CHAPTER XI

BRIDGES AND SYPHONS

1. =Bridges.=--Bridges are of many kinds. In this book only those parts

of them are considered which are exposed to the stream. If a bridge has

piers, there must be some disturbance of the water. The disturbance

will be least when the area of the waterway of the bridge is at least

as great as that of the stream, and when its shape is as nearly as

possible the same. For small streams, a single span clearing the whole

stream may be adopted, especially when the channel is of soft material,

but for a large stream the cost of intermediate piers, even with a

certain amount of protection for them or with deep foundations, will be

more than counterbalanced by the smaller thickness of arch or depth of

girder.

Generally a bridge has vertical abutments which limit the waterway,

but it may have land-spans, and in this case the stream as it rises

can spread out. Piers and abutments should be so designed that abrupt

changes in the section of the stream are, as far as possible, avoided,

the piers being rounded or boat-shaped at both ends and the abutments

suitably curved (fig. 49). Boat-shaped piers, besides presenting the

neatest appearance, cause the least amount of disturbance.

A bridge can be made safe against scour either by giving deep

foundations to the piers and abutments or by adding a floor and, if

necessary, pitching. The former course is usually adopted and is

the best. But in a case in which the discharge of a stream is to be

increased or has been underestimated, it is often far easier to add a

floor to an existing bridge than to increase the span of the bridge. In

order to increase the waterway the floor can be “dished,” _i.e._ made

at a level lower than the bed of the stream[17] and gradually sloped

up--the slopes being pitched--both upstream and downstream of the

bridge, to meet the bed.

[Illustration: FIG. 49.]

In any case in which the water rises above the crown of the arch, the

bridge becomes a syphon, and a floor is probably necessary unless the

foundations are very deep, or unless the rise of water above the crown

is temporary.

[Illustration: FIG. 50.]

In the case of Indian rivers which have soft channels, and are

ordinarily of moderate width but are subject to occasional floods when

the width of the stream is multiplied several times and becomes very

great, it is the rule to make the span of a railway bridge far less

than this greater width. The stream during floods scours out a deep

channel through the bridge with great rapidity, and no heading up worth

mentioning occurs. The foundations of the piers are very deep, being

frequently 50 feet below the lowest point of the river bed which can

be found anywhere within several miles of the bridge. The span of the

bridge can be arrived at by considering a general cross-section of

the river as it is when in high flood, and assuming that scour to the

depth of the lowest point, found as just explained, will take place in

one-third of the span of the bridge. The span can then be so fixed as

to give no heading up. It is not assumed that there will be no increase

in velocity through the bridge. The velocity in the deep scoured

portions will be increased. The piers are protected by loose stone

(fig. 50). The spans vary from 100 to 250 feet. The bridge over the

river Chenab at Wazirabad had originally sixty-four spans of 145 feet

each. The number of spans has since been reduced to twenty-eight. With

a very long bridge, the current of the shifting stream is more likely

to strike the bridge obliquely, though this is not the chief reason for

reducing the length. Long spans, say 250 feet, have been found to be

better than shorter spans; the cost of the stone protection round the

piers is of course less (_Government of India Technical Paper_, No.

153, “River Training and Control on the Guide Bank System,” by Sir F.

J. E. Spring, C.I.E., 1904).

2. =Syphons and Culverts.=--Syphons are used to pass drainage channels

or other streams under canals or other lines of communication. In the

case of a masonry syphon under a stream which may be dry while the

syphon is full, the weight of the arch and its solid load must be not

less than the upward pressure of the water passing through the syphon.

The channel sometimes has a vertical drop at the upstream side (fig.

51) and a slope at the downstream side. The slope enables any solid

materials to be carried through, and facilitates cleaning out and

unwatering. The drop at the upstream side does not give rise to any

shock on the floor when the syphon is full, but a slope is preferable

if there is room for it, and it causes less loss of head.

[Illustration: FIG. 51.]

A culvert which is liable to run full and which has a steep approach

channel (fig. 52) may become suddenly drowned on the upstream side. As

soon as the water rises to the crown of the arch, the wet border of

the culvert increases and this reduces the velocity and discharge. The

water coming down the approach channel then rises abruptly, and the

increased section of the stream causes a reduced velocity of approach,

and this further reduces the discharge through the culvert. The heading

up continues until the difference in the upstream and downstream

water-levels is great enough to readjust matters (_Min. Proc. Inst.

C.E._, vol. clxxxvi.). The possibility of this heading up occurring

should be attended to in the design. In the case of a culvert in a

railway embankment where heavy floods have to be passed, the culvert

may be made bell-mouthed by a curved embankment constructed on its

upstream side.

[Illustration: FIG. 52.]

