CHAPTER V

METHODS OF INCREASING OR REDUCING SILTING OR SCOUR

1. =Preliminary Remarks.=--Most important works which affect the régime

of a stream have some effect on its silting or scouring action, but

this is not generally their chief object. Such works will be dealt

with in due course, and the effects which they are likely to produce

on silting or scouring will be mentioned. In the present chapter only

those works and measures will be considered whose chief object is to

cause a stream to alter its silting or scouring action. It does not

matter, so far as this discussion is concerned, whether the object

is direct, _i.e._ concerned only with the particular place where the

effect is to be produced, or indirect, as, for instance, where a stream

is made to scour in order that it may deposit material further down the

stream. The protection of banks from scour is considered in CHAP. VI.

Dredging is dealt with in CHAP. VIII.

2. =Production of Scour or Reduction of Silting.=--Sometimes the silt

on the bed of a stream is artificially stirred up by simple measures,

as, for instance, by scrapers or harrows attached to boats which are

allowed to drift with the stream, or by means of a cylinder which has

claw-like teeth projecting from its circumference and is rolled along

the bed, or by fitting up boats with shutters which are let down close

to the bed and so cause a rush of water under them, or by anchoring

a steamer and working its screw propeller. It is thus possible to

cause a great deal of local scour, but the silt tends to deposit again

quickly, and it is not easy to keep any considerable length of channel

permanently scoured. The system is suitable in a case in which a local

shallow or sandbank is to be got rid of and deposit of silt a little

further down is not objectionable. It may be suitable in a case in

which the bed is to be scoured while a deposit of silt at the sides of

the channel is required, especially if some arrangement to encourage

silt deposit at the sides is used (_Art. 3_, par. 4; also CHAP. VI.,

_Art. 3_).

Holding back the water by means, for instance, of a regulator or

movable weir, and letting it in again with somewhat of a rush, will,

if frequently repeated, have some effect in moving silt on in the

downstream reach. Regarding the upstream reach, it has been remarked

(CHAP. IV., _Art. 3_) that a weir does not necessarily cause silt

deposit. If, in a stream which does not ordinarily silt, a regulator or

movable weir causes, when the water is headed up, some silt deposit,

the cessation of the heading up not only removes the tendency to silt,

but the section of the stream, at the place where the deposit occurred,

is less than elsewhere, and there is thus a tendency to scour there. If

a regulator is alternately closed and opened, no permanent deposit of

much consequence is likely to occur.

A stream may be made to scour its channel by opening an escape or

branch. This causes a draw in the stream, and an increase in velocity

for a long distance upstream of the bifurcation (_Hydraulics_, CHAP.

VII., _Art. 6_). This procedure is sometimes adopted on irrigation

canals. The escape is generally opened in order to reduce the quantity

of water passing down, but it may be opened solely to induce scour or

prevent silting. The floor of the escape head is usually higher than

the bed of the canal, but this does not interfere with operations

except at low supplies. It may (CHAP. IV., _Art. 2_) have some effect

on the quantity of rolled material passed out of the escape.

If there is a weir in the river below the off-take of the canal, and

if the escape runs back to the river and thus has a good fall, the

scouring action in the canal may be very powerful.

If the main channel has a uniform slope throughout, the slope of its

water surface is greater upstream of the escape than downstream of the

escape, and there is thus an abrupt reduction of velocity and possibly

a deposit of silt in the main channel below the escape. This may or

may not be objectionable. In the case of an irrigation canal, it is

far less objectionable than deposit in the head of the canal. The best

point for the off-take of any escape or scouring channel depends on

the position of the deposits in the main channel. The off-take should

be downstream of the chief deposits, but as near to all of them as

possible. A breach in a bank acts of course in the same way as an

escape.

A stream of clear water when sent down a channel will scour it if the

material is sufficiently soft. In the case of the Sirhind Canal, it has

already been mentioned (CHAP. IV., _Art. 3_), that when the river water

became clear after the floods the proportion of coarse sand, _i.e._

sand above the (·10) class, carried by the canal water was about

1/15,000 by volume. This was in the period from 22nd September to 7th

October. From 8th to 23rd October the proportion averaged 1/32,000 from

24th October to 8th November 1/44,000, and from 9th to 24th November

1/85,000. The reason of this reduction was that the comparatively clear

water kept picking up the sand from the bed and moving it on, the finer

kinds being moved most quickly. As the coarse sand left on the bed

became less in quantity, the water took up less. It appears, however,

that the water also picked up some clay which was left, and that the

total suspended silt in November was 1/9000 of the water. All the

observations mentioned in this paragraph appear to have been made at

Garhi, 26 miles from the head of the canal.

3. =Production of Silt Deposit.=--Works or measures for causing silt

deposit may be undertaken in order to cause silt deposit in specific

places where it will be useful, or in order to free the water from

silt. Sometimes both objects are combined.

