|_D._|_G._|_D._|_G._|_D._
| |------+-----+-----+----+----+----+----+----+----
| | | | | | | | | |
| | | | | | | | | |
| 1 | | | | | | | | |
| 2 | | | | | | | | |
| 3 | | | | | | | | |
| * | * | * | * | * | * | * | * | * | *
| 29 | | | | | | | | |
| 30 | | | | | | | | |
| 31 | | | | | | | | |
--------------+-----+------+-----+-----+----+----+----+----+----+----
Total | | | | | | | | |
--------------------+------+-----+-----+----+----+----+----+----+----
No. of days in flow | | | | | | | | |
--------------------+------+-----+-----+----+----+----+----+----+----
Average | | | | | | | | |
--------------------+------+-----+-----+----+----+----+----+----+----
As regards the weekly indents, the dealing with discharges instead of
gauge readings is of little practical value. The zilladar merely knows
that on some outlets the demand is great, on others moderate, and he
judges that the distributary needs say, 4 feet of water, its full supply
gauge being 5 feet. He cannot tell how many cubic feet each outlet
requires. If he is required to indent in cubic feet per second (he is
not always required to do this) he probably gets at the discharge from
the gauge reading, and not the gauge reading from the discharge. As
regards the general indent made by the Subdivisional Officer, the same
remarks apply. He can probably tell what gauge he requires without going
into discharges.
Regarding the working out of delta month by month, not only are
discharges more or less doubtful, but the area irrigated is seldom
correct till near the end of the crop. However, the figures, towards the
end of a crop, may be useful. If delta on any distributary is higher
than is usual on that distributary, it may be desirable, if the supply
in the whole canal is short, to reduce the supply to that distributary
somewhat, but this remedy can be properly applied after the end of the
crop by altering the turns (Art. 5). Any steps in the direction of
altering outlets can only be taken after the end of the crop. Admitting,
however, that the working out of delta during the crop is useful, it can
be done by adding up the gauge readings for the month and taking the
average reading and the discharge corresponding to it. This is not quite
the same as the average of the daily discharges, but the difference is
small, and there would be a wholesale and most salutary saving in
clerical work. All the columns headed D could be omitted. The handiness
and compactness of the register would be vastly increased. The
discharges are only approximately known, and refinements of procedure
are unnecessary. The correction of the discharge table, by means of
observed discharges, once a month, can of course be effected without
booking the daily discharges.[27]
[27] There should, in any case, be a special place in the gauge
register for showing the discharge tables, with a note of the
discharge observations from which the table was framed or in
consequence of which it was altered.
Supposing the columns D to be retained the calculations of delta can be
made as shown in table II. the form being printed in the gauge book. To
facilitate the adding up of the discharges a line can be left blank in
table I. after each ten days, and the total for the ten days shown on
it. If the column D is not retained, the gauge readings can be added up.
The discharge corresponding to the mean gauge reading of the month,
multiplied by the number of days the distributary was in flow, gives the
figure to be entered in column 2 of table II.
The final working out of delta crop by crop is of course of the greatest
value. The point which needs attention is, as already remarked, greater
accuracy in the discharges. For reasons which have already been given
(CHAP. I., Art. 5, and CHAP. II., Art. 9) the values of delta on
different distributaries will never be the same, but the causes of high
values can always be investigated and, to some extent, remedied.
TABLE II.--CALCULATION OF DELTA FOR RABI, 1912-13, NANGAL DISTRIBUTARY.
------+------------+------------+---------+------+------------------
Month.| Total of | No. of days|Irrigated| Delta| Remarks.
| discharges | in flow. | area up | up to|
+------+-----+------+-----+ to date.| date.|
| For |Up to| For |Up to| | |
|month.|date.|month.|date.| | |
------+------+-----+------+-----+---------+------+------------------
| | | | | Acres | Feet |
Octo- | 3255 | 3255| 31 | 31 | 6510 | 1·0 |
ber | | | | | | |
| | | | | | |
Novem-| 3390 | 6345| 27 | 58 | 9000 | 1·41 |Closed 3 days
ber | | | | | | |because of breach.
------+------+-----+------+-----+---------+------+------------------
4. =Registers of Irrigation and Outlets.= It is obvious that a
Subdivisional Officer cannot look properly into matters connected with
the working of his channels unless he has, ready to hand, a register
showing, crop by crop, the area irrigated by each distributary and each
outlet and keeps it posted up to date. In 1888 the Chief Engineer of the
Punjab Irrigation directed that each Subdivisional Officer should keep
up English registers of irrigation by villages. The order was for years
lost sight of. The matter has lately, in view of certain recent
occurrences on a large perennial canal, again come to notice, and this
most essential factor in the working of a canal is, it is believed,
receiving attention.
As to the precise form which an irrigation register should take,
opinions and practices differ somewhat. In all cases the net irrigated
areas should be shown--kharif, rabi, and total--and the total remitted
area. The areas remitted for kharif and rabi separately may or may not
be shown. The net percentage of the commanded culturable area
irrigated--total of the two crops--can be shown in red ink and is most
useful.[28] It enables the general state of affairs on any outlet to be
seen at a glance and shows how it compares with other outlets and with
the whole distributary.
