COST OF 100 SQUARE YARDS OF THREE-COAT PLASTERING

_Scratch Coat_

6 bushels of lime, at 25 cents per bushel $ 1.50

9 pounds of hair, at 4 cents per pound .36

¾ cubic yard of sand, at $1.50 per cubic yard 1.13

5 hours, plasterer’s time, at 50 cents per hour 2.50

5 hours, laborer’s time, at 25 cents per hour 1.25

-------

Total $ 6.74

_Brown Coat_

6 bushels of lime, at 25 cents per bushel $ 1.50

3 pounds of hair, at 4 cents per pound .12

1 cubic yard of sand, at $1.50 per cubic yard 1.50

13 hours, plasterer’s time, at 50 cents per hour 6.50

6½ hours, laborer’s time, at 25 cents per hour 1.63

------

Total $11.25

_Finishing Coat_

3½ bushels of finishing lime, at 35 cents per

bushel $ 1.23

½ barrel of plaster of Paris, at $1.75 per barrel .88

⅜ bushel of white sand, at 27 cents per bushel .10

18 hours, plasterer’s time, at 50 cents per hour 9.00

4½ hours, laborer’s time, at 25 cents per hour 1.13

------

Total $12.34

The total cost of 100 square yards of three-coat plaster, then, is

$30.33, or about 31 cents per yard.