If a stream can be turned into a large pond or low ground--a bank being

built round it if necessary--it can be made to part with some or all of

its silt whether rolled or suspended. Even if the pond is so large that

the velocity becomes imperceptible, the whole of the suspended matter

will not deposit unless it has sufficient time, but the matter which

remains in the water is likely to be extremely small in amount. The

silting up of marshes, pools, borrow-pits, etc., is now being effected,

or should be effected, in places where mosquitoes and malaria are

prevalent.

In the upper or torrential part of a stream, a high dam, provided with

a sluice and a high-level waste weir, may be built across it. The space

above the dam becomes more or less filled with gravel, etc. This has

been done in Switzerland (_Min. Proc. Inst. C.E._, vol. clxxi.). In

the U.S.A. long weirs have been built in order to stop the progress of

detritus from gold mines. Such detritus was liable to choke up rivers

and damage the adjoining lands. The detritus from hill torrents can

also be reduced by afforestation of the hill sides.

[Illustration: FIG. 3.]

[Illustration: FIG. 4.]

When a stream is in embankment--irrigation channels are frequently

so--the bank can be set back (fig. 3), and suspended silt will then

deposit on the berms. The object of this arrangement is generally to

create very strong banks in low ground. A similar plan can be adopted

when the berm is only slightly below the water-level and even when it

is only occasionally submerged. In this case the deposit of a small

bank of silt along the edge of the berm next the stream will prevent

the access of fresh supplies of silt-bearing water to the parts further

away. Gaps should be cut in the bank of silt at intervals, and cross

banks made to form “silting tanks,” as shown in fig. 4. The inlets to

the tank should be large, and the outlets small, so that the water in

the tank may have little velocity. It is not, however, correct to have

the outlet so small--unless the water contain very little silt--that

there is very little flow through the tank. The tanks will generally

be silted up most quickly by allowing a good flow through them, even

though only a small proportion of the silt in the water is deposited.

Regular banks arranged to form tanks on the above principle can be made

behind the original banks of a canal in cases where the original banks

were not, for any reason, set back.

When a channel is made in low ground and the excavation is not

sufficient to make the banks, borrow-pits can be dug in the bed of the

channel. Such pits should not be long and continuous, but wide bars

should be left so that a number of short pits will result. These pits

will trap rolled material as well as suspended silt. The object in

this case is to free the water from silt and to reduce the size of the

channel and thus reduce the loss of water from percolation.

On the Indus, where it has a strong tendency to shift westwards, long

earthen dams or groynes are run out from the west bank across the

sandbanks. One object is to cause silt deposit, and so increase the

quantity of material which the river will have to cut away, but whether

this result is achieved is doubtful. The sandbanks receive deposits in

any case. A groyne may increase the deposit on its upstream side, but

it cuts off the flood water from its downstream side and so reduces the

deposit there.

4. =Arrangements at Bifurcations.=--At a bifurcation, as where a branch

takes off from a canal, it is possible to reduce the quantity of rolled

material entering the canal by raising its bed or constructing a

weir or “sill” in its head. This arrangement may have great effect in

excluding boulders, shingle, or gravel. As regards rolled sand, it has

much less effect than might be expected (CHAP. IV., _Art. 2_). If the

canal is reduced in width (fig. 5) there will be eddies below the bed

level of the branch. They will stir up the sand and some of it will

enter the branch. If the canal is not reduced in width, eddies will be

produced in the surface water, and they will affect the bed.

The above remarks apply also to the case of a canal taken off from a

river when there are no works in the river.

[Illustration: FIG. 5.]

[Illustration: FIG. 6.]

5. =A Canal with Headworks in a River.=--In the case of a canal taking

off from a river and provided with complete headworks, it is possible

to do a great deal more. The case of the Sirhind Canal, already

referred to (CHAP. IV., _Arts. 5_ and _6_), is a notable example. The

canal (fig. 6) is more than 200 feet wide, the full depth of water

10 feet, and the full discharge about 7000 cubic feet per second. In

1893 when the irrigation had developed, and it became necessary to run

high supplies in the summer--July, August, and part of September--the

increase in the silt deposit threatened to stop the working of the

canal. In the autumn and winter, say from 25th September to 15th

March, the water entering the canal is clear and much of the deposit

was picked up by it, but not all. In the five years 1893 to 1897

inclusive, the following remedial measures were adopted. Increased

use was made of the escape at the twelfth mile. This did some good,

but there was seldom water to spare. In 1893 to 1894 the sill of the

regulator was raised to 7 feet above the canal bed, and it was possible

to raise it 3 feet more by means of shutters. This had little effect.

