DATA ON RUBBLE MASONRY

=24.= The following proportions and cost of materials and amount

of labor required to lay 1 perch of rubble masonry are reasonably

accurate, and will serve to give an idea of how to estimate such work.

A perch of rubble masonry requires, approximately, 2,500 pounds of

stone.

COST OF RUBBLE MASONRY

_Using 1-to-3 Lime Mortar_

1 perch of stone (25 cubic ft.) delivered at work $1.25

1 bushel of lime .25

⅙ cubic yard of sand, at $1.50 per cubic yard .25

½ day, mason’s labor, at $3.20 per day 1.60

¼ day, helper’s labor, at $2 per day .50

-----

Total $3.85

_Using 1-to-3 Portland-Cement Mortar_

1 perch of stone $1.25

¾ barrel of Portland cement, at $2 per barrel 1.50

¼ cubic yard of sand, at $1.50 per cubic yard .38

½ day, mason’s labor, at $3.20 per day 1.60

¼ day, helper’s labor, at $2 per day .50

-----

Total $5.23

To the preceding amounts should be added the cost of scaffolding and

the builder’s profit. If the walls are over two stories in height, 60

cents per perch extra for hoisting should be added.

Hardware, estimating, and mill design · 第 94 / 194 题