[28] Provided that the culturable commanded area is properly shown and
is not made to include jungles or other tracts which were never
intended to be irrigated.
Besides the irrigation figures it is necessary to record for each outlet
its chainage, size of barrel[29] and commanded culturable area. In the
case of a distributary which has been working for years, and on which
the outlets are undergoing few alterations, it may be suitable to record
the above items in a separate “outlet register,” and to give in the
irrigation register a reference to the page of the outlet register. But
even in such a case alterations will have to be made from time to time
in the outlet register and there is great danger of its becoming spoilt,
imperfect or unintelligible. In the case of a distributary on which the
outlets are undergoing frequent changes, the items under consideration
should be shown crop by crop, and also the material of the outlet--wood
or masonry--and the width and mean height of the barrel. In no other way
can the working of the outlet be properly followed and understood. It is
probable that this procedure is the best in every case, _i.e._, even
when the alterations made are not frequent. By arranging the register as
shown in table III. the repetition of the entries, when they undergo no
alteration, is avoided, only dots having to be made.
[29] The sizes of the outlets should be measured by the suboverseer
and some checked by the Subdivisional Officer and the correct
sectional area, as actually built, entered.
The specimen shows only two outlets on a page, and covers five years,
but three outlets can easily be shown on a large page, and the period
can be seven years. If there are more than three outlets in the village,
the lowest part of the page shows the total of the page instead of the
total of the village, and the other outlets are shown on the next page,
the grand total for the village coming at the foot.
TABLE III.--REGISTER BY OUTLETS AND VILLAGES.
Distributary ..................................
------------+-------+------------------------------------------------+
| | Information regarding outlet. |
| |--------+--------+---------+--------------------+
| | | | |Dimensions of barrel|
Name and | | | |Sectional+----------+---------+
description| Year |Chainage|Material| area of | | |
of outlet. | | | | barrel. | Width | Height |
| | | |(minimum)| | |
------------+-------+--------+--------+---------+----------+---------+
Register no.| | | | | | |
|1902-03| | | | | |
Name |1903-04| | | | | |
|1904-05| | | | | |
Bank |1905-06| | | | | |
|1906-07| | | | | |
Flow or lift| | | | | | |
------------+-------+--------+--------+---------+----------+---------+
Register no.| | | | | | |
|1902-03| | | | | |
Name |1903-04| | | | | |
|1904-05| | | | | |
Bank |1905-06| | | | | |
|1906-07| | | | | |
Flow or lift| | | | | | |
------------+-------+--------+--------+---------+----------+---------+
Total } |1902-03| | | | | |
of } |1903-04| | | | | |
|1904-05| | | | | |
{Village |1905-06| | | | | |
{ Page |1906-07| | | | | |
------------+-------+--------+--------+---------+----------+---------+
Village ..................................
------------+-------+-------------------------------------------------
| | Working of outlet.
| |-------------------------------------------------
| | Area in acres. |
Name and | |----------+--------+-----------------+ Net
description| Year | | | Net irrigated |irrigated,
of outlet. | |Commanded |Remitted|------+----+-----+per cent of
| |culturable| |Kharif|Rabi|Total|culturable.
------------+-------+----------+--------+------+----+-----+-----------
Register no.| | | | | | |
|1902-03| | | | | |
Name |1903-04| | | | | |
|1904-05| | | | | |
Bank |1905-06| | | | | |
|1906-07| | | | | |
Flow or lift| | | | | | |
------------+-------+----------+--------+-----------------+-----------
Register no.| | | | | | |
|1902-03| | | | | |
Name |1903-04| | | | | |
|1904-05| | | | | |
Bank |1905-06| | | | | |
|1906-07| | | | | |
Flow or lift| | | | | | |
------------+-------+----------+--------+-----------------+-----------
Total } |1902-03| | | | | |
of } |1903-04| | | | | |
|1904-05| | | | | |
{Village |1905-06| | | | | |
{ Page |1906-07| | | | | |
------------+-------+----------+--------+-----------------+-----------
All the outlets of the uppermost village on the distributary should be
entered, first, even though some of them may be downstream of, and bear
serial numbers lower than, the outlets of the next village. When one
outlet irrigates two or three villages the irrigation of the separate
villages can be entered on one page in the places usually allotted to
outlets, and the lowest part of the page can show the total for the
outlet, the necessary changes in the headings, etc. being made. If any
of the villages has other outlets these will appear on another page and
the total for the village can also be shown.
The village totals should be posted into a second register prepared
somewhat as shown in table IV. and totalled. The totals show the
irrigation for the whole distributary.[30] If necessary the failed areas
can be shown in the register in red ink. If any village is irrigated
from two or more distributaries, each portion of the village should be
dealt with as if it was a separate village.
[30] Very long channels, e.g. inundation canals from which direct
irrigation takes place, can be divided into reaches and the irrigation
of the reaches dealt with as if they were separate channels. A reach
should generally end at a bifurcation or stopdam.
