SCHEDULES AND DRAWINGS FOR THE HARDWARE CONTRACTOR

=157. Hardware Schedules.=—The contractor for the hardware usually

takes off his own bill of material from the general drawings and the

specifications furnished by the architect. However, the architect will

sometimes supply the hardware schedule and obtain prices for the same

direct from the dealer, thus saving the owner the general contractor’s

profit and insuring bids based on material of uniform character and

quality. It is well, therefore, to give some thought to the preparation

of the schedule, so as to insure a good classification and to avoid

omissions.

In drafting a schedule of hardware required for a building, it must be

compiled from a copy of the hardware specifications and a list of all

openings, cabinets, etc. that has been taken from the drawings. The

schedule should be subdivided primarily into building sections, such as

_first floor_, _second floor_, etc. as headings. Under these headings,

each opening or group of openings in each room or division should be

listed. Under the name of each opening or series of openings should be

grouped all the hardware required, itemizing each and every article

necessary and stating the quantity, numbers, sizes, or dimensions,

design, and finish.

Schedules thus prepared are readily priced for estimating, and such

classification eliminates the possibilities of omissions. Besides, the

order can be executed by the manufacturer in exact conformity with

the instructions, the hardware for each opening can be combined in a

separate package, and each package clearly labeled to indicate its

contents and the room or opening to which it belongs. The following

shows a typical form of schedule: