I. ENGINEERING FEATURES.

[Sidenote: Engineering details of the new route.]

The proposed line will leave the West Coast Branch at a point six miles

south of Snohomish City, running east, crossing the Snohomish River on

drawbridge at the junction of the Snoqualmie and Skykomish rivers:

thence up the right bank of Skykomish on a 1 per cent. (52.8 feet per

mile) grade, a distance of forty miles from point of beginning.

Thirty-five miles of 2 per cent. (105.6 feet per mile) grade carries the

line to Cady's Pass and mouth of tunnel. The tunnel will be 3,500 feet

long, in granite rock; probably little or no lining will be necessary.

Descending to the east by a 2 per cent. grade, following the Wenatchie

River, a distance of twenty miles. Descending and level grades alternate

for the next twenty-five miles, where 1,000 feet of tunneling will be

required in the divide between the Wenatchie and Chumstick rivers. This

tunnel saves eight miles of distance in the following eighteen miles,

and avoids entering the box cañon of the Wenatchie, a difficult and

expensive piece of work.

The development in the Chumstick valley is especially easy. Thence into

the Wenatchie valley again, on a 1 per cent. grade, a distance of

twenty-seven miles, to the mouth of the Wenatchie River.

A summary of the distances and grades shows a very prettily balanced

scheme for operating cheaply and effectively.