CEMENT CELLAR FLOORS

=20.= In determining the cost of =cement cellar floors=, the concrete

proper and the top coat should be considered separately. The concrete

proper is usually reckoned by the cubic yard. About 1 hour more is

required to lay a cubic yard of floor than is necessary for plain

concrete work. Therefore, in estimating, 25 cents per cubic yard, or

the wages of a laborer for 1 hour, must be added to the figures given

in Table II. A 1-3-6 mixture is generally used. For stone concrete,

then, the cost of the concrete proper for a cement cellar floor would

be $5.17 per cubic yard, exclusive of the cost of supervision and the

builder’s profit.

An analysis of the cost per square yard of top coat 1 inch thick for a

cement cellar floor is as follows:

Cost

Cents

¼ hour, plasterer’s time, at 45 cents per hour 11¼

¼ hour, laborer’s time, at 25 cents per hour 6¼

¹/₁₅ barrel of cement, at $2 per barrel 13⅓

⅛ barrel of white sand, at 75 cents per barrel 9⅜

------

Approximate cost per square yard 40

To the foregoing should be added the cost of supervision and builder’s

profit.