In all registers some blank spaces should be left for the insertion of
new outlets or new villages. The number of pages to be left will depend
on local circumstances, which should be considered. In case figures are
supplied by the revenue authorities and deal only with whole villages,
the details obtained by the canal staff should always be added up and
checked with them. Similarly the commanded culturable areas for the
outlets and villages should be added up and checked with the known total
for the distributary.
TABLE IV.--ABSTRACT OF IRRIGATION BY VILLAGES AND CHANNELS.
Canal...................... Distributary..............
From....................... To........................
--------+------------+-----------+----------------------------------
Name of |Commanded | | Net Areas Irrigated in Acres.
Village.|Culturable | Detail. +----+----+----+----+----+----+----
|Area (Acres)| |1902|1903|1904|1905|1906|1907|1908
| | | -03| -04| -05| -06| -07| -08| -09
--------+------------+-----------+----+----+----+----+----+----+----
| | Kharif | | | | | | |
| | Rabi | | | | | | |
| | Total | | | | | | |
| |Per cent of| | | | | | |
| |Culturable | | | | | | |
--------+------------+-----------+----+----+----+----+----+----+----
| | Kharif | | | | | | |
| | Rabi | | | | | | |
| | Total | | | | | | |
| |Per cent of| | | | | | |
| |Culturable | | | | | | |
--------+------------+-----------+----+----+----+----+----+----+----
| | Kharif | | | | | | |
| | Rabi | | | | | | |
| | Total | | | | | | |
| |Per cent of| | | | | | |
| |Culturable | | | | | | |
--------+------------+-----------+----+----+----+----+----+----+----
| | | | | | | | |
Total | | | | | | | | |
| | | | | | | | |
The percentages of culturable commanded area irrigated by different
outlets will, as already explained, always show discrepancies. Any
special causes of low percentages, e.g. a large proportion of rice, can
be briefly noted in the register.
On inundation canals, and some others, the alignment and chainage are
liable to undergo alteration. In such cases it is best to adhere to the
original chainage until all the alterations in alignment have been
carried out.
5. =Distribution of Supply.= The question how the supply of a canal is
to be distributed when it is less than the demand, is not always very
simple. Suppose that the main canal, after perhaps giving off several
distributaries, divides, at one place, into three branches, A, B, and C,
whose full supply discharges are respectively 2,500, 2,000 and 1,500 c.
ft. per second. Suppose that the total discharge reaching the
trifurcation is expected to be, when at the lowest during the crop, only
2,200 c. ft. per second, instead of 6,000. It would be possible,
supposing the discharge tables to be fairly accurate, to keep all the
channels running with discharges proportionate to their full supplies,
but this would not be suitable. The water levels would not be high
enough to enable full supplies to be got into the distributaries, or at
least into some of them. Moreover, the running of low supplies causes
much loss by absorption. The plan usually adopted is to give each
channel full supply, or nearly full supply, in turn, and for such a
number of days that the turn of each branch will recur about once a
fortnight, that being a suitable period having regard to the exigencies
of crops, and having the advantage that the turn of each branch comes on
a particular day of the week, so that everyone concerned, and
especially the irrigating community, can remember and understand it.
Table V. shows how the turns in the above case can be arranged. The
figures show the discharges.
TABLE V.
---------+------+------+------
DAY. | A | B | C
---------+------+------+------
1 | 2,200| |
2 | 2,200| |
3 | 2,200| |
4 | 2,200| |
5 | 2,200| |
6 | | 2,000| 200
7 | | 2,000| 200
8 | | 2,000| 200
9 | | 2,000| 200
10 | | 2,000| 200
11 | 700| | 1,500
12 | 700| | 1,500
13 | 700| | 1,500
14 | 700| | 1,500
---------+------+------+------
Total |13,800|10,000| 7,000
| | |
Correct | | |
discharge|12,800|10,300| 7,700
according| | |
to Full | | |
Supply. | | |
---------+------+------+------
The orders given to the gauge readers in these cases are simple, namely
to give each branch full supply in turn, and to send the rest of the
water down the channel next on the list.
The number of days allotted to the larger branches are greater than to
the smallest because this will probably be simplest in the end, and also
because the number of distributaries on a larger branch is likely to be
greater, and the allotment to the distributaries is thus facilitated
somewhat. Each branch receives water in one period of consecutive days.
Any splitting up of the turn would be highly objectionable. It would
cause waste of water, and would give rise to much difficulty in
redistributing the supply among its distributaries. Each branch receives
its residuum turn before it receives its full supply turn. The advantage
of this is that water is not let into the channel suddenly. The total
supplies of A, B and C are in the ratio of 13·8, 10, and 7, and not, as
they should be 12·8, 10·3, and 7·7, but no closer approximation can be
got. If the number of days of full supply allotted to each branch is
changed, or if the residuum from C is given to B, instead of A, the
relative total discharges differ still more from what they should be.
If now the total supply is supposed to be increased to 2,700 c. ft. per
second, the discharges are as shown in table VI.
TABLE VI.
