LIABILITIES OF RAILWAY ENGINEERS FOR THEIR ERRORS.

An action was tried before Mr. Justice Maule, July 30, 1846—the first

case of the kind—which established the liability of railway engineers for

the consequences of any errors they commit.

The action was brought by the Dudley and Madeley Company against Mr.

Giles, the engineer. They had paid him £4,000 for the preparation of the

plans, etc., but when the time arrived for depositing them with the Board

of Trade they were not completely ready. The scheme had consequently

failed. This conduct of the defendant it was estimated had injured the

company to the extent of £40,000. The counsel for the plaintiff did not

claim damages to this amount, but would be content with such a sum as the

jury should, under the circumstances, think the defendant ought to pay,

as a penalty for the negligence of which he had been guilty. For Mr.

Giles, it was contended, that the jury ought not, at the worst, to find a

verdict for more than £1,700, alleging that the remainder £2,300 had been

paid by him in wages for work done, and materials used.

The jury, however, returned a verdict to the tune of £4,500, or £500

beyond the full sum paid him.

But, what said the judge? That “it was clear that the defendant had

undertaken more work than he could complete, and that he should not be

allowed to gratify with impunity, and to the injury of the plaintiffs,

his desire to realise in a few months a fortune which should only be the

result of the labour of years.”