ESTIMATING BRICKWORK

=36.= The following figures and method of estimating brickwork were

supplied by an estimator of a large eastern contractor. The prices

given include office expense and builder’s profit. The wages per hour

on which these figures are based are: Bricklayers, 65 cents; hod

carriers, 25 cents; and common laborers, 18 cents.

Following are mentioned four distinct classes of brick buildings, and

in Table IV are given the labor prices per thousand brick for the

various stories of buildings of these classes.