----------+-------+-------+-----
DAY. | A | B | C
----------+-------+-------+-----
1 | 2,500 | 200 |
2 | 2,500 | 200 |
3 | 2,500 | 200 |
4 | 2,500 | 200 |
5 | 2,500 | 200 |
6 | | 2,000 | 700
7 | | 2,000 | 700
8 | | 2,000 | 700
9 | | 2,000 | 700
10 | | 2,000 | 700
11 | 1,200 | |1,500
12 | 1,200 | |1,500
13 | 1,200 | |1,500
14 | 1,200 | |1,500
----------+-------+-------+-----
Total |17,300 |11,000 |9,500
| | |
Correct | | |
Discharge.|15,700 |12,600 |9,500
----------+-------+-------+-----
Considering both the above tables, A always receives more water than its
share, while B and C on the whole receive too little. Considering table
V. by itself, matters might, perhaps, be set right by altering the total
number of days from 14 to 13 or 12, but this, besides being somewhat
objectionable for the reason already given, might not improve matters
when table VI. came into operation. It is desirable to avoid frequent
changes or complicated rules. It is objectionable to make any turn
consist of other than a whole number of days. The shifting of the
regulator gates is begun at sunrise, a time when officials are about and
can see what is happening. All gauges are read early in the morning, and
those at regulators are read after the regulation has been done and the
flow has become steady. If any regulation were done in the evening, the
entry in the gauge register of that day would convey a wrong impression,
and the discharge would be incorrectly booked. Moreover, any system of
regularly booking evening as well as morning gauges leads to swelling of
the already voluminous gauge register.
The best method of adjusting matters is to make slight alterations in
the full supply gauges. Suppose the normal full supplies in all three
branches to be 6 feet. When table VI. is in operation the full supply of
A can be reduced to about 5·8 feet. This would give, during the first 5
days, less water to A and more to B, and there is the further advantage
that a very small supply, 200 c. ft. per second, is not run in any
branch. As regards table V., branch A never receives full supply. This
is a rare case.[31] If it were safe, as it might be, to run slightly
more than full supply in C, this could be done, and it would increase
the supply in C during the last four days and reduce that in A.
Otherwise a certain gauge would have to be fixed for A which would give
it less than 2,200 c. ft. per second during the first 5 days, and the
balance would go to branch B. Similarly, the gauge of B could be
slightly reduced, and this would increase the balance going to C. The
orders given to the gauge reader are, as before, to send the full supply
down one channel, and the balance to the next. The only additional
procedure necessary is to inform the gauge reader from time to time what
the full supply gauges are. In any case such information has probably to
be conveyed to him at times because the channels undergo changes, and
the discharge corresponding to a given gauge also changes.
[31] The total discharge, 2,200 c. ft. per second, assumed, is very
low compared with the full supply of 6,000 c. ft. per second.
When the discharge of the canal exceeds 3,500 c. ft. per second there
is, when B and C are receiving water, a second residuum, which goes to
A. Tables can be worked out for several discharges of the main canal,
but it is the minimum discharge which is the most important factor in
the case. The minimum discharge, or something very near it, generally
lasts through about half the crop, and it is when the supply is at a
minimum that care and justice in the distribution are most needed.
The chief objection to the arrangements above described is that the
surplus to be sent down one channel or another is sometimes so small
that it must be to a great extent wasted. The best means of preventing
this is to have the discharge tables, including one for the main canal
at some point higher up than the trifurcation, constantly corrected. In
that case, it is known under what circumstances a small surplus will
occur, and the orders can be modified so as to prevent its occurrence.
The orders will of course be more complicated, and will have to be dealt
with by an engineer and not a gauge reader.
The turns, once satisfactorily arranged, may go on for years without
alteration. They may require altering if any branch is found, in the
course of time, to be doing worse than or better than the others, though
the correction can probably be made by altering the full supply gauge.
The turns of the branches having been arranged, it remains to settle
those of the distributaries. The total available discharge being, as
before, assumed to be rather more than one-third of the full supply
discharge, each distributary taking off from the main canal, where it is
not possible or not desirable to regulate the height of the water level
in the canal, can be run with full supply for four or five days out of
each fortnight, and then closed. Whether it be four days or five may
often depend on special circumstances such as whether the distributary
is doing well or otherwise. If necessary the full supply can be
adjusted. When the canal supply increases the four or five days can be
increased.
The same principle can be adopted for any distributary whose off-take is
in the upper part of a branch, _i.e._, where the branch is many times
larger than the distributary, and where it is not possible or not
desirable to regulate the water level of the branch. For a distributary
further down the branch, the turns of branch and distributary can be
arranged as explained above for a canal bifurcation. The orders given to
the gauge reader are, as before, to give the channel whose turn it is,
full supply and to send the balance down the other channel. When the
turn of distributary is over it becomes the turn of the branch. The
distributary would not be closed if this would cause the full supply in
the branch to be exceeded. Care must be taken that every distributary
receives full supply during part of the time when the branch is
receiving full supply. If its turn came only when the branch was
receiving a residuum supply, or rather when the residuum supply was
reaching the distributary off-take--for in the case of a distributary
whose off-take is far down a long branch the two things are not the
same--it might, in the event of the supply in the main canal falling
exceptionally low, receive no water at all.