3. =Training Works.=--The object of the upstream and downstream

protections already described (CHAP. X.) is to prevent damage to the

structure owing to the disturbance caused by the structure itself.

When a river is given to shifting its course (CHAP. IV., _Art. 9_)

and cutting away its banks, protection of another kind is required.

The stream, if left to itself, may cut away one bank upstream of the

structure for a long distance, and eventually damage, or destroy by

undermining, the upstream pitching and the abutment itself. This is

known as outflanking. If in the neighbourhood of the line A B (fig.

53) there is nothing for the river to damage,--if, for instance, the

structure is a weir with a canal, if any, only on the opposite bank of

the river,--and if the land is of no particular value, the case could

conceivably be met by protecting the abutment on all sides, but even

then there might be a chance of the erosion of the bank continuing

until the stream had formed a connection at C with the downstream

reach. This, of course, in the case of a weir, would render the work

useless and might even destroy it.

[Illustration: FIG. 53.]

In the case of a bridge carrying a road or railway, or of a syphon or

aqueduct carrying a canal or other stream, it is wholly inadmissible

to allow the stream to cut away even as far as the point A for fear

of its severing the line of communication. Thus in every case it is

practically necessary to prevent any serious erosion of the bank

upstream of the structure. In ordinary cases it is sufficient to

protect the bank C D by any of the methods given in CHAP. VI., _Art.

3_, the protection being turned inwards, as shown at D, to prevent the

end of it being damaged.

In the case of railway bridges across the great shifting rivers of

India, protection used at one time to be afforded by various systems

of spurs. This has now been abandoned in favour of Bell’s guide banks

(fig. 54), which are found to be far more satisfactory. These guide

banks are discussed in the paper by Spring quoted above (_Art. 1_).

The spaces behind the guide banks become filled with water, at least

during floods, and are meant to be silted up. An opening in the

railway embankment should be provided at A, and another on the opposite

side of the river, to ensure a constant flow of water (CHAP. V., _Art.

3_), but they should not be large enough to cause high velocity. The

chief danger to which a guide bank is liable is outflanking when the

stream assumes the position shown. To guard against this danger it is

necessary to have very strong and massive heads to the guide banks.

When the bank of the eroding stream, downstream of the guide bank head,

becomes a semicircle or thereabouts, the stream takes a short-cut

across the sandbank, and to encourage this an artificial cut can be

dug, at the season of low water, on any suitable line.

[Illustration: FIG. 54.]

If the guide banks were made with an increased width of opening at

the upper end, this would reduce the chance of outflanking but would

increase the danger from a direct attack such as indicated, in the

figure, on the left bank. It has been suggested that the width at

the upstream end should be less than at the bridge, but this seems

undesirable. Probably the form shown in fig. 54 is the proper one. The

length of the guide bank upstream of the bridge is made about equal

to the span of the bridge between the two guide banks. If made less

than this, the river might cut into the line of railway. The length of

guide bank downstream of the bridge is generally 300 to 500 feet, being

greater as the velocity of the river is greater and the sand of its bed

finer.

[Illustration: FIG. 55.]

The Bengal Dooars Railway runs near the foot of the Bhutan Himalayas,

and crosses some broad river channels which, after the excessively

heavy rains which occur, are filled by streams of very high velocities.

One such channel or set of channels (fig. 55), more than half a mile

wide, is provided with a bridge whose waterway consists of ten spans

of 60 feet each. The railway embankment across the remainder of the

channel having been breached in many places in 1903, protection was

afforded by T-headed spurs and other groynes, the first arrangement,

which withstood the floods of 1904, being as shown in the figure. The

triangular apex of the A-shaped groyne, south-east of the bridge, was

added in 1905 because, in its absence, the water struck the bridge

obliquely. After the addition there was a great deposit of silt in

the neighbourhood of the four T-headed spurs. Next year the river,

in a great flood, rose over the top of the railway embankment near

these spurs, and finally caused a breach 600 feet wide. The embankment

was afterwards raised. The velocity through the bridge seems to have

approached 18 feet per second. The bridge had at first no floor. A

floor was added, but was much damaged by the floods (_Min. Proc. Inst.

C.E._, vol. clxxiii.). The level of the floor is not given, but it

would seem to have been desirable to make it at a very low level. The

rising of the stream over the railway embankment was attributed to the

silting up near the T-headed spurs. The addition of the triangular

portion above referred to would seem to have somewhat assisted this

process. If all the trouble could have been foreseen, it might have

been best to build an additional bridge 2000 feet south-east of the

existing bridge. The groynes were composed of the wire-network rolls,

described in CHAP. VI., _Art. 3_, piled pyramid fashion.

River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them. · 第 11 / 15 章