The coarsest class of sand was ·4, and the velocity of the water, even

of that part of it which came up from the river bed and passed over

the sill, was over 2 feet per second, so that all sand was carried

over. In 1894 to 1895 the divide wall, which had been only 59 feet

long, was lengthened to 710 feet, so as to make a pond between the

divide wall and the regulator,[8] but probably the leakage through the

under-sluices was often as much as the canal supply, and the water in

the pond was thus kept in rapid movement and full of silt. The canal

was closed in heavy floods. This did some good, but probably the canal

was often closed needlessly when the water looked muddy but contained

no excessive quantity of sand. The above comments on the measures taken

were made by Mr Kennedy when chief engineer. The above measures did

not reduce the silt deposits, but the scour in the clear water season

improved, probably because higher supplies were run owing to increased

irrigation. The deposit in the upper reaches of the canal, when at

its maximum about the end of August of each year, was generally more

than twenty million cubic feet. From the year 1900 a better system

of regulation was enforced, the under-sluices being kept closed as

much as possible, so that there was much less movement in the pond and

much less silt in its water. By 1904 the deposit in the canal had been

reduced to three million cubic feet, and no further trouble occurred.

During the period from 20th September 1908 to 10th October 1908 the

quantity of silt in the canal above Chamkour (twelfth mile) decreased

from 19,325,800 cubic feet to 12,477,600 cubic feet. The quantity

scoured away was 6,848,200 cubic feet. During this period no silt

entered the canal. The quantity which passed out of the reach in

question in suspension was 4,183,660 cubic feet, so that 2,664,540

cubic feet of material must have been rolled along the bed. The rolled

material was 64 per cent. of the suspended material. During this period

the Daher escape, in the twelfth mile, was open, and the mean velocity

in the canal just above the escape was about 4 feet per second, the

depth of water being about 10 feet. The velocity near the escape was

thus greater than the critical velocity for mixed silt (CHAP. IV.,

_Art. 6_), and even a long way up the canal it would be in excess of

the critical velocity. The water seems to have carried about 1/1800

of its volume of silt. Whether the above proportions of rolled to

suspended matter would hold good in a fully charged stream flowing with

the critical velocity it is not easy to say.

As silt deposits in the pond, the velocity of the water in it, along

the course of the main current towards the canal, increases and

eventually the water begins to carry coarse sand dangerous for the

canal. In order to ascertain when this state of affairs has been

reached, two methods of procedure are possible. One is to frequently

test specimens of the water in the pond along the course of the main

current and see when it contains more than 1/15,000 of its volume of

coarse sand. This plan would be troublesome and liable to error, and

is rejected by Kennedy, who suggests that the depth and velocity of

the water in the pond be frequently observed along the course of the

main current. As soon as the velocity exceeds the critical velocity for

mixed silt, it is time to close the canal and open the under-sluices

and scour out the deposit from the pond. The period in which most silt

is believed to have been deposited in the canal is the spring and early

summer, say from 15th March to 1st July. This is the time when the

snows are melting and the river water is clear. It can then carry more

sand than in the rains--1st July to 15th September,--when it is muddy.

Kennedy also suggests that some under-sluices should be provided at

the far side of the river, _i.e._ at the right-hand side of the weir.

It would then be possible, by opening them, to let floods pass without

interfering with the pond.

The two spurs or groynes, shown in the plan, were constructed in 1897

so as to cause the stream to flow along the face of the canal regulator

and not allow deposits to accumulate there. The depth of silt deposited

in a great part of the pond amounted at times to 8 or 10 feet.

6. =Protection of the Bed.=--It is possible to afford direct protection

from scour to the bed of a stream by constructing walls across it,

but unless the walls are near together the protection will not be

effective. An arrangement used in some streams in Switzerland consists

of tree trunks secured by short piles and resting on brushwood. But

as long as the walls are not raised above the bed they cannot entirely

stop scour, unless extremely close together. If raised above the bed

they form a series of weirs.

The weirs must be so designed that the depth of water in a reach

between two weirs is great enough to reduce the velocity down to the

critical velocity, or less. The fall in the water surface at each

weir being very small, the discharge over the weir can be found by

considering it as an orifice extending up to the downstream water

surface, and the head being the fall in the surface at the weir.

To stop scour of the bed by direct protection without raising the

water-level, the bed can be paved, a plan adopted in artificial

channels with very high velocities. The paving can be of stones,

bricks, or concrete blocks. The Villa system of protection, which has

been used in Italy, France, and Spain, consists of a flexible covering

laid on the bed. Prisms of burnt clay or cement are strung on several

parallel galvanized iron wires, which are attached to cross-bars so as

to form a grid a few feet square. The grids are loosely connected to

one another at the corners, and the whole covering adjusts itself to

the irregularities of the bed (_Min. Proc. Inst. C.E._, vol. cxlvii.).

The special protection or paving required in connection with weirs and

such-like works is considered in CHAP. X., _Arts. 2_ and _3_.