The time taken by a rise in travelling down a canal is very much the
same as that taken by a fall and each takes effect more or less
gradually. When a branch receives, at any point, a temporary increase in
its supply, owing to the closure of a distributary for, say, three
days, there will be a rise lasting for three days at a point further
down. The rise will take some time to come to its height, and some time
to die away. There will be about three days from the commencement of the
rise to the commencement of the fall, or from the end of the rise to the
end of the fall. If, either in the main canal or in a branch, there is
any distributary into which full supply cannot be got, its turn can be
increased accordingly. Owing to the shortness of the turns, and to
allowance having to be made for the time occupied by rises and falls in
travelling down the branch, the fixing of the turns for distributaries
near the tail of the branch requires a good deal of consideration.
Matters are facilitated by making a sketch (Fig. 25) in which the widths
of the channels, as drawn, are roughly in proportion to the full supply
discharges. If 14 copies of the sketch are made the arrangements for
each day can be shown on them, full supply being shown black and
residuum hatched. Distributaries would be shown as well as the main
channels.
[Illustration: FIG. 25.]
The irrigation registers of course show how the irrigation of the
different channels is going on from year to year and if changes in the
turns become necessary they can be effected.
After the water has entered the watercourses the canal officials have
nothing to do with its distribution. The people arrange among
themselves a system of turns, each person taking the water for a certain
number of “pahars”--a pahar is a watch of three hours--or fractions of a
pahar. The zilladar can however be called in by any person who has a
dispute with his neighbour. If the matter is not settled the person
aggrieved can lodge a formal complaint and a canal officer then tries
the case, and if necessary punishes the offender.
In former days it was usual, in some places, for no regular turns to be
fixed for the distributaries, orders being issued regarding them from
time to time. The weak point about any such plan is that in the event of
the controlling officer delaying, owing to any accident, to issue an
order, no one knows what to do. Orders were also sometimes issued to
zilladars giving them discretionary powers in distribution. No one would
now issue such orders. The essential principle is to remove power from
the hands of the subordinates. The working of the main channels by turns
and the construction of outlets of such a size that they never require
closure, has resulted--in places where such matters are attended to--in
the absolute destruction of such power.[32] The only way in which a
zilladar can injure anyone is to say that water is not in demand. This
would however result in damaging the whole of the villages in his
charge. He is not likely to do this.
[32] In the printed form lately in use in the Punjab for reports on
zilladars, one of the questions asked is whether “his arrangements”
for the distribution of water are satisfactory, as if that was still
considered to be the zilladar’s business.
In case the supply is wholly or partially interrupted owing to a breach
or an accident at the headworks, or other cause, one particular branch
or distributary may lose its turn or part of it. If its loss is not
great it may be best to allow the turns to take their usual course, but
otherwise they should be temporarily altered in such a way as to
compensate the channels which have suffered.
On inundation canals the water at a regulator is sometimes headed
up,--all branches being partially closed--in order to give more water to
outlets in the upstream reach. There are even some regulators--or rather
stop-dams--constructed solely for this purpose at places where there is
no bifurcation of the canal or distributary. Any such heading up should
be planned out beforehand and days for it fixed, and also the gauge
reading. If the water, without any heading up, rises to the needful
height on the gauge, nothing has to be done. There are also places on
inundation canals where the land is high and is only irrigable during
floods. At such places it is usual, on some canals, to allow the people
to make cuts in the bank when the water attains a certain height. Owing
to the high level of the country, nothing in the nature of a breach can
occur. In one canal division where the above arrangement was in force,
the people used to send applications to the Executive Engineer for leave
to cut the banks. This resulted in much delay. A list was prepared
showing exactly where the banks might be cut, the people were informed
and the formalities were much reduced.
6. =Extensions and Remodellings.= An existing canal or distributary may
need remodelling for various reasons, and in various degrees. If the
velocity is too high and the bed has scoured, or the sides have fallen
in, it may be necessary to raise the crests of falls, or to construct
intermediate weirs, or to widen the channel and reduce the depth. If the
command is not good it may be necessary to regrade the channel. If silt
deposit occurs, the cross-section of the channel may have to be altered,
to give a better relation between D and V. If there is surplus water,
extensions or enlargements of channels may be desirable and these can
sometimes be undertaken to a moderate extent merely by restricting a
somewhat too lavish supply to existing distributaries. If the water
level is dangerously high it may have to be lowered, or the banks raised
and strengthened. Sometimes it is desirable to cut off bends either to
shorten the channel and gain command or because the bends are sharp and
cause falling in of the banks or, if numerous, silting. In all cases the
general principles are the same as for entirely new projects, but
certain details require consideration.
The distributaries of the older canals were constructed before Kennedy’s
laws regarding silting were known, and it has been necessary to remodel
many of them. In some cases the gradient was wrong, in others the
cross-section.[33] In some cases a distributary ran in rather low
ground, and it was proposed to abandon it and construct a new one on
high ground. It was however pointed out by Kennedy (_Punjab Irrigation
Paper No. 10_, “Remodelling of Distributaries on old Canals,”) that
irrigation had become established along the course of the distributary,
that most of it would remain there and that a new alignment would result
in increased length of watercourses. Such distributaries have therefore
been allowed to remain very much as they were.
[33] The difficulty of reducing the size of a channel which is too
large is well known and has been discussed in _River and Canal
Engineering_, Chapter VIII. It is there explained that a moderate
reduction of width can be effected by “bushing,” but that for great
reductions, groynes or training walls are necessary. When the bed of a
distributary is too low it has been suggested that it could be raised
by filling in earth in each alternate length of 500 feet, and leaving
the rest to silt, but this would be expensive.
Remodelling should not be considered piecemeal, but regard should be had
to the whole channel. When a distributary is remodelled the outlets
should of course be dealt with as well as the channel. The chief thing
to consider is not whether the channel as it exists is exactly as it was
originally designed to be, but how it is doing its work and what kind of
alteration it needs. Even when a simple silt clearance or berm cutting
of a channel has to be undertaken, the work need not always consist in
blindly restoring the channel to its original condition. It may be both
feasible and desirable to remodel it to a slight extent, lowering the
water for instance in reaches where the outlets draw off very good
supplies and thus benefiting less fortunate reaches lower down.
The irrigation boundaries of the extended or remodelled channel should
as far as possible follow drainages, but these are not always important
or pronounced. The actual irrigation boundaries should be shown and also
those of any neighbouring channels of other canals, and any suitable
adjustments should be made.
Regarding the percentage of area to be irrigated, it has already been
stated that one canal or distributary irrigates a far higher percentage
than another. Generally when there is a high percentage in any tract, it
is undesirable to cut it down unless it has very recently sprung up to
the detriment of other tracts. In some remodelling projects a uniform
percentage is taken on the whole area including both new and old
irrigation. This plan is suitable when the percentage of old irrigation
is not very high. In other cases the old irrigation to be provided for
may be taken as the maximum area actually irrigated, a little being
perhaps added for extensions. If the irrigation of considerable areas of
jungle tracts is contemplated and if these consist of numerous small
patches, a further percentage can be added for them. If there are large
jungle tracts they can of course be dealt with separately and any
suitable percentage adopted for them. The percentage for each portion of
a remodelling project is not necessarily the same.
If the discharge of a channel is increased, the waterways of bridges may
need increasing. This can often be done (Chapter II., Art. 12) by making
a floor at a low level. Or the waterway may be allowed to remain small,
the floor being added at the bed level and the bridge then becoming an
incomplete fall, (page 87). The fall in the water surface, though small,
can be recognised and shown on the longitudinal section.
In remodelling schemes, the longitudinal section should give all
possible information. It should show not only the levels of bed and
banks, but the F.S. levels (in blue figures) above and below all falls
or regulators, and the levels of floors and waterways of bridges. The
plan should show all watercourses and the “chaks” or areas assigned to
them.[34] On each chak the actual average irrigation can be shown in
blue figures and the proposed irrigation in red. The “draw-off” for each
proposed outlet can then be shown on the longitudinal section. The area
actually irrigated, as shown on the map, should in each case be the
mean of at least three years, and if possible of five years. The number
of years should be mentioned in a note on the map. Cross-sections of
channels should always be drawn to natural scale, and not with the
horizontal scale differing from the vertical.
[34] The field maps mentioned on page 101 are prepared to a very large
scale and show all watercourses. The maps should always be corrected
up to date by the patwaris. The chak maps which are on a smaller
scale--say 4 inches to the mile--can thus be kept correct.
7. =Remodelling of outlets.= When a channel is remodelled, the
remodelling of the outlets may consist in alterations of the number or
sites or in alterations of their sizes.
Regarding the former, a map should be prepared showing all watercourses,
chaks and contours.[35] On this map new lines for the watercourses can
be shown, the principles enunciated in Chapter II., Art. 9, being
generally followed, but in such a way as to utilise existing
watercourses and outlets as far as possible. The work often consists in
the abolition of a certain number of watercourses, when these are too
close together and run parallel to one another. There may, however, be
little gain in amalgamating two such watercourses if they serve two
different villages. There is nothing to prevent the people from dividing
the watercourse into two as soon as it gets away from the canal, and
they are likely to do this in many cases. When one branch has a flatter
slope than the other it would lose command if it took off further down.
The people on the steeper branch might not agree to using the flatter
one because of silt trouble, or increased height of embankment. In a new
project it is not difficult to get the people to do what is needed, but
when once irrigation has become established it is often difficult to get
suitable changes made. The advantages of amalgamating watercourses,
though appreciable, have been a good deal exaggerated. The chief
advantage is gained by reduction in the sizes of outlets. Then, however
many branches the watercourse may have, they can only run in turns and
not all together. It may happen that two watercourses, though taking off
near one another, run in different directions and that the chaks are of
suitable shapes and sizes. In such a case the only advantage of
amalgamating is that it saves an outlet in the canal bank. No saving in
the length of watercourse will be effected because there will be a
bifurcation as soon as the watercourse leaves the canal boundary. If
both outlets are of suitable design and proper size or require only
slight alteration, both can remain but otherwise amalgamation can be
effected. In some cases amalgamation might give a discharge greater than
that usually allowed for an outlet but this need form no obstacle. The
chief reason for limiting the discharge is the alleged inability of the
farmers to manage a large channel. This matter is exaggerated as already
stated (page 74). In the case under consideration it obviously makes no
difference whether there are two watercourses each discharging 5 c. ft.
per second, or one discharging 10 c. ft. per second, and immediately
dividing into two. Very small watercourses should, when possible, be
joined to others but if there is no other near enough they must
generally remain, however small they may be.
