SELECTION, ESTIMATION, AND APPLICATION OF HARDWARE

=143.= No other material entering into the construction of a building

will pay a larger return in satisfaction, comfort, and permanent

economy for the time and care devoted to its selection than the

finishing hardware. The range of choice and quality has become too

great for the selection to be left to the general contractor under an

omnibus specification, and the practice of according to it the benefit

of careful and discriminating selection by the architect or client, or

both in consultation, is rapidly becoming general. Hardware has become

a factor of utmost importance in the interior decorative scheme of the

modern building, and its selection demands at least the care accorded

to other elements of interior decoration.

The method that should be employed in the selection and purchase of

hardware depends primarily on the existing conditions. If the building

is intended for the purpose of sale or renting, or if cheapness is

the dominating factor, then a competitive method may be expedient;

but if the client intends it for personal occupancy or for permanent

ownership, then competitive bidding is sometimes not productive of the

best results.

In all cases, a preliminary examination should be made of the makes

and grades of the commercial hardware available, and the amount that

it is desired to expend on this item should be decided on. The process

of selection is greatly facilitated by the elimination of articles

outside of the grades selected. When the maker’s grade of goods has

been decided on, the next step is to select in detail the articles,

designs, and finishes to be used in each room, floor, or division of

the building, making such notes of the decisions so reached as will be

convenient in framing the hardware specification, or schedule.

=144. Allowance for Finishing Hardware.=—Architects are constantly

called on to prepare preliminary estimates on proposed buildings, to

assist clients to determine whether they can afford to build. For

this purpose, the architect possesses an approximate knowledge of the

cost of excavation, masonry, woodwork, etc., so that the necessary

expenditure may be computed with a fair degree of accuracy. Builders’

hardware, however, does not readily admit of accurate preliminary

estimating, and in many cases the architect merely specifies the sum

to be expended for finishing hardware, stating that selections are to

be made by himself or his client later, as the work progresses. This

system is found in many instances to be satisfactory to all—architect,

client, and builder.

The cost of the hardware usually bears a fairly constant ratio to

the total cost of various types of buildings. The following figures,

which are based on experience, indicate the range in this ratio under

ordinary conditions. This schedule gives the ratio of cost of finishing

hardware to the total cost of the building, land excluded.

Hardware, estimating, and mill design · 第 41 / 194 题