[35] In small remodelling schemes the lines of existing watercourses
show how the country slopes, and a contour plan is not a necessity.
Regarding the alterations in sizes of outlets, whether or not there are
alterations in their number and position, information as to the actual
duties on the watercourses should be obtained. The discharge of the
watercourses should be observed several times and added up and checked
with the discharge of the distributary. The areas irrigated are known
from the irrigation register. If the duties are abnormal the causes can
be gone into, and a judgement can be formed as to how far they will
remain in existence, and whether any watercourse is often kept closed.
If so the outlet is too large. The duties, modified so far as may seem
desirable, can be used for calculating the sizes of the remodelled
outlets. But alterations of the sizes after a year or two years’ working
will probably be necessary. The above procedure is also applicable to a
case where the old watercourses had no masonry heads but were merely
open cuts as on some inundation canals.
A common case is that in which the channel is not remodelled--or at
least its water level remains very much as before--but merely the
outlets are altered in number, position or size, or in any or all of
these. If the land irrigated by an outlet is high, the irrigation may be
far short of what was expected, and the size of the outlet may have to
be increased or its site shifted, generally upstream. This is often done
at the request of the people, and at their expense.[36]
[36] On some of the more modern canals the people are not allowed to
pay for outlets, so that no question of ownership can arise.
Old outlets should always be removed when superseded by others.
Otherwise they are apt to be reopened or claims set up regarding them.
Near the tail of a channel the discharge of an outlet may be an
appreciable fraction of that of the channel. In such a case the
adjustment of the size of the outlet, and that of the channel or of any
weir or fall in the channel, should be considered together, the
irrigation on the outlet and that on the channel downstream of it being
compared. And similarly as to the sizes of any two or more tail outlets.
Such outlets are sometimes left without masonry heads on the ground that
this injures no one. It may injure an outlet upstream of them by drawing
down the water. Tail outlets often need constructing or reducing in size
to raise the water level in the reach upstream of them.
Whenever the size of an old outlet is altered the design should be
altered if unsuitable. The parapets should be brought into proper line,
the roadway corrected, the floor level adjusted and any splayed wing
walls abolished. If the outlet is skew it should be made square. All
this should also be done to all old outlets or heads of minors even if
the sizes are correct, whenever remodelling of outlets on any channel is
undertaken.[37]
[37] Wherever an outlet is built or altered, a template, made to the
exact size of barrel required, should be supplied to the subordinate
in charge of the work.
It was stated in Chapter II. that the construction of masonry outlets on
a distributary is not usually a final settlement of the matter. In many
cases a proper proportion of water does not reach the tail. Even in such
a case matters have occasionally been left alone, or the old and
pernicious system of closing the upper outlets has been resorted to. In
such circumstances the irrigation of a group of tail villages will be
found to be less than that of a group higher up, the people to some
extent acquiescing in the old idea that a tail village must be a
sufferer. Government, or at least the Irrigation Department, has no
particular direct interest in the matter. The total area irrigated, will
probably be very much the same in any case. But an engineer who takes an
interest in this part of his work will not allow matters to remain long
in the state described. He will, of his own accord, adjust the outlets
and equalise, as far as possible, the irrigated percentages. The people
will disturb matters to some extent by enlarging watercourses, but there
is a limit to this and it can be met by an occasional reduction of an
outlet. A distributary, when once its outlets have been carefully
adjusted, attains to something approaching perfection in its working.
Any excess in the supply is taken partly by the upper outlets but part
of it gets to the tail. Similarly any deficiency in the supply is
distributed over the channel. The outlets which have a poor command and
small head are most affected in either case. On the whole they do not
lose or gain more than the others. The working of such a distributary
causes great satisfaction to the engineer and not the least ingredient
in this is the knowledge that he has wholly destroyed the power of his
native subordinate.
In an inundation canal division in the Punjab, some dozen
distributaries, varying in length from 5 to 28 miles, and with
discharges ranging up to 300 c. feet per second, were dealt with as
above in one season. The engineer in charge being specially desirous
that sufficient water should reach the tails, reduced the sizes of some
outlets too much. When an outlet of 1 or 2 sq. feet has to be reduced to
a small fraction of its size it is not easy to say what the fraction
shall be. Water reached the tails of all the channels in sufficient
quantity, in some cases in rather more quantity than was necessary.
When the irrigation register was examined, it was found that the general
results were entirely satisfactory. In a small proportion of cases
outlets had irrigated too little and had to be re-enlarged somewhat.
After a second season hardly any changes were needed. When any silt
clearance or berm-cutting seemed necessary the irrigation register again
came into play. If, for instance the tail outlets, as a whole, were
receiving too little water, enlargement of the upstream reaches was
effected with consequent lowering of the water level there.
In the case above described the channels flowed for only five months in
the year. Some of them silted a good deal but as this silting was
roughly the same every year, it did not greatly affect the question of
outlet sizes. On a perennial distributary of which the head reach silts
during part of the year and scours during the other part, a proper
distribution of supply by adjustment of outlet sizes alone may be more
difficult. If the silt was frequently cleared, this would cause needless
expense and interference with irrigation. In cases where the
distributary is not run constantly, something can be done by attending
to the regulation. When there is silt in the head reach, the discharge
can be reduced and the period of flow proportionately increased. The
lowered water level reduces the supplies of the upper outlets, and
increases the discharges of those lower down. Moreover the periodical
silting and scour are not always serious. Also it is not essential that
the supply to each watercourse should be exactly the same every year.
There are always good and bad seasons. It is sufficient if a watercourse
is not allowed to suffer on the whole, and is never allowed to suffer
much. There is no doubt that it is possible to deal satisfactorily in
the above manner with very many distributaries. It is frequently
reported that “difficulty is experienced in getting water to the tail.”
This is owing to timidity in reducing the sizes of outlets. The suitable
plan is to reduce them to such an extent as to cause a proper supply to
reach the tail and then, if necessary to enlarge some. It has been
already remarked that only a short length of the barrel need be altered.
The cost of this is very small. The real difficulty in the case is not
the impossibility of securing good results, but the impracticability, in
many cases, of securing the constant attention which the procedure
demands.[38]
[38] See also Chapter V. Art 3.
8. =Miscellaneous Items.= At the headworks of a canal there is a
permanent staff of men who work the gates and look after the works. They
assist in discharge observations and in reading the gauges, and they may
have to take soundings in the river to see what changes are taking
place. Some one is on watch day and night and reads the gauges at
frequent intervals. The officer in charge occasionally inspects the
works at night without notice. Detailed rules regarding the above
matters, and any others that are necessary owing to special local
conditions, are drawn up. Sometimes there is difficulty in getting the
staff to attend properly to the regulation of the supply in the canal at
night. Probably some “tell-tale” watches would be useful. They would at
least show the times at which the men concerned went to the gauges or
other points.
At the headworks, and at all important regulators, a stock of concrete
blocks should be kept ready for the execution of any urgent repairs.
Regarding the ordinary maintenance work on the channels, details are
given in Appendices B and C. Appendix D, reprinted from _Punjab Rivers
and Works_, contains rules for watching and protecting any banks or
embankments which require it.
Silt clearances and berm cutting of channels have been mentioned in Art.
1. Special attention should be given to the accurate ranging of the
centre line. Otherwise the channel may become crooked. The great defect
in the earthwork ordinarily met with in the banks of canals and
distributaries is that the clods are not broken. In consequence of this
new banks are extremely liable to breach, and much trouble and expense
result. Sometimes a dam is thrown across a new distributary, and the
channel upstream of it is gradually filled with water, the bank being
watched and leakages made good. The dam is then shifted to a place
further down. In this way the banks are consolidated.
When a distributary is closed for silt clearance or other work, if the
head regulator has planks and a double set of grooves, it is possible to
stop all leakage by filling in earth between the two sets of planks and
ramming it, but otherwise it is necessary to construct an earthen dam
just below the regulator. Upstream of the dam the water, owing to the
leakage through the planks, gates or needles, rises to the same level as
the water in the canal. Native subordinates have a remarkable aptitude
for allowing such dams to break while the work in the distributary is in
progress or before it is measured. Now and then the dam is wilfully cut.
The remedy is to make the dam of proper strength--the top should be 8
feet wide and a foot above the water,--and to have it watched day and
night.
At a bend in a channel there is often a silt bank next the convex bank,
and a hollow near the concave bank. The average bed level is probably
very much the same as in the straight reaches. Removal of the silt bank
is unnecessary, and if removed it quickly forms again.
Any length of channel in which the depth of silt to be cleared is small,
say ·50 foot in a large channel and ·40 foot in a small one, should not
be cleared, provided its length is considerable (say 1,000 feet), and
that it is not close to (say within 3,000 or 2,000 feet from) the head
of the channel. Estimates should be prepared accordingly, the shallow
digging being struck out. Clearing a small depth of silt merely gives
contractors a chance of cheating by scraping the bed.
If the watercourses at the tail of a distributary are silted, the people
should be pressed to clear them. Otherwise there will be heading up of
the water of the distributary, and silt deposit may result.
When a channel is scoured, any regulator in it can be kept partly closed
so as to reduce the surface slope in the reach upstream of the regulator
and encourage the deposit of silt. A table should, in such cases, be
drawn up giving the gauge readings to be maintained at the tail of the
reach corresponding to given readings at the head.
Various methods of protecting banks are described in _River and Canal
Engineering_, Chapter VI. The growing of plants on the inner slopes of
channels whose sides fall in, needs special attention. Some remarks on
this are given in _Punjab Rivers and Works_, Chapter II., Art. 3. A
specification for bushing is given in Appendix E of this volume.